First Notice | | 6/15/2014 | 6/10/2014 | | DONE |
|
|
|
This permit finaled on the web by Mike McHargue
|
Zoning Approval | 6/5/2014 | 6/5/2014 | 6/5/2014 | | PASS |
Josh Wilson
|
|
|
|
Permanent Occupancy | | | 6/5/2014 | | DONE |
Christina Prado
|
|
|
|
Temporary Occupancy | 4/23/2014 | 7/22/2014 | 4/23/2014 | | DONE |
Barbara Stitt
|
|
|
Temp occupancy extension granted for 60 days per Jason Blais-see scanned documents
|
BLD-Final | 2/27/2014 | 2/28/2014 | 2/28/2014 | A | PASS |
Tom Arcoraci
|
|
|
The hand rail height problem has been corrected Phone #: ###-#### >> Inspection requested via web by Mike McHargue
|
Temporary Occupancy | 2/28/2014 | 5/29/2014 | 2/28/2014 | | DONE |
Tisha Gallop
|
|
|
180 temp per Josh Wilson per landscaping bond in place
|
BLD-Final | 2/27/2014 | 2/27/2014 | 2/27/2014 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Final | 2/26/2014 | 2/27/2014 | 2/27/2014 | A | FAIL |
Mike Jordan
|
|
|
bld15 final Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Provide code compliant handrail. Everything else ok.
|
FIRE-Final Inspection | 2/26/2014 | 2/26/2014 | 2/26/2014 | P | PASS |
Troy Cobbley
|
|
|
Life Safety Passed
|
Case Summary (BLD) | | | 1/24/2014 | | DONE |
|
|
|
|
Zoning Approval Temp | 1/17/2014 | 1/17/2014 | 1/17/2014 | | PASS |
Josh Wilson
|
|
|
180 day for landscaping. Bond in place.
|
BLD-Wall cover | 11/25/2013 | 11/26/2013 | 11/26/2013 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mike McHargue. 1st and 2nd. floor north and south units, firestopping, and shearwalls ok. central units, 2nd. floor only.
|
BLD-Wall cover | 11/15/2013 | 11/15/2013 | 11/15/2013 | A | PASS |
Mike Jordan
|
|
|
first floor Phone #: ###-#### >> Inspection requested via web by Mike McHargue. All remaining units ok to cover.
|
BLD-Wall cover | 11/13/2013 | 11/14/2013 | 11/14/2013 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Work in progress on remaining units, 1st and 2nd layers on 1st floor central units and south units ok.
|
BLD-Wall cover | 11/11/2013 | 11/12/2013 | 11/12/2013 | A | PASS |
Mike Jordan
|
|
|
fire caulking / framing Phone #: ###-#### >> Inspection requested via web by Mike McHargue. 2nd. floor center units and south units ok to cover. ok for 2nd layer on ceiling at first floor center and south units.
|
BLD-Wall cover | 11/7/2013 | 11/8/2013 | 11/8/2013 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mike McHargue. 1st and 2nd floor north end units ok for tape. 3rd floor central units ok for tape.
|
BLD-Wall cover | 11/7/2013 | 11/7/2013 | 11/7/2013 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mike McHargue. work in progress.
|
BLD-Wall cover | 11/6/2013 | 11/6/2013 | 11/6/2013 | P | PART |
Mike Jordan
|
|
|
Drywall screws Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Work in progress on on interior shearwalls and party walls. No new units ready.
|
BLD-Wall cover | 11/5/2013 | 11/5/2013 | 11/5/2013 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mike McHargue. North units, 2nd. floor 1st. layer ok.
|
BLD-Wall cover | 11/4/2013 | 11/4/2013 | 11/4/2013 | P | PART |
Mike Jordan
|
|
|
Screw inspection Phone #: ###-#### >> Inspection requested via web by Mike McHargue. 3rd floor, North and south end units, interior shear walls, party walls and corridor walls ok. All firestopping completed. Ok to tape and cover.
|
BLD-Energy code compliance | 10/29/2013 | 10/29/2013 | 10/29/2013 | P | PASS |
Mike Jordan
|
|
|
Insulation Phone #: ###-#### >> Inspection requested via web by Mike McHargue
|
BLD-Energy code compliance | 10/28/2013 | 10/29/2013 | 10/29/2013 | A | NR |
Mike Jordan
|
|
|
Insulation Phone #: ###-#### >> Inspection requested via web by Mike McHargue
|
BLD-Energy code compliance | 10/25/2013 | 10/28/2013 | 10/28/2013 | A | NR |
Mike Jordan
|
|
|
Insulation Phone #: ###-#### >> Inspection requested via web by Mike McHargue
|
BLD-Energy code compliance | 10/24/2013 | 10/24/2013 | 10/24/2013 | P | PASS |
Mike Jordan
|
|
|
Air Seal Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Airseal has been completed.
|
BLD-Framing/Rough-in | 10/24/2013 | 10/24/2013 | 10/24/2013 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mike McHargueok to insulate 1st. 2nd. and 3rd. floors. All firestopping completred. fireblock at 3rdfloor ceiling behind tubs. Provide additional 5/8 type x sheet rock at chases, 2nd. floor vent fans. Add straps at double top plate splices in same spot.
|
FIRE-Sprinkler Rough-in | 10/23/2013 | 10/23/2013 | 10/23/2013 | P | PASS |
Troy Cobbley
|
|
|
Tenting in attic space is approved. Piping can be covered.
|
BLD-Conference | 10/22/2013 | 10/22/2013 | 10/22/2013 | P | DONE |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mike McHargue
|
BLD-Wall cover | 10/18/2013 | 10/21/2013 | 10/21/2013 | P | CANC |
Mike Jordan
|
|
|
Fire Caulking Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Inspection done in the am.
|
BLD-Framing/Rough-in | 10/18/2013 | 10/21/2013 | 10/21/2013 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Walk through on 1st. floor only. Work in progress on firestopping. All trades not yet inspected. No cover at this time.
|
BLD-Wall Bracing | 9/10/2013 | 9/10/2013 | 9/10/2013 | A | PASS |
Mike Jordan
|
|
|
Sheer Phone #: ###-#### >> Inspection requested via web by Mike McHargue. 1st, 2nd and 3rd floor exterior shearwalls ok. ok to cover exterior of building.
|
BLD-Wall Bracing | 9/9/2013 | 9/9/2013 | 9/9/2013 | P | FAIL |
Mike Jordan
|
|
|
Exterior Sheer Phone #: ###-#### >> Inspection requested via web by Mike McHargu. All floor to floor straps on exterior sheathing installed. Noted several areas were nailing was missing or needs to be tightened up.
|
BLD-Wall Bracing | 8/26/2013 | 8/26/2013 | 8/26/2013 | A | FAIL |
Mike Jordan
|
|
|
First two floors of building 15 sheer / straps / hold downs. Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Several areas missing nailing and holdowns need to be tightened down.
|
Permit Ready to Issue | | | 7/26/2013 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 7/26/2013 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/26/2013 | | DONE |
|
|
|
|
Routing PW Sewer Design | 7/3/2013 | | 7/3/2013 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - FIRE | 6/28/2013 | 6/28/2013 | 6/28/2013 | | PASS |
Tim Frost
|
|
|
|
Plan assigned to (SRZ) | 5/24/2013 | 5/24/2013 | 6/28/2013 | | PASS |
Sam Zahorka
|
|
|
1st review completed. ePlanReview - Union Square Bldg #15
|
Routing - PLAN CHECK | 6/28/2013 | | 6/28/2013 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/28/2013 | | DONE |
Sam Zahorka
|
|
|
|
Routing PW Solid Waste | 5/28/2013 | | 6/28/2013 | | PASS |
Peter J. McCullough
|
|
|
Signed off PASS in ePlan Review.
|
Routing - PLAN CHECK | 6/24/2013 | | 6/28/2013 | | PASS |
Sam Zahorka
|
|
|
|
Routing - PUBLIC WORKS | 6/28/2013 | | 6/28/2013 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Street Lights | 6/27/2013 | | 6/27/2013 | | PASS |
Mike D Hedge
|
|
|
|
Routing - FIRE | 6/24/2013 | 6/24/2013 | 6/24/2013 | | FAIL |
Tim Frost
|
|
|
|
Routing - PLUMBING | 6/24/2013 | | 6/24/2013 | | PASS |
Bill VanDegrift
|
|
|
see bld13-01288 for review comments
|
Routing - PLAN CHECK | 6/21/2013 | | 6/21/2013 | | PEND |
Sam Zahorka
|
|
|
Pending Plumbing, Fire, Public Works, Street lights, and Sewer Design to PASS prior to issuance.
|
Routing Off Site - STRUCTURAL | 6/21/2013 | | 6/21/2013 | | PASS |
Sam Zahorka
|
|
|
|
1st review completed | | | 6/17/2013 | | DONE |
Sam Zahorka
|
|
|
|
Routing PW Street Lights | 5/28/2013 | | 6/17/2013 | | FAIL |
Mike D Hedge
|
|
|
Signed off FAIL (PW Sewer Design, Street Lights) in ePlanReview
|
Routing PW Sewer Design | 5/28/2013 | | 6/17/2013 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Signed off FAIL (PW Sewer Design, Street Lights) in ePlanReview
|
Routing - PLAN CHECK | 5/24/2013 | | 6/17/2013 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - PLANNING Land Div | 5/24/2013 | | 6/17/2013 | | PASS |
Dave Abo
|
|
|
Signed off PASS in ePlanReview
|
Routing - Erosion and Sediment | 5/24/2013 | | 6/17/2013 | | FAIL |
Kimberly M. Johnson
|
|
|
Signed off FAIL in ePlanReview
|
Routing PW Drainage | 5/28/2013 | | 6/12/2013 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLANNING | 5/24/2013 | | 6/6/2013 | | PASS |
Susan Riggs
|
|
|
Susan Riggs - CUP12-00064
|
Route to Impact Fee Review | 5/24/2013 | 5/30/2013 | 6/5/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing Off Site - STRUCTURAL | 5/24/2013 | | 6/3/2013 | | FAIL |
Ron Hill
|
|
|
Sent comments to Billy Edwards architect.
|
Routing - Erosion and Sediment | 6/3/2013 | | 6/3/2013 | | PASS |
Kimberly M. Johnson
|
|
|
|
Routing - PLUMBING | 5/24/2013 | | 5/31/2013 | | FAIL |
Bill VanDegrift
|
|
|
see bld13-01288 for review comments
|
Routing - MECHANICAL | 5/24/2013 | | 5/30/2013 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 5/24/2013 | | 5/29/2013 | | FAIL |
Scott Arellano
|
|
|
Attached report to case and emailed report to architect.
|
Routing - Addressing | 5/24/2013 | | 5/28/2013 | | PASS |
Jason C. Taylor
|
|
|
New addresses have been added to the buildings with correct apartment numbers. Please see uploaded sheets in Project Dox. Jason Taylor ###-####.
|
Routing - PUBLIC WORKS | 5/24/2013 | | 5/28/2013 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Design Review | 5/24/2013 | | 5/28/2013 | | PASS |
Josh Wilson
|
|
|
Josh Wilson - DRH13-00005
|
Routing PW Sewer Rating | 5/28/2013 | | 5/28/2013 | | PASS |
Beverly Mountain
|
|
|
|
Pending Assignment by JCB | 5/24/2013 | | 5/24/2013 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 5/23/2013 | | PASS |
Sam Zahorka
|
|
|
|
Application received | | | 5/21/2013 | | DONE |
|
|
|
Application submitted via PDS Online on May 21 2013 4:17PM
|