BLD-Final | 12/31/2013 | 1/3/2014 | 1/3/2014 | A | PASS |
Dave Hannah
|
|
|
clint Phone #: ###-####
|
DOC - Permit Finaled | 1/3/2014 | 1/3/2014 | 1/3/2014 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 10/29/2013 | 10/30/2013 | 10/30/2013 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 10/25/2013 | 10/28/2013 | 10/28/2013 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall
|
BLD-Wall Bracing | 10/8/2013 | 10/8/2013 | 10/8/2013 | P | PASS |
Dave Hannah
|
|
|
joey Phone #: ###-####
|
BLD-Framing/Rough-in | 10/3/2013 | 10/3/2013 | 10/4/2013 | P | PART |
Dave Hannah
|
|
|
Joey-Shear inspection please Phone #: ###-#### upper level ok to cover ext
|
BLD-Foundation | 8/29/2013 | 8/29/2013 | 8/29/2013 | P | PASS |
Dave Hannah
|
|
|
alvaro Phone #: ###-####
|
BLD-Footing | 8/28/2013 | 8/28/2013 | 8/28/2013 | P | PART |
Jim Storey
|
|
|
Alvaro Phone #: ###-####wip set backs ok
|
Issue PAID IN FULL permit | | | 7/24/2013 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 7/23/2013 | | |
|
|
|
|
Plan assigned to (AJS) | 7/2/2013 | 7/2/2013 | 7/23/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 7/15
|
Telephone call | | | 7/23/2013 | | DONE |
Barbara Stitt
|
|
|
Called and left voice message that pemit is ready and fees due on 7-23-13 @ 3:45pm//BAS
|
Routing - PLAN CHECK | 7/23/2013 | | 7/23/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Case Summary (BLD) | | | 7/23/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/23/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/23/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 7/23/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plan resubmittals received | | | 7/22/2013 | | DONE |
|
|
|
|
Routing - MECHANICAL | | | 7/9/2013 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 7/8/2013 | | 7/8/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
emailed leonard 7/8/13
Leonard,
I have completed the building plan review for BLD13-01750.
Please provide the stamped engineering calculations for the engineered lateral analysis. The balloon framed portion shown on the wall bracing exceeds prescriptive design.
Please provide the beam/ angled post calculations for this project.
Thank you
Adele J. Schaffeld-Griffin
City of Boise
Plans Examiner II
###-####
|
1st review completed | | | 7/8/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Route to Impact Fee Review | 7/2/2013 | 7/8/2013 | 7/5/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 7/3/2013 | | 7/5/2013 | | PASS |
Leon Letson
|
|
|
|
Application received | | 7/2/2013 | 7/3/2013 | | DONE |
Tisha Gallop
|
|
|
|
Routing - Addressing | 7/3/2013 | | 7/3/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 7/3/2013 | | 7/3/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 7/2/2013 | | PASS |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/2/2013 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/2/2013 | | DONE |
Tisha Gallop
|
|
|
|