Permit Information
Permit NumberBLD13-02112
StatusFinaled
Name ESI
Site Address 800 W MAIN ST Unit: 1300
Project NameParsons, Behle and Latimer
Customer Number 
ePlanReviewYes
Description
(PARSONS, BEHLE & LATIMER - 8TH & MAIN BUILDING - 13TH STORY) The fire sprinkler system is used for high-rise. To construct a 15,535 square foot whole story office tenant space located on the 13th story of a high-rise building. There are 2 egress areas. One has a floor area of about 3,175 square feet and one has a floor area of about 12,360 square feet. Work is to include interior nonbearing walls, interior windows, interior doors, suspended acoustical ceilings, gypsum board soffits, millwork, and finishes. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 9/3/201410/9/2014 DONE
This permit finaled on the web by Adam Johnson
Third Notice 6/14/20148/29/2014 DONE
e-mailed to Adam Johnson
Third Notice 5/10/20146/9/2014 DONE
e-mailed to Adam Johnson
Third Notice 4/6/20145/5/2014 DONE
e-mailed to Adam Johnson
Second Notice 3/16/20144/1/2014 DONE
e-mailed to Adam Johnson
First Notice 1/26/20143/6/2014 DONE
BLD-Final1/16/20141/16/20141/16/2014PPASS
DetailsJim Sly
13th floor final with Roger W. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
OK for Perm Occ.
FIRE-Final Inspection1/16/20141/16/20141/16/2014PPASS
DetailsForrest France
Fire life safety finaled.
BLD-Final1/14/20141/15/20141/16/2014PNR
DetailsDave Hannah
Final walk request by Roger Wilson, walk with Dave H. 13th Floor PB&L. Thanks. AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
Permanent Occupancy  1/16/2014 DONE
FIRE-Final Inspection1/14/20141/15/20141/15/2014APART
DetailsForrest France
Fire Final Prewalk with Forrest, requested by Roger Wilson, 13th Floor PB&L. Thanks AKJ Phone #: ###-#### >> Inspection requested via web by Adam Johnson
BLD-Ceiling Grid Inspection12/11/201312/11/201312/12/2013PPASS
DetailsDave Hannah
Ceiling cover inspection on 13th Floor PB&L, per Roger W. Thanks. akj Phone #: ###-#### >> Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in10/27/201310/28/201310/28/2013APASS
DetailsTom Arcoraci
Fireproof patch inspection requested per Roger Wilson, ESI, on 13th Floor. Thanks. Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson
BLD-Conference10/3/201310/4/201310/7/2013APASS
DetailsDave Hannah
Follow up from yesterday, conformation of FP at perimeter, thanks. Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in10/2/201310/3/201310/7/2013APASS
DetailsDave Hannah
Framing Inspection Thanks. Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in10/1/201310/1/201310/7/2013PPASS
DetailsDave Hannah
PB&L Framing Inspection, 13th Floor. Thanks. Adam Phone #: ###-#### >> Inspection requested via web by Adam Johnson
Issue PAID IN FULL permit  9/13/2013 DONE
DetailsBarbara Stitt
Print Occupancy Form  9/13/2013 DONE
DetailsBarbara Stitt
Permit Ready to Issue  9/13/2013 DONE
DetailsBarbara Stitt
CHANGE STATUS TO (ISS)  9/13/2013 DONE
DetailsBarbara Stitt
Plan assigned to (CJW)8/13/20138/13/20139/12/2013 PASS
DetailsCarl Westfall
PARSONS, BEHLE & LATIMER (20 days - Sept 9) ePlanReview
Routing - FIRE9/12/2013 9/12/2013 PASS
DetailsScott Arellano
Attached comments to case.
Routing - PLAN CHECK9/10/2013 9/12/2013 PASS
DetailsCarl Westfall
Drawings approved after the 3rd plan review
PLANS/APPL TAKEN TO FRONT DESK  9/12/2013 DONE
Plan resubmittals received  9/10/2013  
Routing - PLAN CHECK9/5/2013 9/9/2013 FAIL
DetailsCarl Westfall
Items still not resolved. See the abbreviated 2nd review.
Plan resubmittals requested  9/9/2013  
Plan resubmittals received  9/5/2013 DONE
1st review completed  8/28/2013 FAIL
Failed Plan Check and Fire
Plan resubmittals requested  8/28/2013 DONE
Routing - PLAN CHECK8/13/2013 8/28/2013 FAIL
DetailsCarl Westfall
The IBC plan review was started on Aug 26 and finished on Aug 28. Revised drawings were required. See the plan review report and the markups on the drawings.
Routing - FIRE8/13/20138/13/20138/14/2013 FAIL
DetailsScott Arellano
Emailed resubmittal item to architect.
Routing - PLUMBING8/13/2013 8/14/2013 PASS
DetailsBill VanDegrift
Per plan and ISPC.
Routing PW Sewer Rating8/14/2013 8/14/2013 PASS
DetailsBeverly Mountain
Routing - Addressing8/13/2013 8/14/2013 PASS
DetailsEmily Dixon
Routing - PUBLIC WORKS8/13/2013 8/14/2013 PASS
DetailsBeverly Mountain
Payment Received  8/13/2013 DONE
Payment received via Govolutions
Intake Approval  8/13/2013 PASS
DetailsJason Blais
Prescreen passed and Plan Review Fees paid.
Pending Assignment by JCB8/13/2013 8/13/2013 DONE
DetailsJason Blais
Application received  8/1/2013 DONE
Application submitted via PDS Online on Aug 1 2013 5:22PM