Second Notice | | 3/10/2014 | 4/1/2014 | | DONE |
|
|
|
Mailed 4-1-14
|
First Notice | 2/13/2014 | 2/13/2014 | 2/28/2014 | | DONE |
Mike Jordan
|
|
|
mailed 2-28-14
|
BLD-Final | 2/12/2014 | 2/13/2014 | 2/13/2014 | A | PASS |
Mike Jordan
|
|
|
Al Huerta Phone #: ###-####
|
DOC - Permit Finaled | 2/13/2014 | 2/13/2014 | 2/13/2014 | P | PASS |
Mike Jordan
|
|
|
Certificate of completion issued.
|
FIRE-Final Inspection | 2/12/2014 | 2/12/2014 | 2/12/2014 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Framing/Rough-in | 2/5/2014 | 2/5/2014 | 2/5/2014 | P | PART |
Mike Jordan
|
|
|
Albert Phone #: ###-####. Interior steel stud walls for new storage room.
|
BLD-Framing/Rough-in | 2/4/2014 | 2/4/2014 | 2/4/2014 | P | PASS |
Mike Jordan
|
|
|
for phase 3 // Al Phone #: ###-####. Interior steel stud framed walls ok.
|
BLD-Framing/Rough-in | 1/28/2014 | 1/28/2014 | 1/28/2014 | P | PASS |
Mike Jordan
|
|
|
richard Phone #: ###-####. Phase 2 interior steel stud framed walls at north east portion of building and front column at main door. All screws were removed and and kickers added.
|
BLD-Framing/Rough-in | 1/27/2014 | 1/28/2014 | 1/28/2014 | A | FAIL |
Mike Jordan
|
|
|
phase 2 - Richard Phone #: ###-####. Rermove screws from grid to top plate and install kickers to structure above.
|
BLD-Framing/Rough-in | 1/16/2014 | 1/16/2014 | 1/16/2014 | P | PASS |
Mike Jordan
|
|
|
partial r/i for phase 1 // Richard Phone #: ###-####. interior steel stud walls for 5 way mirror dressing rooms, phase 1.
|
BLD-Framing/Rough-in | 1/8/2014 | 1/9/2014 | 1/9/2014 | A | PART |
Mike Jordan
|
|
|
phase 1 framing - Richard Phone #: ###-####. phase 1, interior steel stud framed walls for new storefront showcases. Pending electrical rough in inspection.
|
Issue PAID IN FULL permit | | | 1/3/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CDM) | 8/7/2013 | 8/7/2013 | 8/15/2013 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 8/7/2013 | | 8/15/2013 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 8/15/2013 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/15/2013 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 8/15/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/15/2013 | | DONE |
|
|
|
|
Telephone call | | | 8/15/2013 | | DONE |
Tisha Gallop
|
|
|
called David and told Spencer permit is ready, fee due and need GC.
|
Permit Ready to Issue | | | 8/15/2013 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/7/2013 | | DONE |
Tisha Gallop
|
|
|
|
Payment Received | | | 7/29/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/29/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 29 2013 5:00PM
|