Routing - PLAN CHECK | 8/7/2013 | | 8/19/2020 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see second plan review letter sent in documents
|
BLD-Final | 3/12/2014 | 3/12/2014 | 3/12/2014 | P | PASS |
Jim Sly
|
|
|
phil Phone #: ###-#### C/C issued.
|
DOC - Permit Finaled | 3/12/2014 | 3/12/2014 | 3/12/2014 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 3/11/2014 | 3/11/2014 | 3/11/2014 | P | FAIL |
Jim Storey
|
|
|
phil Phone #: ###-#### fire stop garage ceilling/ b-vent on water heater to reduce clearance to conbustables.
|
BLD-Final | 3/10/2014 | 3/10/2014 | 3/10/2014 | P | NR |
Jim Sly
|
|
|
Phil Phone #: ###-#### Need F/P final.
|
BLD-Energy code compliance | 11/6/2013 | 11/7/2013 | 11/7/2013 | A | PASS |
Jim Storey
|
|
|
Phil Phone #: ###-#### engineer letter pass isues/ truss co applied repair framing and insulation ok
|
BLD-Framing/Rough-in | 10/30/2013 | 10/30/2013 | 10/30/2013 | P | FAIL |
Jim Storey
|
|
|
Phil Phone #: ###-#### gider truss a4 in backwards need fix// pe to address header back porch/ redesign interior sheer by fire place// web braces a/a4// engineer field reviewed fab weld note plan review.
|
BLD-Wall Bracing | 10/10/2013 | 10/10/2013 | 10/10/2013 | P | PASS |
Tom Arcoraci
|
|
|
phil Phone #: ###-####
|
BLD-Foundation | 9/10/2013 | 9/10/2013 | 9/11/2013 | P | PASS |
Dave Hannah
|
|
|
Adam Phone #: ###-####
|
BLD-Footing | 9/6/2013 | 9/6/2013 | 9/6/2013 | P | PASS |
Dave Hannah
|
|
|
adam Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/26/2013 | | DONE |
|
|
|
|
OVERRIDE | | | 8/23/2013 | | |
|
|
|
|
Plan assigned to (AJS) | 7/26/2013 | 7/26/2013 | 8/23/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 8/8
|
Application received | | 7/25/2013 | 8/23/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/23/2013 | | 8/23/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Case Summary (BLD) | | | 8/23/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/23/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/23/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 8/23/2013 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 8/23/2013 | | DONE |
Tisha Gallop
|
|
|
called Sara Seidl and told her permit is ready and fee.
|
Plan resubmittals received | | | 8/22/2013 | | DONE |
Tisha Gallop
|
|
|
received two copies of response from engineer, structural calc, and full set of plans (sheets A0.0, A1.0, A1.1, A1.2, A1.3, A2.0, A2.1, S1.0, S1.1, S2.0, E1.0); taken to Adele.
|
Plan resubmittals received | | | 8/15/2013 | | DONE |
Tisha Gallop
|
|
|
received response letter and two copies of strucural calcs and plan sheets S1.0, A1.0, A1.2, A1.3, S1.1, S2.0; taken to Adele
|
Routing - PLAN CHECK | 8/5/2013 | | 8/7/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
email sent 8/7/13 see letter in documents
John,
I have completed the plan review for 3907 E Barber, BLD13-02038.
Please see the attached plan review letter. Please submit 2 sets of all revised sheets.
Please let me know if you have any questions.
Just so you know the status of all reviews. The mechanical review for this projected has failed.
Thank you
Adele J. Schaffeld-Griffin
City of Boise
Plans Examiner II
###-####
|
1st review completed | | | 8/7/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - MECHANICAL | 8/7/2013 | | 8/7/2013 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/6/2013 | | 8/6/2013 | | PASS |
Leon Letson
|
|
|
|
Routing - MECHANICAL | 7/30/2013 | | 8/5/2013 | | FAIL |
Dixie Fellows
|
|
|
wrong manual j submitted
|
Routing - PUBLIC WORKS | | | 7/30/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING | 7/30/2013 | | 7/30/2013 | | FAIL |
Leon Letson
|
|
|
Home does not meet the required front yard setback of 50' from the back of sidewalk. The letter of approval from the Harris Ranch Review Board must also be submitted.
|
Route to Impact Fee Review | 7/26/2013 | 7/31/2013 | 7/29/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Addressing | 7/26/2013 | | 7/29/2013 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 7/26/2013 | | PASS |
|
|
|
|
Intake Approval | | | 7/25/2013 | | FAIL |
Tisha Gallop
|
|
|
need engineered shear calcs and reduced site plan
|