Print Statement | | | 9/23/2014 | | DONE |
|
|
|
|
Print Statement | | | 7/17/2014 | | DONE |
Christina Prado
|
|
|
|
Second Notice | | 6/15/2014 | 7/9/2014 | | DONE |
|
|
|
|
First Notice | | 5/10/2014 | 6/5/2014 | | DONE |
Christina Prado
|
|
|
|
Permanent Occupancy | | | 4/30/2014 | | DONE |
Christina Prado
|
|
|
|
Zoning Approval | 4/24/2014 | 4/24/2014 | 4/24/2014 | | PASS |
Josh Wilson
|
|
|
Landscaping complete. Bond ok for release.
|
BLD-Final | 1/31/2014 | 2/3/2014 | 2/3/2014 | A | PASS |
Mike Jordan
|
|
|
marcus Phone #: ###-####. ok for temp. occ. Will be ok for perm occ. once zoning signs perm.
|
FIRE-Final Inspection | 1/31/2014 | 2/3/2014 | 2/3/2014 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
Temporary Occupancy | 2/3/2014 | 5/4/2014 | 2/3/2014 | | DONE |
Darla L Downs
|
|
|
|
Zoning Approval Temp | 2/3/2014 | 2/3/2014 | 2/3/2014 | | PASS |
Josh Wilson
|
|
|
90-day temp occ. Bond is in place. JGW
|
FIRE-Conference | 1/14/2014 | 1/15/2014 | 1/15/2014 | A | DONE |
Troy Cobbley
|
|
|
I went over life safety requirements with Marcus, the owner. One additional exit discharge light is needed at the northwest exit door, additional fire extinguishers for the seating area and a K class for the kitchen. It appears that a sprinkler monitoring system is required but its existance on site could not be verified, Marcus is going to follow up. The new kitchen hood suppression system will need to be connected to this fire alarm system as well as a separate permit for the work. The fire sprinkler permit still needs to be finaled and the fire suppression permit needs to be tested and finaled. All other items appear to be ok.
|
BLD-Conference | 1/14/2014 | 1/15/2014 | 1/15/2014 | A | DONE |
Mike Jordan
|
|
|
DAVE Phone #: ###-####
|
BLD-Framing/Rough-in | 1/15/2014 | 1/15/2014 | 1/15/2014 | A | PASS |
Mike Jordan
|
|
|
DAVE Phone #: ###-####
|
OVERRIDE | | | 9/13/2013 | | |
|
|
|
|
Plan assigned to (SRZ) | 8/19/2013 | 8/19/2013 | 9/13/2013 | | PASS |
Sam Zahorka
|
|
|
1st review completed. ePlanReview - Edge Brewery
|
Issue PAID IN FULL permit | | | 9/13/2013 | | DONE |
Barbara Stitt
|
|
|
|
Print Occupancy Form | | | 9/13/2013 | | DONE |
Barbara Stitt
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/13/2013 | | DONE |
Sam Zahorka
|
|
|
|
Permit Ready to Issue | | | 9/13/2013 | | DONE |
Christina Prado
|
|
|
Ready pending RP info - owners went to get signed up and will be back in shortly 9/13 11:20AM
|
Routing - PLANNING | 9/3/2013 | | 9/12/2013 | | PASS |
David Moser
|
|
|
CZC13-00203 was approved for the new dumpster enclosure.
|
Routing - FIRE | 9/3/2013 | 9/3/2013 | 9/4/2013 | | PASS |
Scott Arellano
|
|
|
Attached plan review report to case.
|
Routing - PLAN CHECK | 9/3/2013 | | 9/3/2013 | | PASS |
Sam Zahorka
|
|
|
|
Routing PW Environmental | 9/3/2013 | | 9/3/2013 | | PASS |
Walt Baumgartner
|
|
|
OK, corrections made.
|
1st review completed | | | 8/29/2013 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLANNING | 8/19/2013 | | 8/29/2013 | | FAIL |
David Moser
|
|
|
David Moser - CUP13-00035
|
Routing - PLAN CHECK | 8/19/2013 | | 8/29/2013 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - FIRE | 8/19/2013 | 8/19/2013 | 8/21/2013 | | FAIL |
Scott Arellano
|
|
|
Emailed resubmittal ittem to architect. Attached report to case and plans.
|
Routing - Erosion and Sediment | 8/19/2013 | | 8/20/2013 | | PASS |
Jason C. Taylor
|
|
|
ESC Permit and Waiver Request Letter approved. Jason Taylor ###-####
|
Routing - PLUMBING | 8/19/2013 | | 8/20/2013 | | PASS |
Bill VanDegrift
|
|
|
plans approved with
1) 120 deg. max hot water to hand sinks and lavs.
2) floor sink P-5 to grease waste per public works review.
3) all floor sinks to be exposed under cabinets.
|
Routing - Addressing | 8/19/2013 | | 8/19/2013 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 8/19/2013 | | 8/19/2013 | | PASS |
Beverly Mountain
|
|
|
|
Pending Assignment by JCB | 8/19/2013 | | 8/19/2013 | | DONE |
Jason Blais
|
|
|
|
Routing PW Sewer Rating | 8/19/2013 | | 8/19/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | 8/19/2013 | | 8/19/2013 | | FAIL |
Walt Baumgartner
|
|
|
Re route floor sink P 5 in kitchen to grease interceptor line
|
Payment Received | | | 8/16/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Intake Approval | | | 8/16/2013 | | PASS |
Jason Blais
|
|
|
|
Application received | | | 8/15/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 15 2013 1:58PM
|