Third Notice | | 8/31/2014 | 9/12/2014 | | DONE |
Christina Prado
|
|
|
|
Print Statement | | | 9/12/2014 | | DONE |
Christina Prado
|
|
|
|
Second Notice | | 7/25/2014 | 8/26/2014 | | DONE |
|
|
|
|
First Notice | | 6/21/2014 | 7/15/2014 | | DONE |
|
|
|
Faxed 7-15-14
|
BLD-Final | 6/11/2014 | 6/11/2014 | 6/11/2014 | P | PASS |
Jim Storey
|
|
|
per bo jblais
|
Permanent Occupancy | | | 6/11/2014 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 6/9/2014 | 6/10/2014 | 6/10/2014 | P | PART |
Jim Storey
|
|
|
bill - Phone #: ###-#### final ok pending pw sign off for perm
|
FIRE-Final Inspection | 6/9/2014 | 6/10/2014 | 6/10/2014 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection passed after corrections finished while on site.
|
PubWorks Occupancy Approval | 6/10/2014 | 6/10/2014 | 6/10/2014 | | DONE |
Jason C. Taylor
|
|
|
Bond has been placed for final drainage and revegetation. Occupancy may be granted. Jason Taylor ###-####.
|
FIRE-Conference | 6/9/2014 | 6/9/2014 | 6/9/2014 | P | DONE |
Forrest France
|
|
|
Regarding fire life safety inspection items.
|
FIRE-Final Inspection | 6/5/2014 | 6/6/2014 | 6/6/2014 | A | CANC |
Forrest France
|
|
|
Bill Tonklin Phone #: ###-####
|
Zoning Approval | 6/6/2014 | 6/6/2014 | 6/6/2014 | | PASS |
Josh Wilson
|
|
|
|
BLD-Ceiling Grid Inspection | 4/25/2014 | 4/28/2014 | 4/28/2014 | A | PASS |
Jim Storey
|
|
|
bill Phone #: ###-####
|
BLD-Energy code compliance | 2/27/2014 | 2/28/2014 | 2/28/2014 | P | PASS |
Jim Storey
|
|
|
bILL Phone #: ###-####
|
BLD-Framing/Rough-in | 2/25/2014 | 2/26/2014 | 2/26/2014 | A | PART |
Jim Storey
|
|
|
Phone #: ###-#### fire blk at drop ceillings wall lines
|
BLD-Wall Bracing | 2/13/2014 | 2/14/2014 | 2/14/2014 | A | PASS |
Jim Storey
|
|
|
Bill Tonkin Phone #: 407-over nailling okfor exterior ok
|
BLD-Framing/Rough-in | 2/7/2014 | 2/10/2014 | 2/10/2014 | A | CANC |
Jim Storey
|
|
|
Partial Framing please contact Bill with questions ###-####
|
Print Occupancy Form | | | 2/10/2014 | | DONE |
Barbara Stitt
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/10/2014 | | DONE |
Barbara Stitt
|
|
|
|
(F) Reprint permit | | | 2/10/2014 | | DONE |
Barbara Stitt
|
|
|
|
OVERRIDE | | | 2/7/2014 | | |
|
|
|
|
Telephone call | | | 2/7/2014 | | DONE |
Barbara Stitt
|
|
|
Called Corin with Guho and told her that the plan modification is ready and the fees due and that the fees need paid so they can have the monday inspection that they have been asking for today.
|
Routing PW Sewer Design | 2/4/2014 | | 2/7/2014 | | PASS |
Kyle S. Rosenmeyer
|
|
|
Sanitary Keynote 3 should be removed from sheet C300.
|
Routing - PLAN CHECK | 2/4/2014 | | 2/7/2014 | | PASS |
John Menard
|
|
|
|
Plan assigned to (JCM) | 2/4/2014 | | 2/7/2014 | | DONE |
John Menard
|
|
|
|
Routing - PLUMBING | 2/4/2014 | | 2/5/2014 | | PASS |
Daryl Spivey
|
|
|
Per plan and NFPA 99C and ISPC.
|
Routing - PUBLIC WORKS | 2/4/2014 | | 2/4/2014 | | PASS |
Connie Baumgartner
|
|
|
|
Plan Modification Accepted | | | 2/3/2014 | | DONE |
|
|
|
started work flow
|
BLD-Framing/Rough-in | 1/28/2014 | 1/29/2014 | 1/29/2014 | A | PART |
Tony Young
|
|
|
Bill-Please call prior to insepection Phone #: ###-####,, ok to cover ceiling,, all truss engineering and connections will be made ok
|
Print Occupancy Form | | | 1/28/2014 | | DONE |
Barbara Stitt
|
|
|
|
CHANGE STATUS TO (ISS) | | | 1/28/2014 | | DONE |
Barbara Stitt
|
|
|
|
(F) Reprint permit | | | 1/28/2014 | | DONE |
Barbara Stitt
|
|
|
|
OVERRIDE | | | 12/23/2013 | | |
|
|
|
|
Routing - PUBLIC WORKS | 12/20/2013 | | 12/20/2013 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Drainage | 12/20/2013 | | 12/20/2013 | | PASS |
Brian Murphy
|
|
|
|
Plan assigned to (JCM) | 12/19/2013 | | 12/20/2013 | | PASS |
John Menard
|
|
|
Plan Mod Review completed 12/19/2013
|
Routing - PLAN CHECK | 12/19/2013 | | 12/20/2013 | | PASS |
John Menard
|
|
|
|
Routing - PLUMBING | 12/19/2013 | | 12/20/2013 | | PASS |
Daryl Spivey
|
|
|
water service isolation is addressed on P3.1 note 6
|
BLD-Foundation | 12/18/2013 | 12/19/2013 | 12/19/2013 | A | PASS |
Tom Arcoraci
|
|
|
930
|
Routing - Design Review | 12/19/2013 | | 12/19/2013 | | PASS |
Josh Wilson
|
|
|
|
Routing - PUBLIC WORKS | 12/19/2013 | | 12/19/2013 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Sewer Design | 12/19/2013 | | 12/19/2013 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Plan Reviewer's activity | | | 12/19/2013 | | PASS |
John Menard
|
|
|
Reviewed and approved plan modification. JCM
|
BLD-Foundation | 12/18/2013 | 12/18/2013 | 12/18/2013 | P | NR |
Tom Arcoraci
|
|
|
Pouring at 3/please call ahead to verify inspection - bill Phone #: ###-####
|
BLD-Footing | 12/13/2013 | 12/17/2013 | 12/17/2013 | A | PASS |
Jim Storey
|
|
|
Pouring at 10 - Bill Phone #: ###-####
|
Plan Modification Accepted | | | 12/17/2013 | | DONE |
|
|
|
started workflow
|
Print Occupancy Form | | | 12/5/2013 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 12/5/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 8/13/2013 | | |
|
|
|
|
Routing - PLUMBING | 8/12/2013 | | 8/12/2013 | | PASS |
Daryl Spivey
|
|
|
per plans and ISPC
|
Routing - PLAN CHECK | 8/12/2013 | | 8/12/2013 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/12/2013 | | DONE |
John Menard
|
|
|
|
Routing - PLAN CHECK | 8/8/2013 | | 8/12/2013 | | |
John Menard
|
|
|
|
Plan assigned to (JCM) | 7/10/2013 | | 8/12/2013 | | PASS |
John Menard
|
|
|
1st Review Completed 7-18-2013
|
Plan Reviewer's activity | | | 8/8/2013 | | PASS |
John Menard
|
|
|
Reviewed and approved final structural revisions. JCM
|
Routing - PLUMBING | 8/8/2013 | | 8/8/2013 | | FAIL |
Bill VanDegrift
|
|
|
|
Routing - PLUMBING | 8/2/2013 | | 8/7/2013 | | FAIL |
Daryl Spivey
|
|
|
Provide a floor sink for dental equipment ( vacuum pump ).
|
Routing Off Site - STRUCTURAL | 8/2/2013 | | 8/7/2013 | | FAIL |
John Menard
|
|
|
|
Routing - PUBLIC WORKS | 8/2/2013 | | 8/5/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Design | 8/5/2013 | | 8/5/2013 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - PLAN CHECK | 8/2/2013 | | 8/2/2013 | | PASS |
John Menard
|
|
|
|
Plan Reviewer's activity | | | 8/2/2013 | | PASS |
John Menard
|
|
|
Reviewed and approved requested revisions. JCM
|
Routing Off Site - STRUCTURAL | 7/10/2013 | | 8/2/2013 | | FAIL |
John Menard
|
|
|
|
1st review completed | | | 7/24/2013 | | DONE |
John Menard
|
|
|
|
Routing PW Drainage | 7/10/2013 | | 7/24/2013 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLAN CHECK | 7/10/2013 | | 7/24/2013 | | FAIL |
John Menard
|
|
|
|
Routing - FIRE | 7/10/2013 | 7/10/2013 | 7/15/2013 | | PASS |
Scott Arellano
|
|
|
Attached plan review comments to case. Plans approved with red line annotations.
|
Routing - PLUMBING | 7/10/2013 | | 7/12/2013 | | FAIL |
Daryl Spivey
|
|
|
provide a floor sink for the dental equipment
|
Routing - Design Review | 7/10/2013 | | 7/12/2013 | | PASS |
Josh Wilson
|
|
|
OK per DRH13-00139
|
Route to Impact Fee Review | 7/10/2013 | | 7/11/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Addressing | 7/10/2013 | | 7/11/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing PW Sewer Design | 7/10/2013 | | 7/11/2013 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Add notes: Sewer Tap permits required from Boise City Public Works prior to construction.
Add manhole base channelization detail.
|
Routing PW Sewer Rating | 7/10/2013 | | 7/10/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Solid Waste | 7/10/2013 | | 7/10/2013 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Environmental | 7/10/2013 | | 7/10/2013 | | PASS |
Walt Baumgartner
|
|
|
|
Pending Assignment by JCM | 7/10/2013 | | 7/10/2013 | | DONE |
John Menard
|
|
|
|
Routing - PLANNING Land Div | 7/10/2013 | | 7/10/2013 | | PASS |
Dave Abo
|
|
|
|
Routing - PUBLIC WORKS | 7/10/2013 | | 7/10/2013 | | FAIL |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | 7/10/2013 | | 7/10/2013 | | PASS |
Kimberly M. Johnson
|
|
|
|
Application received | | | 7/3/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 3 2013 4:08PM
|