Letter of compliance/Occupancy | | | 3/4/2015 | | DONE |
|
|
|
|
BLD-Final | 6/25/2014 | 6/25/2014 | 6/25/2014 | P | PASS |
Dave Hannah
|
|
|
Eric Phone #: ###-####
|
DOC - Permit Finaled | 6/25/2014 | 6/25/2014 | 6/25/2014 | P | PASS |
Dave Hannah
|
|
|
|
PubWorks Occupancy Approval | 6/25/2014 | 6/25/2014 | 6/25/2014 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Energy code compliance | 1/28/2014 | 1/29/2014 | 1/29/2014 | A | PASS |
Dave Hannah
|
|
|
eric Phone #: ###-####
|
BLD-Framing/Rough-in | 1/22/2014 | 1/22/2014 | 1/22/2014 | P | PASS |
Dave Hannah
|
|
|
eric Phone #: ###-####
|
Plan Modification Accepted | | | 12/9/2013 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 12/9/2013 | | 12/9/2013 | | PASS |
Troy James
|
|
|
resubmitted manaul j report
|
BLD-Foundation | 9/27/2013 | 9/30/2013 | 9/30/2013 | P | PASS |
Dave Hannah
|
|
|
BEN Phone #: ###-####
|
BLD-Footing | 9/20/2013 | 9/20/2013 | 9/20/2013 | P | PASS |
Dave Hannah
|
|
|
Ben Phone #: ###-####
|
PubWorks Subgrade Approval | 9/6/2013 | 9/6/2013 | 9/6/2013 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
(F) Reprint permit | | | 8/29/2013 | | DONE |
Christina Prado
|
|
|
|
Issue PAID IN FULL permit | | | 8/27/2013 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 8/20/2013 | | |
|
|
|
|
Plan assigned to (AJS) | 7/29/2013 | 7/29/2013 | 8/20/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Due 8/15 Hillside
|
Routing - PLAN CHECK | 8/20/2013 | | 8/20/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Case Summary (BLD) | | | 8/20/2013 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/20/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/20/2013 | | DONE |
|
|
|
|
Telephone call | | | 8/20/2013 | | DONE |
Christina Prado
|
|
|
called Robert to advise permit is ready and gave fees due
|
Permit Ready to Issue | | | 8/20/2013 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 8/16/2013 | | DONE |
Christina Prado
|
|
|
received two sets of revised structural calcs, back elevation details and foundation details(both 8 1/2 X11); Taken to Adele for review
|
1st review completed | | | 8/14/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
emailed comments to applicant 8/14/13
|
Routing - PLAN CHECK | 8/8/2013 | | 8/14/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see plan review comments in documents
|
Routing - MECHANICAL | 8/13/2013 | | 8/13/2013 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 8/8/2013 | | 8/8/2013 | | PASS |
Scott Arellano
|
|
|
Plans are approved as shown. No comments attached.
|
Routing - Erosion and Sediment | 8/7/2013 | | 8/8/2013 | | PASS |
Kimberly M. Johnson
|
|
|
|
Routing - MECHANICAL | 8/1/2013 | | 8/7/2013 | | FAIL |
Troy James
|
|
|
emailed corrections to Don Heating Supply
|
Routing PW Grading-Hillside | 8/5/2013 | | 8/6/2013 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. All compaction testing results must be submitted as well. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - PLANNING | 7/30/2013 | | 8/1/2013 | | PASS |
Joshua Johnson
|
|
|
|
Routing - PUBLIC WORKS | 7/30/2013 | | 7/30/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Route to Impact Fee Review | 7/29/2013 | 8/1/2013 | 7/29/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Addressing | 7/29/2013 | | 7/29/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Intake Approval | | | 7/29/2013 | | PASS |
|
|
|
|
Application received | | | 7/28/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 28 2013 5:27PM
|