Second Notice | | 12/9/2013 | 12/4/2013 | | DONE |
Christina Prado
|
|
|
completed 12-04-2013 pdf
|
First Notice | | 11/1/2013 | 11/29/2013 | | DONE |
Christina Prado
|
|
|
mailed 12-2-13
|
BLD-Final | 10/21/2013 | 10/22/2013 | 10/22/2013 | A | PASS |
Tom Arcoraci
|
|
|
was signed temp occ ok for perm occ
|
Permanent Occupancy | | | 10/22/2013 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 10/20/2013 | 10/21/2013 | 10/21/2013 | A | PASS |
Tom Arcoraci
|
|
|
Phone #: ###-#### >> Inspection requested via web by derek cooper ok for perm occ
|
FIRE-Final Inspection | 10/21/2013 | 10/21/2013 | 10/21/2013 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
FIRE-Final Inspection | 10/20/2013 | 10/21/2013 | 10/21/2013 | A | FAIL |
Troy Cobbley
|
|
|
Need city approved plans, sticker at main exit, tag on fire extinguisher, battery backup for the exit sign at the main exit and approved single action hardware on the north exit door.
|
FIRE-Final Inspection | 10/18/2013 | 10/18/2013 | 10/18/2013 | P | CANC |
Troy Cobbley
|
|
|
Not ready for a final the contractor needed a cover inspection for the fire sprinklers
|
BLD-Ceiling Grid Inspection | 10/18/2013 | 10/18/2013 | 10/18/2013 | P | PASS |
Tom Arcoraci
|
|
|
derek Phone #: ###-####
|
BLD-Framing/Rough-in | 9/25/2013 | 9/26/2013 | 9/26/2013 | P | PASS |
Jim Sly
|
|
|
Derek Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 9/16/2013 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Issue PAID IN FULL permit | | | 9/16/2013 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/16/2013 | | DONE |
|
|
|
|
CHANGE STATUS TO (RDY) | | | 9/16/2013 | | DONE |
|
|
|
need to pay ACHD
|
CHANGE Issued DATE | | | 9/16/2013 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 8/20/2013 | 8/20/2013 | 8/29/2013 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 8/29/2013 | | 8/29/2013 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/29/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/29/2013 | | DONE |
Alexandra L. DeYoung
|
|
|
|
1st review completed | | | 8/28/2013 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 8/20/2013 | | 8/28/2013 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - FIRE | 8/20/2013 | 8/20/2013 | 8/21/2013 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans.
|
Routing PW Sewer Rating | 8/20/2013 | | 8/20/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 8/20/2013 | | 8/20/2013 | | PASS |
Emily Dixon
|
|
|
This building has multiple addresses. The overall parcel address is 234 S Whisperwood Way; however, the address listed on the plans (232 S Whisperwood Way) is correct for their portion of the building.
|
Routing - PUBLIC WORKS | 8/20/2013 | | 8/20/2013 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 8/20/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Payment Received | | | 8/19/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Intake Approval | | | 8/16/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please re name each sheet with approved conventional naming, this included P,M and E sheets. A1.0-Floor Plan
|
Application received | | | 8/12/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 12 2013 1:09PM
|