BLD-Final | 3/13/2014 | 3/13/2014 | 3/13/2014 | P | PASS |
Tony Young
|
|
|
jeff Phone #: ###-####
|
DOC - Permit Finaled | 3/13/2014 | 3/13/2014 | 3/13/2014 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 3/12/2014 | 3/13/2014 | 3/13/2014 | A | PASS |
Tony Young
|
|
|
jeff Phone #: ###-####
|
BLD-Final | 3/11/2014 | 3/12/2014 | 3/12/2014 | P | PEND |
Tony Young
|
|
|
Jeff Phone #: ###-####,, walk through only
|
BLD-Other | 12/24/2013 | 12/26/2013 | 12/26/2013 | P | PASS |
Tony Young
|
|
|
soffits
|
BLD-Energy code compliance | 12/23/2013 | 12/24/2013 | 12/24/2013 | A | PASS |
Tony Young
|
|
|
Jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 12/19/2013 | 12/19/2013 | 12/19/2013 | P | PART |
Tony Young
|
|
|
Jeff Phone #: ###-####,, need truss engineering,, strap top plates,, point loads solid to the footings,, mechanical pass,, ok to insulate
|
BLD-Wall Bracing | 12/3/2013 | 12/4/2013 | 12/4/2013 | A | PART |
Tony Young
|
|
|
jeff - ###-####shear inspection,, exterior ok after renailing some
|
BLD-Other | 12/3/2013 | 12/3/2013 | 12/3/2013 | P | PEND |
Tony Young
|
|
|
jeff - ###-####shear inspection
|
BLD-Foundation | 10/31/2013 | 10/31/2013 | 10/31/2013 | P | PART |
Tony Young
|
|
|
pat Phone #: ###-####
|
BLD-Footing | 10/28/2013 | 10/29/2013 | 10/29/2013 | A | NR |
Tony Young
|
|
|
pat Phone #: ###-####
|
PubWorks Subgrade Approval | 10/29/2013 | 10/29/2013 | 10/29/2013 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 10/28/2013 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 9/19/2013 | | |
|
|
|
|
Plan assigned to (JG) | 9/3/2013 | 9/3/2013 | 9/19/2013 | | PASS |
Javier Guzman
|
|
|
1st review completed, Hillside Due 9/5
|
Routing - PLAN CHECK | 9/3/2013 | | 9/19/2013 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 9/19/2013 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/19/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/19/2013 | | DONE |
|
|
|
|
Telephone call | | | 9/19/2013 | | DONE |
Christina Prado
|
|
|
called Shane to advise permit is ready and gave fees due
|
Permit Ready to Issue | | | 9/19/2013 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 9/16/2013 | | DONE |
Christina Prado
|
|
|
received two sets of revised plan sheets marked 7 & 8 of 10 as well as two sets of letter from engineer; Taken to Javier for further review
|
Plan assigned to (AJS) | 8/19/2013 | 8/19/2013 | 9/3/2013 | | DEFR |
Adele J Schaffeld-Griffin
|
|
|
Hillside Due 9/5
|
1st review completed | | | 9/3/2013 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 8/28/2013 | | 9/3/2013 | | FAIL |
Javier Guzman
|
|
|
emailed applicant 9-3-2013
|
Routing - Erosion and Sediment | 8/30/2013 | | 8/30/2013 | | PASS |
Jason C. Taylor
|
|
|
See ESC Permit for details.
|
Routing - FIRE | 8/23/2013 | | 8/28/2013 | | PASS |
Scott Arellano
|
|
|
No comments.
|
Routing - MECHANICAL | 8/21/2013 | | 8/23/2013 | | PASS |
Troy James
|
|
|
|
Plan resubmittals received | | | 8/22/2013 | | DONE |
|
|
|
|
Routing - PLANNING | 8/20/2013 | | 8/21/2013 | | PASS |
Susan Riggs
|
|
|
|
Route to Impact Fee Review | 8/19/2013 | 8/22/2013 | 8/20/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Addressing | 8/19/2013 | | 8/20/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | | | 8/20/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | | | 8/20/2013 | | FAIL |
|
|
|
Need two full size plans to review prior to approval. Jason Taylor ###-####
|
Routing PW Grading-Hillside | 8/20/2013 | | 8/20/2013 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
Application received | | 8/19/2013 | 8/19/2013 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/19/2013 | | DONE |
|
|
|
|
Intake Approval | | | 8/19/2013 | | |
|
|
|
|