First Notice | 8/12/2013 | 8/12/2013 | 6/10/2014 | | DONE |
Mike Jordan
|
|
|
This permit finaled on the web by Mike McHargue
|
BLD-Conference | 8/12/2013 | 8/12/2013 | 8/12/2013 | P | PASS |
Mike Jordan
|
|
|
Final foundation permit over to building permit Phone #: ###-#### >> Inspection requested via web by Mike McHargue
|
DOC - Permit Finaled | 8/12/2013 | 8/12/2013 | 8/12/2013 | P | PASS |
Mike Jordan
|
|
|
Foundation only permit, a building permit has been issued.
|
BLD-Concrete | 7/16/2013 | 7/16/2013 | 7/16/2013 | P | PASS |
Jim Sly
|
|
|
East side of building 14 interior thickend slab footing. Phone #: ###-#### >> Inspection requested via web by Mike McHargue
|
BLD-Concrete | 7/15/2013 | 7/15/2013 | 7/15/2013 | P | PASS |
Tom Arcoraci
|
|
|
West slab and breezeways base prep and thickend footings. Phone #: ###-#### >> Inspection requested via web by Mike McHargue
|
BLD-Conference | 7/10/2013 | 7/10/2013 | 7/10/2013 | A | DONE |
Mike Jordan
|
|
|
Bld conference with framer. 10 AM. Phone #: ###-#### >> Inspection requested via web by Mike McHargue
|
BLD-Energy code compliance | 7/8/2013 | 7/8/2013 | 7/8/2013 | P | PASS |
Mike Jordan
|
|
|
foundation insulation Phone #: ###-#### >> Inspection requested via web by Mike McHargue. R-10 rigid insulation and thermal break on interior side of stemwall under slab on grade.
|
BLD-Energy code compliance | 7/8/2013 | 7/8/2013 | 7/8/2013 | A | FAIL |
Mike Jordan
|
|
|
Foundation Insulation Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Provide 24 inches of R-10 rigid insulation and the required thermal break.
|
BLD-Foundation | 7/1/2013 | 7/1/2013 | 7/1/2013 | P | PASS |
Mike Jordan
|
|
|
After 2pm for east end of the building stem wall rebar inspection. Phone #: ###-#### >> Inspection requested via web by Mike McHargue. est half ok.
|
BLD-Foundation | 6/27/2013 | 6/28/2013 | 6/28/2013 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Mike McHargue. Stemwall, west half only.
|
BLD-Conference | 6/25/2013 | 6/25/2013 | 6/25/2013 | P | DONE |
Mike Jordan
|
|
|
BLD13-01292 1391 S GOLDKING WAY Phone #: ###-#### >> Inspection requested via web by Mike McHargue
|
BLD-Footing | 6/24/2013 | 6/25/2013 | 6/25/2013 | A | PASS |
Jim Sly
|
|
|
Mike, building 14 footing/rebar inspection. Phone #: ###-#### >> Inspection requested via web by Mike McHargue Verbal From Bob Arnold Sub Grade OK.
|
BLD-Conference | 6/20/2013 | 6/20/2013 | 6/20/2013 | P | CANC |
Mike Jordan
|
|
|
Michael Phone #: ###-####. Wrong permit called in. contractor wanted to place footings for bldg. 16, garage. that permit is still under review. No concrete at this time.
|
Permit Ready to Issue | | | 6/5/2013 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 6/5/2013 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 6/5/2013 | | DONE |
Tisha Gallop
|
|
|
|
(F) Reprint permit | | | 6/5/2013 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 6/5/2013 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (SRZ) | 5/24/2013 | 5/24/2013 | 6/3/2013 | | PASS |
Sam Zahorka
|
|
|
ePlanReview - Union Square Bldg #14 Foundation
|
Routing - PLAN CHECK | 5/24/2013 | | 6/3/2013 | | PASS |
Sam Zahorka
|
|
|
|
1st review completed | | | 6/3/2013 | | DONE |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/3/2013 | | DONE |
Sam Zahorka
|
|
|
|
Pending Assignment by JCB | 5/24/2013 | | 5/24/2013 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 5/23/2013 | | PASS |
Sam Zahorka
|
|
|
|
Application received | | | 5/21/2013 | | DONE |
|
|
|
Application submitted via PDS Online on May 21 2013 4:17PM
|