BLD-Final | 1/3/2014 | 1/3/2014 | 1/3/2014 | P | PASS |
Mike Jordan
|
|
|
>> Inspection requested via web by Paul Thompson
|
DOC - Permit Finaled | 1/3/2014 | 1/3/2014 | 1/3/2014 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 12/30/2013 | 1/2/2014 | 1/2/2014 | A | NR |
Mike Jordan
|
|
|
there is a key in the outlet box on the front porch. Phone #: ###-#### >> Inspection requested via web by Paul Thompson. Needs mech. rough in inspection, post address. Correction notice posted.
|
BLD-Blower Door Test Results | 1/2/2014 | 1/2/2014 | 1/2/2014 | A | DONE |
Mike Jordan
|
|
|
3.3
|
BLD-Final | 12/19/2013 | 12/23/2013 | 12/21/2013 | A | CANC |
Mike Jordan
|
|
|
PAUL Phone #: ###-#### Inspection cancelled from web by: Paul Thompson
|
BLD-Wall cover | 11/11/2013 | 11/12/2013 | 11/12/2013 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Paul Thompson. Fireblocking installed at mech chase 2nd. floor.
|
BLD-Framing/Rough-in | 10/28/2013 | 11/1/2013 | 11/1/2013 | A | PART |
Mike Jordan
|
|
|
Paul Phone #: ###-####. Pending mechanical rough in inspection. Also needs to fire block HVAC ducts at ceiling, 2nd. floor.
|
BLD-Framing/Rough-in | 10/21/2013 | 10/22/2013 | 10/22/2013 | A | NR |
Mike Jordan
|
|
|
paul Phone #: ###-####. Needs mechanical rough in inspection. Mechanical work not yet completed.
|
Plan resubmittals received | | | 10/16/2013 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 10/16/2013 | | 10/16/2013 | | PASS |
Troy James
|
|
|
resubmitted manual j
|
BLD-Wall Bracing | 9/24/2013 | 9/24/2013 | 9/24/2013 | P | PASS |
Tom Arcoraci
|
|
|
paul Phone #: ###-####
|
BLD-Framing/Rough-in | 9/17/2013 | 9/17/2013 | 9/17/2013 | P | PASS |
Mike Jordan
|
|
|
1st floor shear inspection please-Paul Phone #: ###-####. 1st. floor exteior wall bracing only ok.
|
BLD-Foundation | 8/14/2013 | 8/15/2013 | 8/15/2013 | P | PASS |
Mike Jordan
|
|
|
Late a.m. if possible. Thank you Phone #: ###-#### >> Inspection requested via web by Paul Thompson
|
BLD-Footing | 8/14/2013 | 8/14/2013 | 8/14/2013 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Paul Thompson
|
Issue PAID IN FULL permit | | | 7/30/2013 | | DONE |
|
|
|
|
OVERRIDE | | | 7/24/2013 | | |
|
|
|
|
Plan assigned to (CDM) | 7/10/2013 | 7/10/2013 | 7/24/2013 | | PASS |
Carl D Madsen
|
|
|
PRJ DOX
|
Routing - PLAN CHECK | 7/10/2013 | | 7/24/2013 | | PASS |
Carl D Madsen
|
|
|
PRJ DOX
|
1st review completed | | | 7/24/2013 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/24/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/24/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 7/24/2013 | | DONE |
Christina Prado
|
|
|
|
Routing - MECHANICAL | 7/10/2013 | | 7/15/2013 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 7/10/2013 | | 7/11/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Route to Impact Fee Review | 7/10/2013 | 7/15/2013 | 7/10/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PUBLIC WORKS | 7/10/2013 | | 7/10/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING | 7/10/2013 | | 7/10/2013 | | PASS |
Joshua Johnson
|
|
|
|
Intake Approval | | | 7/9/2013 | | PASS |
|
|
|
Ok per Carl M on stair section per phone call 7-9-13///dld
|
Application received | | | 7/8/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 8 2013 12:08PM
|
Intake Approval | | | 7/8/2013 | | FAIL |
|
|
|
need stair section and cover sheet needs to be landscape ///dld
|