First Notice | | 11/25/2013 | 11/15/2013 | | DONE |
|
|
|
|
Permanent Occupancy | | | 11/15/2013 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 11/13/2013 | 11/13/2013 | 11/13/2013 | P | PASS |
Jim Storey
|
|
|
jared Phone #: ###-####
|
FIRE-Final Inspection | 11/4/2013 | 11/4/2013 | 11/5/2013 | P | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
FIRE-Final Inspection | 10/31/2013 | 10/31/2013 | 11/1/2013 | P | NR |
Forrest France
|
|
|
Final pending project related fire sprinkler permit work.
|
BLD-Framing/Rough-in | 10/22/2013 | 10/22/2013 | 10/22/2013 | P | PASS |
Jim Storey
|
|
|
Ceiling grid inspection please-Derrick Phone #: ###-####
|
BLD-Framing/Rough-in | 9/20/2013 | 9/20/2013 | 9/20/2013 | P | PART |
Jim Storey
|
|
|
Derek Phone #: ###-#### ok pending hvac aprovals
|
BLD-Framing/Rough-in | 9/18/2013 | 9/18/2013 | 9/18/2013 | P | PASS |
Jim Storey
|
|
|
derek Phone #: ###-####
|
BLD-Conference | 8/13/2013 | 8/14/2013 | 8/14/2013 | A | PASS |
Jim Storey
|
|
|
call before// derek Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/12/2013 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/19/2013 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 7/19/2013 | | |
|
|
|
|
Override - Parcel Holds | | | 7/19/2013 | | |
|
|
|
|
Permit Ready to Issue | | | 7/19/2013 | | DONE |
|
|
|
|
Telephone call | | | 7/19/2013 | | DONE |
Tisha Gallop
|
|
|
called Thomas and left vm permit is ready and fee.
|
Plan assigned to (TLW) | 6/21/2013 | | 7/18/2013 | | PASS |
Tim L. Woodard
|
|
|
1st Review Complete.
|
Routing - PLAN CHECK | 7/16/2013 | | 7/18/2013 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/18/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 7/18/2013 | | DONE |
Tim L. Woodard
|
|
|
|
1st review completed | | | 7/16/2013 | | FAIL |
|
|
|
Failed plan check.
|
Routing - FIRE | 7/11/2013 | | 7/15/2013 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Plan resubmittals received | | | 7/11/2013 | | DONE |
Christina Prado
|
|
|
Received two sets of revised plans marked A0.1.1, A2.1, A2.2, A2.7, A4.0 & A4.1;Plans taken to Tim for further review
|
Routing - PLAN CHECK | 6/25/2013 | | 7/8/2013 | | FAIL |
Tim L. Woodard
|
|
|
Refer to Plan Review Report attached. TLW
|
Routing - Addressing | 6/21/2013 | | 6/25/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 6/25/2013 | | 6/25/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Design Review | 6/25/2013 | | 6/25/2013 | | PASS |
Sarah Schafer
|
|
|
Sarah Schafer- Office area verification in M-1D Zoning
Office space approved per CUP06-00039.
|
Plan Reviewer's activity | | | 6/25/2013 | | DONE |
Jason Blais
|
|
|
Received email from Christy Little. No ACHD impact fees due.
|
Routing PW Sewer Rating | 6/25/2013 | | 6/25/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Plan Reviewer's activity | | | 6/21/2013 | | DONE |
Jason Blais
|
|
|
Emailed architect to have him contact ACHD for evaluation of any impact fees due. Written verification from ACHD needs to be provided to our Permit Counter prior to the permit being issued.
|
Pending Assignment by JCB | 6/20/2013 | | 6/21/2013 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 6/20/2013 | | PASS |
|
|
|
OK to submit
|
Plans ACCEPTED BY PLAN TECH | | | 6/20/2013 | | DONE |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/20/2013 | | DONE |
Christina Prado
|
|
|
|
Application received | | 6/20/2013 | | | |
|
|
|
|