Permit Information
Permit NumberBLD13-01309
StatusIssued
Name EKC INC
Site Address 720 E PARK BLVD Unit: 100
Project NameMk Plaza II
Customer Number 
ePlanReviewYes
Description
(Health Management Systems Suite 100) his project consists of construction of a new tenant demising wall to downsize the existing Health Management Systems Tenant Space (Suite 100) to 5,283 s.f. and to create a new 1,646 s.f. vanilla finish tenant space(Suite 104) (BLD13-01523) on the first floor of Plaza II. Work includes minor demolition, construction of non-load bearing walls and a new doorway into Suite 104, patch and repair of existing finishes, mechanical and electrical modifications to support the new tenant layouts. Interior finishes shall be in compliance with chapter 8 of the 2006 IBC. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. This building is fire sprinklered for area increase and high rise provisions. **AJS**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/22/201311/25/201311/25/2013APASS
DetailsDave Hannah
call 20 min prior to meet // Tim Phone #: ###-####
BLD-Framing/Rough-in7/29/20137/30/20137/30/2013APASS
DetailsDave Hannah
please call 20min prior for access - tim Phone #: ###-####
Place hold on job7/11/2013 7/25/2013 DONE
DetailsTisha Gallop
Bld13-01309 (suite 100) and BLD13-01523 (suite 104) are on the same set of plan in ePlanReview. Must issue both permits together.//6/12/13 leg
Permit Ready to Issue  7/25/2013 DONE
Issue PAID IN FULL permit  7/25/2013 DONE
DetailsChristina Prado
Print Occupancy Form  7/25/2013 DONE
DetailsChristina Prado
Plan assigned to (AJS)5/30/20135/30/20136/12/2013 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed Due 6/12 level 2 TI e plan
Routing - PLAN CHECK6/12/2013 6/12/2013 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  6/12/2013 DONE
Routing - PLAN CHECK5/30/2013 6/11/2013 FAIL
DetailsAdele J Schaffeld-Griffin
1st review completed  6/11/2013 FAIL
DetailsAdele J Schaffeld-Griffin
see change marks in e plans
Intake Approval  5/30/2013 PASS
DetailsAdele J Schaffeld-Griffin
Payment Received  5/23/2013 DONE
Payment received via Govolutions
Application received  5/22/2013 DONE
Application submitted via PDS Online on May 22 2013 2:05PM