Second Notice | | 10/11/2013 | 10/4/2013 | | DONE |
Christina Prado
|
|
|
complete 10-04-2013
|
First Notice | | 9/6/2013 | 10/1/2013 | | DONE |
Christina Prado
|
|
|
mailed 10-2-13
|
Permanent Occupancy | | | 8/27/2013 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 8/26/2013 | 8/26/2013 | 8/26/2013 | P | PASS |
Dave Hannah
|
|
|
Zack Phone #: ###-####
|
BLD-Framing/Rough-in | 8/15/2013 | 8/15/2013 | 8/15/2013 | P | PASS |
Dave Hannah
|
|
|
Zack-ceiling grid inspection please Phone #: ###-####
|
FIRE-Final Inspection | 8/15/2013 | 8/15/2013 | 8/15/2013 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Contractor to provide correct address prior to building sign off.
|
Override - Condition Holds | 8/15/2013 | 1/1/1900 | 8/15/2013 | | |
|
|
|
Not final inspection
|
Override - Condition Holds | 8/15/2013 | 1/1/1900 | 8/15/2013 | | |
|
|
|
not final occ inspection
|
BLD-Framing/Rough-in | 7/9/2013 | 7/10/2013 | 7/11/2013 | A | PASS |
Dave Hannah
|
|
|
derek Phone #: ###-####
|
Override - Parcel Holds | | | 7/5/2013 | | |
|
|
|
|
Permit Ready to Issue | | | 7/5/2013 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 7/5/2013 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 7/5/2013 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (AJS) | 5/30/2013 | 5/30/2013 | 6/25/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 6/5 Level 1 TI e plan
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/25/2013 | | DONE |
|
|
|
|
Routing - Addressing | 6/20/2013 | | 6/20/2013 | | PASS |
Jason C. Taylor
|
|
|
Address was changed to 855 Broad St Suite 100 to keep tenants in the correct order.
|
Telephone call | | | 6/14/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
spoke with Derik, he is comming in for an early start permit as they need to take care of the addressing issue.
|
Routing - Addressing | 6/11/2013 | | 6/14/2013 | | FAIL |
Jason C. Taylor
|
|
|
Below ground suites must be two digits (Suite 10-90) 101-190 are reserved for above ground tenants. Suites must be renamed to reflect correct addressing. Jason Taylor ###-####.
|
Routing - PLAN CHECK | 6/11/2013 | | 6/11/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 5/30/2013 | | 6/5/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see change marks in e plan review
|
1st review completed | | | 6/5/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Intake Approval | | | 5/30/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 5/21/2013 | | DONE |
|
|
|
Application submitted via PDS Online on May 21 2013 7:21PM
|