Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD13-01625
StatusExpired
Name HANSON RAYMOND L
Site Address 1402 S BROADWAY AVE
Project Name 
Customer Number 
ePlanReviewNo
Description
**(Basement Apartments A & B)** Application for inspection to determine requirements for issuance of a Certificate of Occupancy for a 1800 sq ft existing residential tenant. This building was built in 1952 as a 4 plex, 2 units upstairs and 2 units in the basement. In 1966 The Association of Idaho Cities renovated the building into office space. The permit does not indicate if the basement apartments were part of the renovation to an office occupancy as the permit states building converted for new occupancy. Jason Blais, Building Official and Raymond Hanson, Building Owner met. We will allow and occupancy evaluation to be submitted on the apartments but we must be allowed access to inspect the apartments. We will be checking to ensure that code compliant egress windows are installed in the sleeping rooms, smoke detectors are installed carbon monoxide detectors installed if there is gas to the building and that the 1st floor and the basement are separated. NO NEW WORK IS AUTHORIZED UNDER THIS PERMIT. There will be no change to the occupancy. **AJS**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Expired5/14/20195/14/20195/14/2019PPASS
DetailsJim Storey
ncfi fire/bld
Issue PAID IN FULL permit  7/3/2013 DONE
DetailsTisha Gallop
Plan assigned to (AJS)6/21/20136/21/20136/25/2013 PASS
DetailsAdele J Schaffeld-Griffin
Due 6/27
1st review completed  6/25/2013 DONE
DetailsAdele J Schaffeld-Griffin
Case Summary (BLD)  6/25/2013 DONE
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  6/25/2013 DONE
Permit Ready to Issue  6/25/2013 DONE
DetailsTisha Gallop
Print Occupancy Form  6/25/2013 DONE
DetailsTisha Gallop
Telephone call  6/25/2013 DONE
DetailsTisha Gallop
called Raymond and told him permit is ready and fee due.
Routing - PLAN CHECK6/21/2013 6/25/2013 PASS
DetailsAdele J Schaffeld-Griffin
Plans ACCEPTED BY PLAN TECH  6/21/2013  
ok per Tim W to take in
Plan assigned to (TLW)6/21/2013 6/21/2013 DEFR
DetailsAdele J Schaffeld-Griffin
Defered to AJS. TLW
Application received 6/20/2013