Third Notice | | 5/10/2014 | 5/13/2014 | | DONE |
|
|
|
This permit finaled on the web by Kari LeGresley
|
Third Notice | | 4/6/2014 | 5/5/2014 | | DONE |
|
|
|
mailed
|
Third Notice | | 3/8/2014 | 4/1/2014 | | DONE |
|
|
|
mailed
|
Second Notice | | 2/6/2014 | 3/3/2014 | | DONE |
Christina Prado
|
|
|
mailed 3-4-14
|
First Notice | | 1/17/2014 | 1/27/2014 | | DONE |
|
|
|
|
BLD-Final | 1/6/2014 | 1/7/2014 | 1/7/2014 | P | PASS |
Mike Jordan
|
|
|
james Phone #: ###-####. Ok for perm occ.
|
FIRE-Final Inspection | 1/6/2014 | 1/7/2014 | 1/7/2014 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
Permanent Occupancy | | | 1/7/2014 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/16/2013 | 12/17/2013 | 12/17/2013 | A | CANC |
Troy Cobbley
|
|
|
gregg Phone #: ###-####
|
BLD-Final | 12/16/2013 | 12/17/2013 | 12/17/2013 | P | NR |
Mike Jordan
|
|
|
gregg - temp only Phone #: ###-####
|
BLD-Final | 12/13/2013 | 12/16/2013 | 12/16/2013 | P | NR |
Mike Jordan
|
|
|
Greg Phone #: ###-####. Will reschedule for the pm on 12-17.
|
BLD-Energy code compliance | 11/12/2013 | 11/13/2013 | 11/13/2013 | P | PASS |
Mike Jordan
|
|
|
Greg Phone #: ###-####
|
BLD-Framing/Rough-in | 11/13/2013 | 11/13/2013 | 11/13/2013 | P | PASS |
Mike Jordan
|
|
|
Greg Phone #: ###-####. interior steel stud walls ok.
|
BLD-Framing/Rough-in | 11/8/2013 | 11/12/2013 | 11/12/2013 | A | PART |
Mike Jordan
|
|
|
Greg Phone #: ###-####. Interior furred walls along perimeter CMU walls. Ok to install rigid insulation at areas that do not cover electrical. Also needs to provide a full set of approved plans that are readable as per IBC sec. 107.2.1.
|
BLD-Framing/Rough-in | 11/7/2013 | 11/8/2013 | 11/8/2013 | P | CANC |
Mike Jordan
|
|
|
greg Phone #: ###-#### Inspection cancelled from web by: Barbara Stitt
|
Issue PAID IN FULL permit | | | 11/4/2013 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 11/4/2013 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 9/26/2013 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 8/6/2013 | 8/6/2013 | 9/4/2013 | | PASS |
Carl Westfall
|
|
|
AUTOZONE (20 days - Sept 2) ePlanReview
|
Routing - PLAN CHECK | 8/29/2013 | | 9/4/2013 | | PASS |
Carl Westfall
|
|
|
Drawings approved
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/4/2013 | | DONE |
|
|
|
|
Plan resubmittals received | | | 8/29/2013 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 8/22/2013 | | DONE |
|
|
|
|
1st review completed | | | 8/22/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/6/2013 | | 8/22/2013 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on August 20, 2013 and finished on August 22, 2013. The drawings were approved with "red lines". After discussing the project with the Architect, he decided that he wanted to incoporate the "red lines" into the drawings and upload those revised sheets. For this reason the project was failed in ePlan and in Tidemark.
|
Routing - FIRE | 8/6/2013 | 8/6/2013 | 8/13/2013 | | PASS |
Scott Arellano
|
|
|
Attached Fire Code comments to plans.
|
Routing - Design Review | 8/6/2013 | | 8/12/2013 | | PASS |
Josh Wilson
|
|
|
Josh Wilson - DRH13-00010
|
Routing - PLUMBING | 8/6/2013 | | 8/9/2013 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - Addressing | 8/6/2013 | | 8/7/2013 | | PASS |
Jason C. Taylor
|
|
|
Address was wrong on application/plans. Address should be 10483 W Overland Rd
|
Routing - PUBLIC WORKS | 8/6/2013 | | 8/7/2013 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Sewer Rating | 8/7/2013 | | 8/7/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Payment Received | | | 8/6/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Intake Approval | | | 8/6/2013 | | PASS |
Jason Blais
|
|
|
Prescreen passed by Adele Schaffeld-Griffin and Plan Review Fees paid.
|
Pending Assignment by JCB | 8/6/2013 | | 8/6/2013 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 8/5/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
1. Please re up load the plans so that all plans read left to right. 7/16/13 There are still sheets uploaded incorrectly. All sheets must be read left to right.
8/5/13 Plans uploaded correctly
2. Please upload completed 518 checklist and all items required by the check list. 7/16/13 The check list was not uploaded on the resubmittal.
8/5/13 Please upload the 518 completed checklist. The document uploaded and labled 518 checklist is the same completed permit application that has already been uploaded. Here is the link for the 518 check list from our web site.
http://pds.cityofboise.org/media/103552/518_Minor_TI_Checklist.pdf
3. Please rename all of the sheets to the conventioal naming requirments. example A1.0-Cover Sheet 7/16/13 Please remove the sheets that have been replaced with the conventional naming that are duplicate sheets.
8/5/13 Naming corrected
Once this additional information is recieved I will be able to complete the pre screen.
Thank you
|
Intake Approval | | | 8/5/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
1. Please re up load the plans so that all plans read left to right. 7/16/13 There are still sheets uploaded incorrectly. All sheets must be read left to right.
8/5/13 Plans uploaded correctly
2. Please upload completed 518 checklist and all items required by the check list. 7/16/13 The check list was not uploaded on the resubmittal.
8/5/13 Please upload the 518 completed checklist. The document uploaded and labled 518 checklist is the same completed permit application that has already been uploaded. Here is the link for the 518 check list from our web site.
http://pds.cityofboise.org/media/103552/518_Minor_TI_Checklist.pdf
8/5/13 I have reviewed the completed 518 check list. The only item missing from the check list is the 304 design professional form. Please see the change mark located on the checklist.
3. Please rename all of the sheets to the conventioal naming requirments. example A1.0-Cover Sheet 7/16/13 Please remove the sheets that have been replaced with the conventional naming that are duplicate sheets.
8/5/13 Naming corrected
Once this additional information is recieved I will be able to complete the pre screen.
Thank you
|
Intake Approval | | | 7/17/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
1. Please re up load the plans so that all plans read left to right. 7/16/13 There are still sheets uploaded incorrectly. All sheets must be read left to right.
2. Please upload completed 518 checklist and all items required by the check list. 7/16/13 The check list was not uploaded on the resubmittal.
3. Please rename all of the sheets to the conventioal naming requirments. example A1.0-Cover Sheet 7/16/13 Please remove the sheets that have been replaced with the conventional naming that are duplicate sheets.
Once this additional information is recieved I will be able to complete the pre screen.
Thank you
|
Intake Approval | | | 7/16/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
1. Please re up load the plans so that all plans read left to right.
2. Please upload completed 518 checklist and all items required by the check list.
3. Please rename all of the sheets to the conventioal naming requirments. example A1.0-Cover Sheet
Once this additional information is recieved I will be able to complete the pre screen.
Thank you
|
Application received | | | 7/11/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 11 2013 11:20AM
|