Second Notice | | 9/9/2013 | 10/1/2013 | | DONE |
Christina Prado
|
|
|
mailed 10/2/13///faxd back 10-3-13
|
First Notice | | 8/10/2013 | 8/30/2013 | | DONE |
|
|
|
Faxed 8-30-13
|
Permanent Occupancy | | | 7/31/2013 | | |
|
|
|
|
BLD-Final | 7/29/2013 | 7/30/2013 | 7/30/2013 | A | PASS |
Jim Sly
|
|
|
kelly Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 7/29/2013 | 7/29/2013 | 7/29/2013 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Ceiling Grid Inspection | 7/16/2013 | 7/17/2013 | 7/17/2013 | A | PASS |
Tony Young
|
|
|
kelly Phone #: ###-####
|
FIRE-Final Inspection | 7/16/2013 | 7/16/2013 | 7/16/2013 | P | FAIL |
Troy Cobbley
|
|
|
Need the ceiling tile installed so that I can final the fire sprinkler permit and then final the life safety for this permit.
|
BLD-Final | 7/15/2013 | 7/16/2013 | 7/16/2013 | A | NR |
Jim Sly
|
|
|
kelly Phone #: ###-#### Need mech, fire/life and sprinkler finals. Notified Contr.
|
Plan assigned to (CDM) | 6/4/2013 | 6/4/2013 | 6/12/2013 | | PASS |
Carl D Madsen
|
|
|
First review completed 6-11-13 CDM
|
Routing - PLAN CHECK | 6/12/2013 | | 6/12/2013 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/12/2013 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/12/2013 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/12/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 6/12/2013 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 6/12/2013 | | DONE |
Tisha Gallop
|
|
|
called Kelly and left vm in general mailbox permit is ready, fee and need GC form.
|
Issue PAID IN FULL permit | | | 6/12/2013 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLAN CHECK | 6/4/2013 | | 6/11/2013 | | FAIL |
Carl D Madsen
|
|
|
Waiting for a call back about some area usage. 6-11-13 CDM
|
1st review completed | | | 6/11/2013 | | FAIL |
|
|
|
|
Telephone call | | | 6/11/2013 | | DONE |
|
|
|
Spoke with Kelly to verify use of spaces. He indicated that the architect had called out a break room which is actually storage. Plans were altered per the tenant to reflect the actual uses. 6-11-13 CDM
|
Plans ACCEPTED BY PLAN TECH | | | 6/4/2013 | | |
|
|
|
6-4-13 Ok per Carl M to take in as a level 1
|
Application received | | 6/4/2013 | | | |
|
|
|
|