BLD-Final | 7/24/2014 | 7/24/2014 | 7/24/2014 | P | PASS |
Jim Sly
|
|
|
Troy Phone #: ###-####
|
DOC - Permit Finaled | 7/24/2014 | 7/24/2014 | 7/24/2014 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 5/16/2014 | 5/16/2014 | 5/17/2014 | P | PASS |
Jim Sly
|
|
|
travis Phone #: ###-####
|
BLD-Framing/Rough-in | 5/16/2014 | 5/16/2014 | 5/17/2014 | P | PASS |
Jim Sly
|
|
|
travis Phone #: ###-####
|
BLD-Framing/Rough-in | 5/13/2014 | 5/14/2014 | 5/14/2014 | A | PASS |
Jim Sly
|
|
|
Troy Phone #: ###-####
|
BLD-Framing/Rough-in | 5/12/2014 | 5/13/2014 | 5/13/2014 | A | PASS |
Jim Sly
|
|
|
troy Phone #: ###-####
|
BLD-Footing | 2/18/2014 | 2/18/2014 | 2/18/2014 | P | PASS |
Jim Sly
|
|
|
building is on the South end // Travis Phone #: ###-####
|
BLD-Footing | 12/2/2013 | 12/2/2013 | 12/2/2013 | P | PASS |
Jim Sly
|
|
|
Travis Phone #: ###-####
|
BLD-Footing | 11/27/2013 | 11/27/2013 | 11/27/2013 | P | FAIL |
Mike Jordan
|
|
|
Travis Phone #: ###-####. No city approved plans on site.
|
BLD-Footing | 11/26/2013 | 11/27/2013 | 11/27/2013 | A | NR |
Mike Jordan
|
|
|
Travis Phone #: ###-####. Footing subgrade and forms were not blanketed overnite. noted frozen conditions. ACI 306 cold weather conrete standard shall be utilized. No concrete to be placed in am. contractor to reschedule inspection for this afternoon.
|
Issue PAID IN FULL permit | | | 11/22/2013 | | DONE |
Christina Prado
|
|
|
|
Extend Review Timeline | | | 11/5/2013 | | DONE |
Christina Prado
|
|
|
extension approved - see approval letter in docs
|
Expiration Notice | 10/24/2013 | 11/15/2013 | 10/24/2013 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 7/24/2013 | | |
|
|
|
|
Plan assigned to (CDM) | 6/6/2013 | 6/6/2013 | 7/24/2013 | | PASS |
Carl D Madsen
|
|
|
ePlan review
|
Routing - PLANNING | 7/24/2013 | | 7/24/2013 | | PASS |
Joshua Johnson
|
|
|
|
Inspection Record Card- Bld | | | 7/24/2013 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 7/24/2013 | | 7/24/2013 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/24/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/24/2013 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 6/6/2013 | | 6/10/2013 | | FAIL |
Carl D Madsen
|
|
|
ePlan review
These plans until revisions are made to the condo platt as these plans do not match the current condo platt. 6-10-13 CDM
|
Routing - MECHANICAL | 6/6/2013 | | 6/10/2013 | | PASS |
Troy James
|
|
|
eplan
|
Route to Impact Fee Review | 6/6/2013 | 6/11/2013 | 6/7/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PUBLIC WORKS | 6/6/2013 | | 6/7/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/6/2013 | | DONE |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/6/2013 | | DONE |
Christina Prado
|
|
|
|
1st review completed | | | 6/6/2013 | | DONE |
|
|
|
|
Routing - Addressing | 6/6/2013 | | 6/6/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Payment Received | | | 6/5/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Intake Approval | | | 5/29/2013 | | PASS |
Christina Prado
|
|
|
|
Intake Approval | | | 5/23/2013 | | FAIL |
Rita DeYoung
|
|
|
Per ePlan review
|
Application received | | | 5/17/2013 | | DONE |
|
|
|
Application submitted via PDS Online on May 17 2013 2:09PM
|