Third Notice | | 9/3/2014 | 10/9/2014 | | DONE |
|
|
|
This permit finaled on the web by Adam Johnson
|
Third Notice | | 6/14/2014 | 8/29/2014 | | DONE |
|
|
|
e-mailed to Adam Johnson
|
Third Notice | | 5/10/2014 | 6/9/2014 | | DONE |
|
|
|
e-mailed to Adam Johnson
|
Third Notice | | 4/6/2014 | 5/5/2014 | | DONE |
|
|
|
e-mailed to Adam Johnson
|
Second Notice | | 3/16/2014 | 4/1/2014 | | DONE |
|
|
|
e-mailed to Adam Johnson
|
First Notice | | 1/26/2014 | 3/6/2014 | | DONE |
|
|
|
|
BLD-Final | 1/16/2014 | 1/16/2014 | 1/16/2014 | P | PASS |
Jim Sly
|
|
|
13th floor final with Roger W. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson OK for Perm Occ.
|
FIRE-Final Inspection | 1/16/2014 | 1/16/2014 | 1/16/2014 | P | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
BLD-Final | 1/14/2014 | 1/15/2014 | 1/16/2014 | P | NR |
Dave Hannah
|
|
|
Final walk request by Roger Wilson, walk with Dave H. 13th Floor PB&L. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
Permanent Occupancy | | | 1/16/2014 | | DONE |
|
|
|
|
FIRE-Final Inspection | 1/14/2014 | 1/15/2014 | 1/15/2014 | A | PART |
Forrest France
|
|
|
Fire Final Prewalk with Forrest, requested by Roger Wilson, 13th Floor PB&L. Thanks AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Ceiling Grid Inspection | 12/11/2013 | 12/11/2013 | 12/12/2013 | P | PASS |
Dave Hannah
|
|
|
Ceiling cover inspection on 13th Floor PB&L, per Roger W. Thanks. akj Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 10/27/2013 | 10/28/2013 | 10/28/2013 | A | PASS |
Tom Arcoraci
|
|
|
Fireproof patch inspection requested per Roger Wilson, ESI, on 13th Floor. Thanks. Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Conference | 10/3/2013 | 10/4/2013 | 10/7/2013 | A | PASS |
Dave Hannah
|
|
|
Follow up from yesterday, conformation of FP at perimeter, thanks. Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 10/2/2013 | 10/3/2013 | 10/7/2013 | A | PASS |
Dave Hannah
|
|
|
Framing Inspection Thanks. Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
BLD-Framing/Rough-in | 10/1/2013 | 10/1/2013 | 10/7/2013 | P | PASS |
Dave Hannah
|
|
|
PB&L Framing Inspection, 13th Floor. Thanks. Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson
|
Issue PAID IN FULL permit | | | 9/13/2013 | | DONE |
Barbara Stitt
|
|
|
|
Print Occupancy Form | | | 9/13/2013 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 9/13/2013 | | DONE |
Barbara Stitt
|
|
|
|
CHANGE STATUS TO (ISS) | | | 9/13/2013 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (CJW) | 8/13/2013 | 8/13/2013 | 9/12/2013 | | PASS |
Carl Westfall
|
|
|
PARSONS, BEHLE & LATIMER (20 days - Sept 9) ePlanReview
|
Routing - FIRE | 9/12/2013 | | 9/12/2013 | | PASS |
Scott Arellano
|
|
|
Attached comments to case.
|
Routing - PLAN CHECK | 9/10/2013 | | 9/12/2013 | | PASS |
Carl Westfall
|
|
|
Drawings approved after the 3rd plan review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/12/2013 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/10/2013 | | |
|
|
|
|
Routing - PLAN CHECK | 9/5/2013 | | 9/9/2013 | | FAIL |
Carl Westfall
|
|
|
Items still not resolved. See the abbreviated 2nd review.
|
Plan resubmittals requested | | | 9/9/2013 | | |
|
|
|
|
Plan resubmittals received | | | 9/5/2013 | | DONE |
|
|
|
|
1st review completed | | | 8/28/2013 | | FAIL |
|
|
|
Failed Plan Check and Fire
|
Plan resubmittals requested | | | 8/28/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/13/2013 | | 8/28/2013 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on Aug 26 and finished on Aug 28. Revised drawings were required. See the plan review report and the markups on the drawings.
|
Routing - FIRE | 8/13/2013 | 8/13/2013 | 8/14/2013 | | FAIL |
Scott Arellano
|
|
|
Emailed resubmittal item to architect.
|
Routing - PLUMBING | 8/13/2013 | | 8/14/2013 | | PASS |
Bill VanDegrift
|
|
|
Per plan and ISPC.
|
Routing PW Sewer Rating | 8/14/2013 | | 8/14/2013 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | 8/13/2013 | | 8/14/2013 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 8/13/2013 | | 8/14/2013 | | PASS |
Beverly Mountain
|
|
|
|
Payment Received | | | 8/13/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Intake Approval | | | 8/13/2013 | | PASS |
Jason Blais
|
|
|
Prescreen passed and Plan Review Fees paid.
|
Pending Assignment by JCB | 8/13/2013 | | 8/13/2013 | | DONE |
Jason Blais
|
|
|
|
Application received | | | 8/1/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 1 2013 5:22PM
|