Third Notice | | 6/14/2014 | 6/9/2014 | | DONE |
Christina Prado
|
|
|
|
Third Notice | | 5/10/2014 | 6/9/2014 | | DONE |
|
|
|
mailed to Unico/Liz Fitzberald
|
Second Notice | | 4/13/2014 | 5/5/2014 | | DONE |
|
|
|
|
First Notice | | 3/22/2014 | 4/3/2014 | | DONE |
|
|
|
Faxed 4-3-14
|
Print Occupancy Form | | | 3/12/2014 | | DONE |
Christina Prado
|
|
|
|
Permanent Occupancy | | | 3/12/2014 | | DONE |
|
|
|
|
BLD-Final | 8/22/2013 | 8/23/2013 | 8/23/2013 | P | PASS |
Dave Hannah
|
|
|
Sam Phone #: ###-####
|
FIRE-Final Inspection | 8/22/2013 | 8/23/2013 | 8/23/2013 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory.
|
BLD-Ceiling Grid Inspection | 8/12/2013 | 8/12/2013 | 8/12/2013 | P | PASS |
Dave Hannah
|
|
|
grid cover - sam Phone #: ###-####
|
BLD-Wall cover | 8/5/2013 | 8/5/2013 | 8/5/2013 | P | PASS |
Dave Hannah
|
|
|
Sam Phone #: ###-####
|
Print Occupancy Form | | | 7/23/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/23/2013 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 7/23/2013 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 7/17/2013 | 7/17/2013 | 7/22/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Level 1 Due 7/23
|
Routing - PLAN CHECK | 7/17/2013 | | 7/22/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
1st review completed | | | 7/22/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/22/2013 | | DONE |
|
|
|
|
Intake Approval | | | 7/17/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please revise the names of the drawings in the files to meet the conventional naming requirments. A1.01 -Cover Sheet
|
Intake Approval | | | 7/17/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 7/15/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 15 2013 4:24PM
|