BLD-Final | 12/19/2013 | 12/23/2013 | 12/23/2013 | A | PASS |
Dave Hannah
|
|
|
garage code is 1979 Phone #: ###-#### >> Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 12/23/2013 | 12/23/2013 | 12/23/2013 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 10/15/2013 | 10/17/2013 | 10/17/2013 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 10/14/2013 | 10/15/2013 | 10/15/2013 | A | PART |
Jim Sly
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall C/N posted. OK to insulate.
|
BLD-Framing/Rough-in | 9/26/2013 | 9/26/2013 | 9/26/2013 | P | PASS |
Jim Storey
|
|
|
Shear inspection please-Joey Phone #: ###-####
|
BLD-Wall Bracing | 9/23/2013 | 9/23/2013 | 9/23/2013 | P | PART |
Dave Hannah
|
|
|
joey Phone #: ###-#### second level ok to cover
|
BLD-Foundation | 8/14/2013 | 8/14/2013 | 8/14/2013 | P | PASS |
Jim Storey
|
|
|
ANTON Phone #: ###-####
|
BLD-Footing | 8/13/2013 | 8/13/2013 | 8/13/2013 | P | PASS |
Dave Hannah
|
|
|
Anton Phone #: ###-####
|
Plan assigned to (AJS) | 7/2/2013 | 7/2/2013 | 7/18/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 7/15
|
Routing - PLAN CHECK | 7/15/2013 | | 7/18/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Case Summary (BLD) | | | 7/18/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/18/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/18/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 7/18/2013 | | |
|
|
|
|
Telephone call | | | 7/18/2013 | | |
|
|
|
7-18-13 Emailed Tahoe Homes permit ready and fee given ///dld
|
Issue PAID IN FULL permit | | | 7/18/2013 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/16/2013 | | DONE |
Christina Prado
|
|
|
received two sets of structural calcs and revised sheets marked 3.0 & 5.0;Taken to Adele for additional review
|
Routing - MECHANICAL | 7/9/2013 | | 7/16/2013 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 7/3/2013 | | 7/9/2013 | | FAIL |
Troy James
|
|
|
emailed travis to provide page 2 of duct system summary sheet.
|
Routing - PLAN CHECK | 7/5/2013 | | 7/5/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
emailed loenard 7/5
Leonard,
I have completed the building plan review for BLD13-01754.
Please provide the stamped engineering calculations for the engineered lateral as indicated on the plans.
Please provide the beam calculations for this project.
Thank you
Adele J. Schaffeld-Griffin
City of Boise
Plans Examiner II
###-####
|
1st review completed | | | 7/5/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Route to Impact Fee Review | 7/2/2013 | 7/8/2013 | 7/3/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 7/2/2013 | | 7/3/2013 | | PASS |
Todd Tucker
|
|
|
|
Intake Approval | | | 7/2/2013 | | PASS |
|
|
|
|
Routing - Addressing | 7/2/2013 | | 7/2/2013 | | PASS |
Jason C. Taylor
|
|
|
Address is 2860 S honeycomb way
|
Routing - PUBLIC WORKS | | | 7/2/2013 | | PASS |
|
|
|
|
Application received | | 7/2/2013 | | | |
|
|
|
|