First Notice | 12/6/2013 | 12/6/2013 | 12/30/2013 | | DONE |
Barbara Stitt
|
|
|
Faxed 12-30-13
|
BLD-Final | 12/5/2013 | 12/6/2013 | 12/6/2013 | A | PASS |
Jim Storey
|
|
|
Jim, call me when you get here, will meet you with Wade up front, everyone is signed off. Phone #: ###-#### >> Inspection requested via web by Miles Hash
|
DOC - Permit Finaled | 12/6/2013 | 12/6/2013 | 12/6/2013 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 11/26/2013 | 11/27/2013 | 11/29/2013 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory.
|
BLD-Framing/Rough-in | 9/16/2013 | 9/17/2013 | 9/17/2013 | A | PASS |
Jim Storey
|
|
|
call me Jim and I will meet you at the front desk Phone #: ###-#### >> Inspection requested via web by Miles Hash
|
BLD-Framing/Rough-in | 8/23/2013 | 8/26/2013 | 8/26/2013 | A | PART |
Jim Storey
|
|
|
call and I will met you at the front office for sign-in and escort, maybe some power bars when you are done. thanks Jim it''s Miles long time no see. Phone #: ###-#### >> Inspection requested via web by Miles Hash rfi as to double door header for gyp support. ok to cover pending responce from arch.
|
Inspection Record Card- Bld | | | 8/21/2013 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 8/20/2013 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/20/2013 | | |
|
|
|
|
(F) Reprint permit | | | 8/20/2013 | | DONE |
|
|
|
|
Routing - FIRE | 8/13/2013 | | 8/15/2013 | | PASS |
Scott Arellano
|
|
|
Attached Fire Code comments to plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/15/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 7/12/2013 | | 8/15/2013 | | PASS |
Tim L. Woodard
|
|
|
Level 3 TI - Powerbar
|
Routing - PLAN CHECK | 8/13/2013 | | 8/13/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 7/12/2013 | | 8/7/2013 | | FAIL |
Tim L. Woodard
|
|
|
Refer to change mark on drawings. TLW
|
Routing - PLUMBING | 7/12/2013 | | 8/7/2013 | | PASS |
Bill VanDegrift
|
|
|
Approved in e-plan review. TLW
|
Routing - Erosion and Sediment | 7/12/2013 | | 8/7/2013 | | PASS |
Kimberly M. Johnson
|
|
|
ESC permit needed for new underslab plumbing work? No permit required
Kim added notes and signed off in E-plan that no ESC is required. TLW
|
1st review completed | | | 8/7/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - FIRE | 7/12/2013 | 7/12/2013 | 7/16/2013 | | FAIL |
Scott Arellano
|
|
|
Emailed resubmittal item to architect. Attached plan review report to case.
|
Routing PW Environmental | 7/15/2013 | | 7/16/2013 | | PASS |
Walt Baumgartner
|
|
|
New "work area" indicates two new floor sinks, facility subject to pretreatment inspection
|
Routing - Design Review | 7/12/2013 | | 7/15/2013 | | PASS |
Sarah Schafer
|
|
|
Sarah Schafer - Exterior door change - I have signed off on the exterior door change as part of the building permit application.
|
Routing PW Sewer Rating | 7/15/2013 | | 7/15/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 7/12/2013 | | 7/15/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 7/12/2013 | | 7/15/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 7/12/2013 | | PASS |
Jason Blais
|
|
|
Prescreen passed by Adele Schaffeld-Griffin on 7/11/13 and Plan Review Fees paid on 7/12/13.
|
Pending Assignment by JCB | 7/12/2013 | | 7/12/2013 | | DONE |
Jason Blais
|
|
|
|
Plan Reviewer's activity | | | 7/11/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
Spoke with Tim and called Rebecca to let her know we woudl accept the pre screen but this project would be routed as a mojor. I will let Jason know when it comes though for routing.
|
Application received | | | 7/10/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 10 2013 7:46AM
|