Third Notice | | 3/5/2014 | 4/18/2014 | | DONE |
Tisha Gallop
|
|
|
credit given for value pulled on interior demo permit Bld13-00790
|
Third Notice | | 2/3/2014 | 2/28/2014 | | DONE |
|
|
|
mailed
|
Second Notice | | 1/3/2014 | 1/29/2014 | | DONE |
|
|
|
|
First Notice | | 12/23/2013 | 12/24/2013 | | DONE |
Christina Prado
|
|
|
mailed 12-26-13
|
Permanent Occupancy | | | 12/13/2013 | | DONE |
|
|
|
|
BLD-Final | 12/11/2013 | 12/12/2013 | 12/12/2013 | A | PASS |
Jim Storey
|
|
|
Trent phone #: ###-####
|
FIRE-Final Inspection | 12/10/2013 | 12/11/2013 | 12/11/2013 | P | PASS |
Forrest France
|
|
|
Fire life safety passed pending repair of non-functional door hardware at the bid room per discussion.
|
BLD-Final | 10/9/2013 | 10/9/2013 | 10/9/2013 | P | PART |
Jim Storey
|
|
|
Steve Phone #: ###-####
|
BLD-Framing/Rough-in | 7/25/2013 | 7/26/2013 | 7/26/2013 | A | PASS |
Jim Storey
|
|
|
Steve Phone #: ###-#### frame ok need stair enclosers seal be for ceillings
|
FIRE-Conference | 7/2/2013 | 7/2/2013 | 7/2/2013 | A | DONE |
Forrest France
|
|
|
On site conference with contractor regarding project related FIR trade work, fire life safety conditions, etc.
|
Permit Ready to Issue | | | 6/13/2013 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 6/13/2013 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 6/13/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/11/2013 | | 6/11/2013 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/11/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 5/23/2013 | | 6/11/2013 | | PASS |
Tim L. Woodard
|
|
|
1st Review Completed. TLW
|
Plan resubmittals received | | | 6/10/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 6/10/2013 | | 6/10/2013 | | FAIL |
Tim L. Woodard
|
|
|
Need to address change marks on drawings. TLW
|
Routing - PLAN CHECK | 5/23/2013 | | 6/5/2013 | | FAIL |
Tim L. Woodard
|
|
|
Refer to change marks in E-plan. TLW
|
Routing - PUBLIC WORKS | 5/23/2013 | | 6/5/2013 | | PASS |
Connie Baumgartner
|
|
|
Approved in E-plan review. TLW
|
1st review completed | | | 6/5/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - FIRE | 5/23/2013 | | 5/31/2013 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing - Addressing | 5/23/2013 | | 5/24/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Intake Approval | | | 5/23/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Payment Received | | | 5/22/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/20/2013 | | DONE |
|
|
|
Application submitted via PDS Online on May 20 2013 2:06PM
|