Third Notice | | 3/5/2014 | 3/10/2014 | | DONE |
Christina Prado
|
|
|
completed 3-10-14
|
Second Notice | | 2/6/2014 | 2/28/2014 | | DONE |
Christina Prado
|
|
|
mailed 2-28-14
|
First Notice | | 12/19/2013 | 1/27/2014 | | DONE |
|
|
|
|
Permanent Occupancy | | | 12/9/2013 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 12/3/2013 | 12/4/2013 | 12/4/2013 | P | PASS |
Tom Arcoraci
|
|
|
Jim Martin ###-#### Phone #: ###-#### >> Inspection requested via web by Brad Turk
|
FIRE-Final Inspection | 12/3/2013 | 12/4/2013 | 12/4/2013 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Ceiling Grid Inspection | 11/12/2013 | 11/13/2013 | 11/13/2013 | P | PASS |
Tom Arcoraci
|
|
|
Brad Turk Phone #: ###-#### >> Inspection requested via web by Brad Turk
|
BLD-Framing/Rough-in | 10/10/2013 | 10/11/2013 | 10/11/2013 | A | PASS |
Tom Arcoraci
|
|
|
Contact. Jim Martin Phone #: ###-#### >> Inspection requested via web by Brad Turk
|
Issue PAID IN FULL permit | | | 8/29/2013 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 8/29/2013 | | DONE |
Tisha Gallop
|
|
|
|
Print Occupancy Form | | | 8/21/2013 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 8/21/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (CJW) | 7/24/2013 | 7/24/2013 | 8/20/2013 | | PASS |
Carl Westfall
|
|
|
ST AL'S EMERGENCY DEPT TEMP EXAM ROOM (20 days - Aug. 20)
|
Routing - PLAN CHECK | 8/13/2013 | | 8/20/2013 | | PASS |
Carl Westfall
|
|
|
Drawings approved after resubmittal review.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/20/2013 | | DONE |
|
|
|
|
Plan resubmittals received | | | 8/13/2013 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 8/9/2013 | | DONE |
|
|
|
|
1st review completed | | | 8/9/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/24/2013 | | 8/9/2013 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on August 7 and finished on August 9. Revised drawings were required. See the plan review report and the changemarks on the ePlan drawings.
|
Routing - Addressing | 7/24/2013 | | 7/30/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - FIRE | 7/24/2013 | 7/24/2013 | 7/26/2013 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing PW Sewer Rating | 7/25/2013 | | 7/26/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLUMBING | 7/24/2013 | | 7/26/2013 | | PASS |
Bill VanDegrift
|
|
|
Install per plan and ISPC and NFPA 99C.
|
Routing - PUBLIC WORKS | 7/24/2013 | | 7/25/2013 | | PASS |
Beverly Mountain
|
|
|
|
Payment Received | | | 7/24/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Intake Approval | | | 7/24/2013 | | PASS |
Jason Blais
|
|
|
Prescreen passed on 7/23/13. Plan Review Fees paid on 7/24/13.
|
Application received | | | 7/17/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 17 2013 3:39PM
|