Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD13-01556
StatusFinaled
Name SUNRISE DEVELOPMENT LLC
Site Address 2822 S HOLDEN LN
Project Name 
Customer Number 
ePlanReviewNo
Description
(For Lot 1 Block 5 Tianna Park Sub) Permit for the construction of a new 2031 sq. ft., two story (first story 1371 sq. ft., second story 660 sq. ft.) single family dwelling with 3 bedrooms, 2 bathrooms, approximately 32 sq. ft. of covered patio/porch and a 468 sq. ft. attached garage per the approved plans, plan review report and any notations. R-1C zoning and setbacks per planning. JG
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/24/20146/25/20146/25/2014APASS
DetailsJim Storey
Justin Phone #: ###-####
DOC - Permit Finaled6/25/20146/25/20146/25/2014PPASS
DetailsJim Storey
BLD-Energy code compliance3/12/20143/12/20143/12/2014PPASS
DetailsJim Storey
Justin Phone #: ###-####
BLD-Framing/Rough-in3/10/20143/10/20143/10/2014PPASS
DetailsJim Storey
justin Phone #: ###-#### 316 aproved previously.
BLD-Energy code compliance1/28/20141/29/20141/30/2014APASS
DetailsJim Sly
Justin Phone #: ###-####
BLD-Framing/Rough-in1/27/20141/27/20141/27/2014PPART
DetailsJim Storey
Justin Phone #: ###-#### hgr1 broken bc mud rm// east soffit max 1 ft prorected. ok to insulate.
BLD-Framing/Rough-in1/24/20141/24/20141/24/2014PNR
DetailsJim Storey
please call ahead for access - Justin Phone #: ###-####
BLD-Framing/Rough-in1/16/20141/17/20141/17/2014ANR
DetailsJim Storey
JUSTIN Phone #: ###-####
BLD-Wall Bracing1/16/20141/17/20141/17/2014ANR
DetailsJim Storey
Justin Phone #: ###-####
BLD-Wall Bracing12/18/201312/19/201312/19/2013AFAIL
DetailsMike Jordan
justin Phone #: ###-####. Install all missing blocking and restaple.
BLD-Footing10/1/201310/1/201310/1/2013PPASS
DetailsJim Storey
Pat Phone #: ###-####
OVERRIDE  9/27/2013  
Issue PAID IN FULL permit  9/27/2013 DONE
Permit Ready to Issue  9/27/2013 DONE
Plan assigned to (JG)9/25/20139/25/20139/26/2013 PASS
DetailsJavier Guzman
Routing - PLAN CHECK9/26/2013 9/26/2013 PASS
DetailsJavier Guzman
Case Summary (BLD)  9/26/2013 DONE
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  9/26/2013 DONE
Inspection Record Card- Bld  9/26/2013 DONE
DetailsChristina Prado
Plan assigned to (AJS) 6/14/20139/25/2013 DEFR
DetailsAdele J Schaffeld-Griffin
1st review completed Due 6/27
Routing - PLAN CHECK9/24/2013 9/24/2013 FAIL
DetailsJavier Guzman
need girder truss loyout and detials
Plan resubmittals received  9/19/2013  
9-19-13 received 1 subdivision info sheet, 2 copies of sheets A1.0,A2.0,A2.1,A3.0,A4.0,A5.0,A6.0,A7.0 sent to Adele
Routing - PLANNING9/10/2013 9/10/2013 PASS
DetailsCody Riddle
Approved per CUP13-00022
Routing - PLANNING Land Div9/10/2013 9/10/2013 PASS
DetailsCody Riddle
Tianan Park #1 has been recorded.
Telephone call  9/10/2013 DONE
DetailsAdele J Schaffeld-Griffin
Recieved voice mail this morning from Kristina wanting to know if she could come in and pick up her permit. I let her know that I have not recieved any revised plans to address the 11 comments from the plan review letter sent to her 6/26. I re sent the same email to her this morning and took the plans to Cody to veriy the platt and CUP were finaled. I will take to Jason T. to get address approved then PW and back to me to wait for resubmittals. 9/10/13
Routing - Addressing9/10/2013 9/10/2013 PASS
DetailsJason C. Taylor
Routing - PUBLIC WORKS9/10/2013 9/10/2013 PASS
DetailsConnie Baumgartner
Routing - PLAN CHECK6/26/2013 6/26/2013 FAIL
DetailsAdele J Schaffeld-Griffin
Recieved revised site plan 6/25/13, plan review comments in documents emailed 6/26/13
Telephone call  6/25/2013 DONE
DetailsAdele J Schaffeld-Griffin
Called Kristine as I did not recieve a phone call from the designer yesterday to follow up.
1st review completed  6/25/2013 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK6/20/2013 6/25/2013 FAIL
DetailsAdele J Schaffeld-Griffin
spoke with Kristine 6/24 and 6/25 I need a site plan that shows the distance to P.L on all 4 sides as this has very little setbacks and a majority of the plan review items can be addressed with a current site plan. I will not start my official review until this is recieved.
Telephone call  6/24/2013 DONE
DetailsAdele J Schaffeld-Griffin
Called Kristine and asked for site plan showing setbacks on all 4 sides. Discussed the issues with the close PL. She said she will have her disigner call me.
Routing - MECHANICAL  6/20/2013 PASS
DetailsTroy James
Route to Impact Fee Review6/14/20136/19/20136/17/2013 PASS
DetailsCindy M. Gould
Credit given for one unit on Demo permit BLD13-01204
Routing - Addressing6/14/2013 6/17/2013 FAIL
DetailsJason C. Taylor
Project has not been recorded, no parcel numbers assigned by Ada County, no addresses can be assigned until parcel numbers are assigned. Jason Taylor ###-####.
Routing - PUBLIC WORKS  6/17/2013 FAIL
DetailsConnie Baumgartner
Failed by Public Works, subdivision has not recorded, no address information available until parcel is platted.
Plans ACCEPTED BY PLAN TECH  6/14/2013 DONE
DetailsChristina Prado
Intake Approval  6/14/2013 PASS
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  6/14/2013 DONE
DetailsChristina Prado
Application received 6/14/2013   
Routing - PLANNING    FAIL
Needs CUP mod and Plat recorded