BLD-Final | 9/9/2013 | 9/9/2013 | 9/9/2013 | P | PASS |
Jim Storey
|
|
|
adam Phone #: ###-####
|
DOC - Permit Finaled | 9/9/2013 | 9/9/2013 | 9/9/2013 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 7/19/2013 | 7/22/2013 | 7/22/2013 | A | PASS |
Jim Storey
|
|
|
adam Phone #: ###-####
|
BLD-Framing/Rough-in | 7/16/2013 | 7/16/2013 | 7/16/2013 | P | PASS |
Jim Storey
|
|
|
Adam Phone #: ###-####
|
BLD-Wall Bracing | 7/2/2013 | 7/3/2013 | 7/3/2013 | P | PASS |
Jim Storey
|
|
|
Adam Phone #: ###-####
|
BLD-Foundation | 6/12/2013 | 6/14/2013 | 6/14/2013 | P | PASS |
Jim Storey
|
|
|
stem wall //Adam Phone #: ###-####
|
BLD-Footing | 6/12/2013 | 6/13/2013 | 6/13/2013 | P | PASS |
Jim Storey
|
|
|
Adam Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/12/2013 | | |
Tisha Gallop
|
|
|
|
Plan assigned to (AJS) | 5/23/2013 | 5/23/2013 | 6/3/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 6/5
|
Routing - PLAN CHECK | 6/3/2013 | | 6/3/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Case Summary (BLD) | | | 6/3/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/3/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/3/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 6/3/2013 | | |
|
|
|
|
Telephone call | | | 6/3/2013 | | |
|
|
|
6-3-13 called Abram permit ready and fee given ///dld
|
1st review completed | | | 5/31/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
called Abram 5-31-13
|
Routing - PLAN CHECK | 5/30/2013 | | 5/31/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Called Abram left voice mail. need to know if hashed marks on foundation plan will be 2x6 or stem walls for bearing location shown on floor plan. But the bearing locations shown on the floor plan do not match the foundation plan.
|
Routing - MECHANICAL | | | 5/30/2013 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 5/23/2013 | 5/29/2013 | 5/24/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 5/24/2013 | | 5/24/2013 | | PASS |
Leon Letson
|
|
|
approved site plan
|
Routing - Addressing | 5/23/2013 | | 5/24/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | | | 5/24/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 5/23/2013 | 5/23/2013 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/23/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/23/2013 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 5/23/2013 | | PASS |
Barbara Stitt
|
|
|
|