First Notice | | 11/2/2013 | 10/24/2013 | | DONE |
|
|
|
|
Permanent Occupancy | | | 10/23/2013 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 10/22/2013 | 10/22/2013 | 10/22/2013 | P | PASS |
Mike Jordan
|
|
|
Phone #: 208869911 >> Inspection requested via mobile web by Carrie. ok for perm occ.
|
FIRE-Final Inspection | 10/22/2013 | 10/22/2013 | 10/22/2013 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 10/18/2013 | 10/21/2013 | 10/21/2013 | P | PART |
Mike Jordan
|
|
|
Phone #: 208869911 >> Inspection requested via mobile web by Carrie. Ok for temp oc.
|
FIRE-Final Inspection | 10/18/2013 | 10/21/2013 | 10/21/2013 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy is being given with scotts approval until the revised wall/exiting plan is resubmitted for tims review. All other items passed.
|
BLD-Conference | 10/15/2013 | 10/16/2013 | 10/16/2013 | A | DONE |
Mike Jordan
|
|
|
Phone #: 208869911 >> Inspection requested via mobile web by Carrie
|
BLD-Framing/Rough-in | 9/23/2013 | 9/24/2013 | 9/24/2013 | P | PASS |
Tom Arcoraci
|
|
|
As late as possible Phone #: 208869911 >> Inspection requested via mobile web by Carrie
|
BLD-Framing/Rough-in | 9/17/2013 | 9/18/2013 | 9/18/2013 | A | PART |
Mike Jordan
|
|
|
Phone #: 208869911 >> Inspection requested via mobile web by Carrie. ok to one side and pre rock rear enterance to build lid.
|
FIRE-Conference | 9/9/2013 | 9/10/2013 | 9/10/2013 | A | DONE |
Craig D. Hanson
|
|
|
space has no smoke control system. Plans submited do not match existing. Client will send pictures of space to Building for review.
|
Permit Ready to Issue | | | 9/6/2013 | | DONE |
Christina Prado
|
|
|
Emailed Carrie at CSDI fees due
|
Print Occupancy Form | | | 9/6/2013 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/6/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/4/2013 | | 9/4/2013 | | PASS |
Tim L. Woodard
|
|
|
BLD13-02159 resubmitted drawings illistrating how the smoke evacuation system will be tied into this space. With that submittal it was determined this space can be released to build. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/4/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 9/4/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 8/19/2013 | | 9/4/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 8/19/2013 | | 8/28/2013 | | PASS |
Tim L. Woodard
|
|
|
Cannot approve intil shell permit to create this space is approved. TLW
|
1st review completed | | | 8/28/2013 | | DONE |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 8/19/2013 | | PASS |
Tim L. Woodard
|
|
|
|
Payment Received | | | 8/16/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 8/13/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 13 2013 2:51PM
|