BLD-Final | 10/29/2013 | 10/31/2013 | 10/31/2013 | P | PASS |
Dave Hannah
|
|
|
BRIAN Phone #: ###-####
|
DOC - Permit Finaled | 10/31/2013 | 10/31/2013 | 10/31/2013 | P | PASS |
Dave Hannah
|
|
|
|
PubWorks Occupancy Approval | 10/31/2013 | 10/31/2013 | 10/31/2013 | | DONE |
Jason C. Taylor
|
|
|
Recieved approval letter from civil engineer approving grading and drainage. Project has been stabilized and ok for occupancy. Jason Taylor ###-####
|
BLD-Energy code compliance | 8/29/2013 | 8/30/2013 | 8/30/2013 | P | PASS |
Dave Hannah
|
|
|
bryan Phone #: ###-####
|
BLD-Framing/Rough-in | 8/27/2013 | 8/28/2013 | 8/29/2013 | P | PART |
Dave Hannah
|
|
|
bryan - call hour prior Phone #: ###-#### c/n on site ok to insulate and shear ok to cover ext
|
BLD-Wall Bracing | 8/23/2013 | 8/26/2013 | 8/26/2013 | A | PART |
Mike Jordan
|
|
|
bryan Phone #: ###-####. Remove paper from exterior wall, installmissing blocking. recall for inspection.
|
BLD-Foundation | 7/2/2013 | 7/3/2013 | 7/3/2013 | A | PASS |
Dave Hannah
|
|
|
Eric Phone #: ###-####
|
BLD-Footing | 6/24/2013 | 6/25/2013 | 6/25/2013 | A | PASS |
Dave Hannah
|
|
|
eric Phone #: ###-####
|
PubWorks Subgrade Approval | 6/24/2013 | 6/24/2013 | 6/24/2013 | | DONE |
Jason C. Taylor
|
|
|
Recieved subgrade approval from geotechnical engineer for the entire building footings. Building department may be scheduled for footing inspections. Jason Taylor ###-####.
|
OVERRIDE | | | 6/17/2013 | | |
|
|
|
|
Telephone call | | | 6/17/2013 | | DONE |
Tisha Gallop
|
|
|
called Doug Lasher Const and left vm permit is ready and fee.
|
Issue PAID IN FULL permit | | | 6/17/2013 | | DONE |
Christina Prado
|
|
|
|
Routing PW Grading-Hillside | 6/17/2013 | | 6/17/2013 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Inspection Record Card- Bld | | | 6/17/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 6/17/2013 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (AJS) | 5/30/2013 | 5/30/2013 | 6/14/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed / Due 6/17 Hillside
|
Routing - PLAN CHECK | 6/14/2013 | | 6/14/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Case Summary (BLD) | | | 6/14/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/14/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/14/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 6/14/2013 | | DONE |
Tisha Gallop
|
|
|
|
1st review completed | | | 6/13/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
comments faxed 6/13/13
|
Plan resubmittals received | | | 6/13/2013 | | DONE |
Christina Prado
|
|
|
Received two sets of plans marked A-104, A-105, A-106, A-107, S105 & S106; Plan taken to Adele for further review
|
Routing - PLAN CHECK | 6/7/2013 | | 6/12/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see documents for plan review letter
|
Routing - FIRE | 6/4/2013 | | 6/7/2013 | | PASS |
Scott Arellano
|
|
|
Approved with no comments.
|
Routing - Erosion and Sediment | 6/4/2013 | | 6/4/2013 | | PASS |
Kimberly M. Johnson
|
|
|
|
Routing - MECHANICAL | 5/31/2013 | | 6/4/2013 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 5/31/2013 | | 5/31/2013 | | PASS |
Susan Riggs
|
|
|
CFH13-00014-Susan Riggs
|
Plan resubmittals received | | | 5/31/2013 | | |
|
|
|
Received 1 copy of sheet C1 and inserted into plans
|
Routing - PUBLIC WORKS | | | 5/31/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Grading-Hillside | 5/30/2013 | | 5/30/2013 | | FAIL |
Jason C. Taylor
|
|
|
Missing additional grading plans. Applicant to submit additional copy for approval. Jason Taylor ###-####.
|
Routing - Addressing | 5/30/2013 | | 5/30/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Route to Impact Fee Review | 5/29/2013 | 6/3/2013 | 5/29/2013 | | PASS |
James McMahon
|
|
|
|
Application received | | 5/29/2013 | 5/29/2013 | | DONE |
Barbara Stitt
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/29/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/29/2013 | | DONE |
Barbara Stitt
|
|
|
|
Intake Approval | | | 5/29/2013 | | PASS |
Barbara Stitt
|
|
|
Due 6-17 Hillside
|