First Notice | 8/27/2013 | 8/27/2013 | 8/29/2013 | | DONE |
Mike Jordan
|
|
|
mailed 8/29/13
completed 9-26-13
|
BLD-Final | 8/26/2013 | 8/27/2013 | 8/27/2013 | P | PASS |
Mike Jordan
|
|
|
christine Phone #: ###-####
|
DOC - Permit Finaled | 8/27/2013 | 8/27/2013 | 8/27/2013 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 8/26/2013 | 8/27/2013 | 8/27/2013 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Issue PAID IN FULL permit | | | 8/5/2013 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 7/24/2013 | 7/24/2013 | 8/2/2013 | | PASS |
Carl D Madsen
|
|
|
Level 2 - Cradlepoint Racking
|
Routing - FIRE | 7/30/2013 | | 8/2/2013 | | PASS |
Scott Arellano
|
|
|
No plan review comments attached to plans. A seperate fire sprinkler permit is required for the necessary modification to the building fire sprinkler system. Refer to FIR13-00356.
|
1st review completed | | | 8/2/2013 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 8/2/2013 | | 8/2/2013 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/2/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/2/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/2/2013 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 8/2/2013 | | DONE |
Christina Prado
|
|
|
called Chrisitne to advise permit is ready adn gave fees due
|
Case Summary (BLD) | | | 7/30/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/24/2013 | | 7/30/2013 | | PASS |
Carl D Madsen
|
|
|
|
Application received | | 7/1/2013 | 7/24/2013 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/24/2013 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/24/2013 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 7/24/2013 | | PASS |
Jason Blais
|
|
|
Passed by Adele Schaffeld-Griffin.
|
FIRE-Conference | 7/10/2013 | 7/10/2013 | 7/10/2013 | P | DONE |
Troy Cobbley
|
|
|
Conference was for the status of the racking permit. christine stated that she is still waiting on Treasure Valley Fire to provide her with a sprinkler system analysis. I left her some competitors phone numbers and I also left jeff with TVFP a voice message. Also upon looking into the warehouse I saw that the racks were being used so I reminded Christine that per our previous agreement the area under them could be used (floor space) but the racks them selves could not. She said that she had misunderstood me. She is going to remove the product.
|
Intake Approval | | | 7/1/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
failed fire intake, need vacinety plan, key plan, evaluation report on hold downs, signed special inspection statement, 2 copies of all documents,
|
Pending Assignment by JCB | 7/24/2013 | | | | |
Jason Blais
|
|
|
|