First Notice | | 11/24/2013 | 11/29/2013 | | DONE |
|
|
|
Faxed 11-29-13
|
Permanent Occupancy | | | 11/14/2013 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 11/13/2013 | 11/13/2013 | 11/13/2013 | P | PASS |
Mike Jordan
|
|
|
Ok for perm occ.
|
BLD-Final | 11/12/2013 | 11/13/2013 | 11/13/2013 | A | NR |
Mike Jordan
|
|
|
Charles Phone #: ###-####
|
FIRE-Final Inspection | 11/12/2013 | 11/12/2013 | 11/12/2013 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. I spoke to Mike Jordan about the manual lock on the main door inactive leaf.
|
BLD-Conference | 10/28/2013 | 10/29/2013 | 10/29/2013 | A | DONE |
Mike Jordan
|
|
|
Charles Phone #: ###-####
|
BLD-Framing/Rough-in | 9/27/2013 | 9/30/2013 | 9/30/2013 | P | PASS |
Tom Arcoraci
|
|
|
Charles Phone #: ###-####
|
BLD-Framing/Rough-in | 9/26/2013 | 9/27/2013 | 9/27/2013 | P | PART |
Jim Storey
|
|
|
Charles Phone #: ###-#### walls ok to back of store grid d/e area
|
Issue PAID IN FULL permit | | | 9/19/2013 | | DONE |
|
|
|
|
Plan assigned to (CDM) | | 8/5/2013 | 9/4/2013 | | PASS |
Carl D Madsen
|
|
|
|
Application received | | 8/1/2013 | 9/4/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/4/2013 | | 9/4/2013 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/4/2013 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/4/2013 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/4/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 9/4/2013 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 9/4/2013 | | DONE |
Tisha Gallop
|
|
|
called Amy Diekevers/applicant and left vm permit is ready and fee due.
|
Plan resubmittals received | | | 9/3/2013 | | DONE |
Christina Prado
|
|
|
received two sets of revised plan sheets marked A000, A101, A102, A103, A104, A303, A400, E-1, E-2, M-1, M-2 & P-1, as well as one response letter as lighting calcs;Plans and documents taken to Carl Madsen for further review
|
1st review completed | | | 8/16/2013 | | FAIL |
|
|
|
E-Mailed applicant
|
Routing - PLAN CHECK | 8/5/2013 | | 8/16/2013 | | FAIL |
Carl D Madsen
|
|
|
E-Mailed applicant
|
Routing - Addressing | 8/5/2013 | | 8/5/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | | | 8/5/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 8/5/2013 | | 8/5/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 8/5/2013 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/5/2013 | | DONE |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/5/2013 | | DONE |
Christina Prado
|
|
|
|