Plan Reviewer's activity | | | 7/11/2014 | | DONE |
Javier Guzman
|
|
|
i never recieved the resubmitals requested on 3-10-2014 of the 500 sq. ft. modified crawl space turned into a storage space, i conclude that all the issues and review were done in the field by the field inspector since this project has been finaled out and completed.
|
Letter of compliance/Occupancy | | | 5/19/2014 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 5/5/2014 | 5/6/2014 | 5/6/2014 | A | PASS |
Tony Young
|
|
|
|
DOC - Permit Finaled | 5/6/2014 | 5/6/2014 | 5/6/2014 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 5/2/2014 | 5/5/2014 | 5/5/2014 | A | NR |
Tony Young
|
|
|
Jeff Phone #: ###-####
|
PubWorks Occupancy Approval | 5/5/2014 | 5/5/2014 | 5/5/2014 | | DONE |
Jason C. Taylor
|
|
|
Bond posted for drainage channel. Jason Taylor ###-####.
|
BLD-Final | 5/1/2014 | 5/2/2014 | 5/2/2014 | A | CANC |
Jim Sly
|
|
|
jess Phone #: ###-#### Contr cancelled.....Need HVAC final.
|
BLD-Energy code compliance | 3/14/2014 | 3/17/2014 | 3/17/2014 | A | PASS |
Tony Young
|
|
|
jeff Phone #: ###-####
|
BLD-Energy code compliance | 3/14/2014 | 3/14/2014 | 3/14/2014 | P | DONE |
Tony Young
|
|
|
jeff Phone #: ###-####
|
BLD-Energy code compliance | 3/13/2014 | 3/14/2014 | 3/14/2014 | A | DONE |
Tony Young
|
|
|
jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 3/13/2014 | 3/13/2014 | 3/13/2014 | P | PART |
Tony Young
|
|
|
jeff Phone #: ###-####,, need fire blocks,,ok to insulate
|
BLD-Framing/Rough-in | 3/12/2014 | 3/13/2014 | 3/13/2014 | A | PASS |
Tony Young
|
|
|
Jeff Phone #: ###-####,, basement room ok to insulate
|
Telephone call | | | 3/10/2014 | | DONE |
Javier Guzman
|
|
|
called Shane Jayo then emailed on 3/10/2014 left message then emailed shane a request for plans showing type of floor and wall framing type, floor and wall insulation type, how you are venting the under floor area, vapor barrier, wood needing protection from decay, for new added basement storage.
|
Plan resubmittals received | | | 3/6/2014 | | DONE |
Tisha Gallop
|
|
|
received two copies of floor plan; taken to Javier
|
BLD-Energy code compliance | 2/11/2014 | 2/12/2014 | 2/12/2014 | A | PART |
Tony Young
|
|
|
Jeff Phone #: ###-####,, ok to cover all except the fireplace (pending elec. pass), and new area (pending permit issue change)
|
BLD-Energy code compliance | 2/10/2014 | 2/11/2014 | 2/11/2014 | A | NR |
Tony Young
|
|
|
Jeff Phone #: ###-####,, need to fill in some areas.. need elec fix done,, fire block top of chase
|
BLD-Energy code compliance | 2/10/2014 | 2/10/2014 | 2/10/2014 | P | PEND |
Tony Young
|
|
|
Jeff Phone #: ###-####
|
BLD-Conference | 2/5/2014 | 2/5/2014 | 2/5/2014 | P | PART |
Tony Young
|
|
|
jeff Phone #: ###-####,, on site with 2 plan reviewers
|
BLD-Framing/Rough-in | 2/4/2014 | 2/5/2014 | 2/5/2014 | A | PART |
Tony Young
|
|
|
jeff Phone #: ###-####,, ok to insulate main house area.. NOT new area.. need fire blocking etc.
|
BLD-Framing/Rough-in | 2/3/2014 | 2/4/2014 | 2/4/2014 | A | PEND |
Tony Young
|
|
|
jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 2/3/2014 | 2/3/2014 | 2/3/2014 | P | FAIL |
Tony Young
|
|
|
jeff Phone #: ###-####,, correction posted
|
BLD-Framing/Rough-in | 1/31/2014 | 2/3/2014 | 2/3/2014 | A | NR |
Tony Young
|
|
|
|
BLD-Energy code compliance | 1/31/2014 | 1/31/2014 | 1/31/2014 | P | NR |
Tony Young
|
|
|
jeff Phone #: ###-####,, need plans approved for change in floor area
|
PubWorks Occupancy Approval | 1/28/2014 | 1/28/2014 | 1/28/2014 | | FAIL |
Jason C. Taylor
|
|
|
Hillside drainage catchment swale must be repaired prior to occupancy approval. Call Jason Taylor at ###-####.
|
BLD-Framing/Rough-in | 1/10/2014 | 1/13/2014 | 1/13/2014 | A | NR |
Tony Young
|
|
|
dave Phone #: ###-####
|
BLD-Energy code compliance | 1/6/2014 | 1/10/2014 | 1/10/2014 | A | NR |
Tony Young
|
|
|
dave Phone #: ###-####
|
BLD-Framing/Rough-in | 1/6/2014 | 1/10/2014 | 1/10/2014 | A | NR |
Tony Young
|
|
|
dave Phone #: ###-####
|
BLD-Wall Bracing | 1/2/2014 | 1/3/2014 | 1/3/2014 | P | NR |
Tony Young
|
|
|
Jeff Phone #: ###-####,, conf only
|
BLD-Conference | 1/2/2014 | 1/3/2014 | 1/3/2014 | A | PART |
Tony Young
|
|
|
Jeff Phone #: ###-####,, ?? on job,, may add some area underfloor,, needs to see plan review
|
BLD-Conference | 1/2/2014 | 1/2/2014 | 1/2/2014 | P | CANC |
Tony Young
|
|
|
Jeff Phone #: ###-####
|
BLD-Conference | 12/31/2013 | 1/2/2014 | 1/2/2014 | A | CANC |
Tony Young
|
|
|
Jeff Phone #: ###-####
|
BLD-Wall Bracing | 12/31/2013 | 1/2/2014 | 1/2/2014 | A | CANC |
Tony Young
|
|
|
Jeff Phone #: ###-####
|
BLD-Wall Bracing | 12/30/2013 | 12/31/2013 | 12/31/2013 | A | NR |
Tony Young
|
|
|
Jeff Phone #: ###-####
|
BLD-Wall Bracing | 12/27/2013 | 12/30/2013 | 12/30/2013 | A | PART |
Tony Young
|
|
|
Jeff Phone #: ###-####,, exterior ok after re doing areas painted
|
BLD-Foundation | 10/17/2013 | 10/18/2013 | 10/18/2013 | A | PART |
Tony Young
|
|
|
pat Phone #: ###-####,, ok to pour
|
BLD-Foundation | 10/17/2013 | 10/17/2013 | 10/17/2013 | P | PART |
Tony Young
|
|
|
pat Phone #: ###-####,, work in progress,, ok
|
BLD-Foundation | 10/11/2013 | 10/16/2013 | 10/17/2013 | A | PART |
Tony Young
|
|
|
pat Phone #: ###-####
|
BLD-Other | 10/15/2013 | 10/15/2013 | 10/15/2013 | P | PART |
Tony Young
|
|
|
pat Phone #: ###-####,, rebar in basement wall
|
BLD-Footing | 10/10/2013 | 10/11/2013 | 10/11/2013 | A | PASS |
Tony Young
|
|
|
pat Phone #: ###-####
|
PubWorks Subgrade Approval | 10/11/2013 | 10/11/2013 | 10/11/2013 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the basement and residence footings subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 10/1/2013 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 9/3/2013 | | |
|
|
|
|
Plan assigned to (JG) | 9/3/2013 | 9/3/2013 | 9/3/2013 | | PASS |
Javier Guzman
|
|
|
Due 9/4 Hillside
|
1st review completed | | | 9/3/2013 | | DONE |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 9/3/2013 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/3/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/3/2013 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 9/3/2013 | | DONE |
Christina Prado
|
|
|
called Shane to advise permit is ready for pick up and gave fees due
|
Permit Ready to Issue | | | 9/3/2013 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 8/28/2013 | | 9/3/2013 | | PASS |
Javier Guzman
|
|
|
|
Routing - Erosion and Sediment | 8/30/2013 | | 8/30/2013 | | PASS |
Jason C. Taylor
|
|
|
See ESC Permit for details.
|
Routing - FIRE | 8/22/2013 | | 8/28/2013 | | PASS |
Scott Arellano
|
|
|
No comments.
|
Plan resubmittals received | | | 8/22/2013 | | DONE |
|
|
|
|
Routing - MECHANICAL | 8/21/2013 | | 8/22/2013 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/20/2013 | | 8/21/2013 | | PASS |
Susan Riggs
|
|
|
|
Routing - PUBLIC WORKS | 8/19/2013 | | 8/20/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Grading-Hillside | | | 8/19/2013 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Hillside drainage catchment swale must be repaired prior to occupancy approval. Call Jason Taylor at ###-####.
|
Routing - Addressing | 8/15/2013 | | 8/19/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - Erosion and Sediment | | | 8/19/2013 | | FAIL |
Jason C. Taylor
|
|
|
Need two sets of full size plans to review. Jason Taylor ###-####
|
Route to Impact Fee Review | 8/15/2013 | 8/20/2013 | 8/16/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/16/2013 | | DONE |
|
|
|
|
Intake Approval | | | 8/16/2013 | | PASS |
|
|
|
|
Plan assigned to (AJS) | 8/15/2013 | 8/15/2013 | 8/15/2013 | | DEFR |
Adele J Schaffeld-Griffin
|
|
|
Due 9/4 Hillside
|
Application received | | 8/15/2013 | 8/15/2013 | | DONE |
|
|
|
|