Permit Information
Permit NumberBLD13-02219
StatusFinaled
Name WOOD RIVER BUILDERS
Site Address 880 N RIVER PATH LANE
Project Name880 river path
Customer Number 
ePlanReviewYes
Description
Permit for the construction of a new 1892 sq. ft., two story (first story 1306 sq. ft., second story 586 sq. ft.) single family dwelling with 3 bedrooms, 2.5 bathrooms, approximately 46 sq. ft. of covered patio/porch and a 660 sq. ft. attached garage per the approved plans, plan review report and any notations. R-1C zoning and setbacks per planning. JG
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/2/20141/3/20141/3/2014APASS
DetailsTony Young
Bobby Phone #: ###-####
DOC - Permit Finaled1/3/20141/3/20141/3/2014PPASS
DetailsTony Young
c of o issued
BLD-Conference11/6/201311/6/201311/6/2013PPASS
DetailsTom Arcoraci
call when on way to meet // Bobby Phone #: ###-#### alcove at landing ok for decorations
BLD-Energy code compliance10/7/201310/8/201310/8/2013PPASS
DetailsTony Young
Bobby Phone #: ###-####
BLD-Framing/Rough-in10/7/201310/7/201310/7/2013PPASS
DetailsTony Young
late pm please// Bobby Phone #: ###-####,, will need tempered glass on the front windows w/in 18" of the floor
Plan resubmittals received  9/30/2013 DONE
new manual j
Routing - MECHANICAL9/30/2013 9/30/2013 PASS
DetailsTroy James
resubmitted manual j
BLD-Wall Bracing9/23/20139/24/20139/24/2013APASS
DetailsTony Young
Bobby Phone #: ###-####
BLD-Footing9/5/20139/5/20139/5/2013PPASS
DetailsTony Young
pat Phone #: ###-####
Issue PAID IN FULL permit  8/28/2013 DONE
DetailsChristina Prado
Plan assigned to (JG)8/22/20138/22/20138/27/2013 PASS
DetailsJavier Guzman
1st review complete eplan
Routing - MECHANICAL8/27/2013 8/27/2013 PASS
DetailsTroy James
Routing - PLAN CHECK8/27/2013 8/27/2013 PASS
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  8/27/2013 DONE
Inspection Record Card- Bld  8/27/2013 DONE
Permit Ready to Issue  8/27/2013  
Routing - PLAN CHECK8/26/2013 8/26/2013 FAIL
DetailsJavier Guzman
need new Manual JDS orientation moved
Routing - PLAN CHECK8/14/2013 8/23/2013 PASS
DetailsJavier Guzman
PRJ DOX CASE
1st review completed  8/23/2013 FAIL
DetailsJavier Guzman
failed pending planning resubmital JG
Routing - PLANNING8/14/2013 8/23/2013 PASS
DetailsColleen T Carroll
Plan assigned to (CDM)8/14/20138/14/20138/22/2013 DEFR
DetailsCarl D Madsen
PRJ DOX CASE
Routing - MECHANICAL8/14/2013 8/21/2013 PASS
DetailsTroy James
Route to Impact Fee Review8/14/20138/19/20138/16/2013 PASS
DetailsCindy M. Gould
Routing - PUBLIC WORKS8/14/2013 8/15/2013 PASS
DetailsBeverly Mountain
Payment Received  8/14/2013 DONE
Payment received via Govolutions
Application received  8/14/2013 DONE
Application submitted via PDS Online on Aug 14 2013 11:15AM
Intake Approval  8/14/2013 PASS
DetailsBarbara Stitt
Routing - Addressing8/14/2013 8/14/2013 PASS
DetailsEmily Dixon