Permit Information
Permit NumberBLD13-02128
StatusFinaled
Name HC COMPANY INC
Site Address 1114 W FRONT ST
Project NameWOODLAND EMPIRE ALE CRAFT
Customer Number 
ePlanReviewNo
Description
(WOODLAND EMPIRE ALE CRAFT) This building does not have a fire sprinkler system. To remodel an existing 8,641 square foot building for a brewery with tasting room. The occupant load of the entire building will exceed 100. To avoid installing a fire sprinkler system, two fire areas will be created. The A-2 fire area will have a floor area of about 1,465 square feet and an occupant load of 71. The F-1, S-1, and B fire area will have a floor area of about 7,176 square feet and an occupant load of 52. Work is to include 3-hr fire barrier walls, 3-hr fire doors, a 1-hr incidental use separation with a 60 minute fire door, 2 restrooms accessible to the disabled, interior nonbearing walls, interior doors, new exterior windows, new exterior doors, an alcove at an exterior door, a new awning, a parking space accessible to the disabled, and new exterior landings at doors. Special Inspection is required for welding and masonry anchors. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 2/7/20142/4/2014 DONE
This permit finaled on the web by Jeremy Barber
First Notice 1/19/20141/28/2014 DONE
BLD-Final1/9/20141/9/20141/10/2014PPASS
DetailsDave Hannah
Late afternoon, please call ahead - Steve Phone #: ###-####
Zoning Approval1/9/20141/9/20141/9/2014 DONE
DetailsAndrea Tuning
Permanent Occupancy  1/9/2014 DONE
DetailsTisha Gallop
FIRE-Final Inspection12/5/201312/6/201312/6/2013APASS
DetailsCraig D. Hanson
Railing in Brew area needs to be more secure.
BLD-Conference12/3/201312/3/201312/4/2013PPEND
DetailsDave Hannah
Steve-Please call prior to insepction 15-20 mins Phone #: ###-#### walked bldg 3hr door and wall infills ok
BLD-Other11/7/201311/7/201311/7/2013PCANC
DetailsDave Hannah
Fire taping-Steve Phone #: ###-#### one hour ceiling in heater room and 3hr fill ins ok
BLD-Framing/Rough-in11/4/201311/5/201311/5/2013APASS
DetailsDave Hannah
steve Phone #: ###-####
BLD-Framing/Rough-in10/31/201311/1/201311/1/2013PPART
DetailsDave Hannah
Steve Phone #: ###-#### ok to cover rest rooms
BLD-Other10/8/201310/9/201310/9/2013ACANC
DetailsDave Hannah
steve Phone #: ###-####
Issue PAID IN FULL permit  9/19/2013 DONE
DetailsChristina Prado
Plan assigned to (CJW)8/5/20138/5/20138/29/2013 PASS
DetailsCarl Westfall
WOODLAND EMPIRE ALE CRAFT (20 days - Aug 30)
Routing - PLAN CHECK8/21/2013 8/29/2013 PASS
DetailsCarl Westfall
Drawings approved after the 2nd plan review
PLANS/APPL TAKEN TO FRONT DESK  8/29/2013 DONE
Print Occupancy Form  8/29/2013 DONE
DetailsChristina Prado
Permit Ready to Issue  8/29/2013  
Plan resubmittals received  8/23/2013 DONE
rec'd copies of transmittal/response letter, calcs, and sheets A0.0; A0.1; A2.0; A2.2; E2.0L; E3.1; M0.0; M2.1 - taken to CW
Routing - FIRE8/16/20138/16/20138/21/2013 PASS
DetailsScott Arellano
Attached IFC comments to plans.
1st review completed  8/21/2013 FAIL
Failed Plan Check
Route to Impact Fee Review8/16/20138/21/20138/16/2013 PASS
DetailsCindy M. Gould
Tenant improvement no impact fees
Routing - PLAN CHECK8/9/2013 8/16/2013 FAIL
DetailsCarl Westfall
The IBC plan review was started on Aug 9 and was finished on Aug 16. Revised drawings were required. See the plan review report.
Routing - Design Review  8/9/2013 PASS
DetailsAndrea Tuning
Andrea Tuning - CZC13-00174
Routing - PLUMBING8/8/2013 8/8/2013 PASS
DetailsBill VanDegrift
per plans and ISPC
Routing PW Solid Waste8/7/2013 8/8/2013 PASS
DetailsPeter J. McCullough
Alley service only.
Routing PW Sewer Rating8/6/2013 8/8/2013 PASS
DetailsConnie Baumgartner
Routing - PUBLIC WORKS  8/8/2013 PASS
Routing - Erosion and Sediment8/8/2013 8/8/2013 PASS
DetailsKimberly M. Johnson
waiver approved
Routing PW Environmental8/6/2013 8/7/2013 PASS
DetailsWalt Baumgartner
Reviewed by Terry Alber - comments below

No food, No grease abatement required.
Plan resubmittals received  8/7/2013  
Received 2 copies of sheets Cover sheet, A1.0, M3.1, M3.2 inserted by architects office
Plan Reviewer's activity  8/6/2013 DONE
DetailsJason Blais
Emailed architect to have him contact ACHD for evaluation of any impact fees due. Our Permit Counter will need written verification from ACHD prior to the building permit being issued.
Routing - Addressing8/6/2013 8/6/2013 PASS
DetailsJason C. Taylor
Application received 8/5/20138/5/2013 DONE
DetailsBarbara Stitt
Intake Approval  8/5/2013 PASS
Plans ACCEPTED BY PLAN TECH  8/5/2013 DONE
DetailsChristina Prado
Recd Pcfee & Taken To Pln CK  8/5/2013 DONE
DetailsChristina Prado
Pending Assignment by JCB8/5/2013 8/5/2013 DONE
DetailsJason Blais