BLD-Final | 5/5/2014 | 5/6/2014 | 5/6/2014 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 5/6/2014 | 5/6/2014 | 5/6/2014 | P | PASS |
Jim Storey
|
|
|
|
BLD-Blower Door Test Results | 5/6/2014 | 5/6/2014 | 5/6/2014 | P | DONE |
Jim Storey
|
|
|
2.9 Phone #: ###-#### >> Inspection requested via web by Clint Wall
|
PubWorks Occupancy Approval | 5/6/2014 | 5/6/2014 | 5/6/2014 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Final | 5/2/2014 | 5/5/2014 | 5/5/2014 | A | FAIL |
Jim Storey
|
|
|
Clint Phone #: ###-#### need public works/ 311.7.2 lights on stairs
|
BLD-Energy code compliance | 2/18/2014 | 2/20/2014 | 2/20/2014 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 2/18/2014 | 2/19/2014 | 2/19/2014 | A | PASS |
Jim Storey
|
|
|
Clint Phone #: ###-####
|
BLD-Framing/Rough-in | 2/17/2014 | 2/18/2014 | 2/18/2014 | A | FAIL |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Clint Wall
|
BLD-Other | 1/21/2014 | 1/22/2014 | 1/22/2014 | A | PASS |
Jim Sly
|
|
|
Fire can protection - Clint Phone #: ###-####
|
BLD-Wall Bracing | 1/13/2014 | 1/14/2014 | 1/14/2014 | A | PASS |
Jim Storey
|
|
|
Joey Phone #: ###-####
|
BLD-Wall Bracing | 1/7/2014 | 1/8/2014 | 1/8/2014 | A | PASS |
Jim Storey
|
|
|
joey Phone #: ###-####
|
BLD-Foundation | 10/10/2013 | 10/10/2013 | 10/10/2013 | P | PASS |
Jim Storey
|
|
|
avarlo Phone #: ###-####
|
BLD-Footing | 10/8/2013 | 10/8/2013 | 10/8/2013 | P | PASS |
Jim Storey
|
|
|
late as poss// Wes Phone #: ###-####
|
PubWorks Subgrade Approval | 9/30/2013 | 9/30/2013 | 9/30/2013 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 8/15/2013 | | DONE |
|
|
|
|
OVERRIDE | | | 8/12/2013 | | |
|
|
|
|
Plan assigned to (PEP) | 8/7/2013 | 8/7/2013 | 8/12/2013 | | DONE |
Perry Paine
|
|
|
|
Routing - PLAN CHECK | 8/12/2013 | | 8/12/2013 | | PASS |
Perry Paine
|
|
|
|
1st review completed | | | 8/12/2013 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/12/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/12/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/12/2013 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | | | 8/12/2013 | | PASS |
Perry Paine
|
|
|
|
Telephone call | | | 8/12/2013 | | DONE |
Tisha Gallop
|
|
|
called Tahoe Homes and left vm permit is ready and fee
|
Routing - FIRE | 8/12/2013 | | 8/12/2013 | | PASS |
Scott Arellano
|
|
|
No comments.
|
Routing - Erosion and Sediment | 8/8/2013 | | 8/9/2013 | | PASS |
Kimberly M. Johnson
|
|
|
ESC plan waived
|
Routing - MECHANICAL | 8/2/2013 | | 8/8/2013 | | PASS |
Troy James
|
|
|
|
Plan assigned to (AJS) | 7/30/2013 | 7/30/2013 | 8/7/2013 | | DEFR |
Adele J Schaffeld-Griffin
|
|
|
Due 8/16 Hillside
|
Route to Impact Fee Review | 7/30/2013 | 8/2/2013 | 8/2/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 8/2/2013 | | 8/2/2013 | | PASS |
David Moser
|
|
|
|
Routing - PUBLIC WORKS | 7/31/2013 | | 8/2/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Grading-Hillside | | | 8/1/2013 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit a letter approving the site grading and drainge must be recieved by the project engineer and the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - Addressing | 7/31/2013 | | 8/1/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Application received | | 7/30/2013 | 7/31/2013 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/30/2013 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/30/2013 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 7/30/2013 | | PASS |
Tisha Gallop
|
|
|
|