Routing PW Grading-Hillside | 9/3/2013 | | 9/3/2013 | | PASS |
Jason C. Taylor
|
|
|
Recieved civil engineers approval for grading and drainage. Public Works Hilllside must give approval before permit is finaled. Jason Taylor ###-####.
|
BLD-Foundation | 8/20/2013 | 8/20/2013 | 8/20/2013 | P | PART |
Tony Young
|
|
|
retaining wall - jay Phone #: ###-####,, work in progress,, rebar not in place yet within wall
|
BLD-Footing | 8/19/2013 | 8/20/2013 | 8/20/2013 | A | PART |
Tony Young
|
|
|
retaining wall - jay Phone #: ###-####,, wall ok
|
BLD-Footing | 8/14/2013 | 8/15/2013 | 8/15/2013 | A | PASS |
Tony Young
|
|
|
Jay Phone #: ###-####
|
PubWorks Subgrade Approval | 8/14/2013 | 8/14/2013 | 8/14/2013 | | DONE |
Jason C. Taylor
|
|
|
Recieved subgrade approval for footings. Building inspections may be scheduled. Jason Taylor ###-####
|
Issue PAID IN FULL permit | | | 8/5/2013 | | DONE |
|
|
|
|
OVERRIDE | | | 8/2/2013 | | |
|
|
|
|
Plan assigned to (PEP) | 8/2/2013 | 8/2/2013 | 8/2/2013 | | PASS |
Perry Paine
|
|
|
|
Application received | | 8/1/2013 | 8/2/2013 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 8/1/2013 | 8/1/2013 | 8/2/2013 | P | DONE |
Perry Paine
|
|
|
|
1st review completed | | | 8/2/2013 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/2/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/2/2013 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 8/2/2013 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 8/2/2013 | | DONE |
Tisha Gallop
|
|
|
called Jay and told him permit is ready and fee.
|
Routing Walk-In (PW Hillside) | 8/1/2013 | 8/1/2013 | 8/1/2013 | P | PASS |
Jason C. Taylor
|
|
|
Subgrade approval wil be required prior to scheduling of building department for footing inspections. Jason Taylor ###-####
Before occupancy is approved a letter from the civil engineer approving the site grading/drainage/slope stabilization must be submitted to Public Works. Jason Taylor ###-####
Before occupancy is approved a letter from the structural engineer approving the construction and drainage of the retaining wall must be submitted to Public Works. Jason Taylor ###-####
|
Routing Walk-In (Zoning) | 8/1/2013 | 8/1/2013 | 8/1/2013 | P | PASS |
Jason C. Taylor
|
|
|
|
Routing - Erosion and Sediment | 8/1/2013 | | 8/1/2013 | | PASS |
Kimberly M. Johnson
|
|
|
Waiver approved. Will need to schedule site prep
|