Routing PW Environmental | 9/6/2013 | | 9/11/3013 | | PASS |
Connie Baumgartner
|
|
|
|
Third Notice | | 11/9/2014 | 12/2/2014 | | DONE |
|
|
|
|
Second Notice | | 10/16/2014 | 11/4/2014 | | DONE |
|
|
|
|
First Notice | | 9/15/2014 | 10/6/2014 | | DONE |
|
|
|
|
Permanent Occupancy | | | 9/5/2014 | | DONE |
|
|
|
|
PubWorks Occupancy Approval | 9/3/2014 | 9/3/2014 | 9/3/2014 | | DONE |
Brian Murphy
|
|
|
ok per BGM
|
FIRE-Final Inspection | 9/2/2014 | 9/2/2014 | 9/2/2014 | P | PASS |
Troy Cobbley
|
|
|
life safety passed. Fire extinguishers are placed but brackets will not be available for acouple of days.
|
BLD-Final | 8/29/2014 | 9/2/2014 | 9/2/2014 | A | PASS |
Phil Shearer
|
|
|
Ron Phone #: ###-####
|
DOC - Permit Finaled | 9/2/2014 | 9/2/2014 | 9/2/2014 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Final | 8/28/2014 | 8/29/2014 | 8/29/2014 | A | CANC |
Phil Shearer
|
|
|
Ron Phone #: ###-####
|
BLD-Final | 5/15/2014 | 5/16/2014 | 5/16/2014 | P | PART |
Tom Arcoraci
|
|
|
Ron-wants temp co Phone #: ###-####
|
Zoning Approval | 5/16/2014 | 5/16/2014 | 5/16/2014 | | DONE |
Josh Wilson
|
|
|
|
FIRE-Final Inspection | 5/8/2014 | 5/9/2014 | 5/9/2014 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy for life safety is being given until the interior equipmetent has been installed and possible fire sprinkler modifications performed.
|
FIRE-Conference | 5/2/2014 | 5/5/2014 | 5/6/2014 | P | DONE |
Troy Cobbley
|
|
|
Went over life safety requirements with Mike. I deferred knox box location to the fire dept. I noted missing exit signs, building address and fire extinguisher and approval notes. Also project is not to be finaled until the interior equipment has been installed.
|
BLD-Framing/Rough-in | 4/29/2014 | 4/30/2014 | 4/30/2014 | A | PASS |
Tom Arcoraci
|
|
|
Ron-Ceiling grid inspection please Phone #: ###-####
|
BLD-Framing/Rough-in | 4/3/2014 | 4/4/2014 | 4/4/2014 | A | PASS |
Tom Arcoraci
|
|
|
Gayle Phone #: ###-####
|
Plan assigned to (JCM) | 3/28/2014 | | 4/3/2014 | | PASS |
John Menard
|
|
|
Plan Modification
|
Routing - PLAN CHECK | 3/28/2014 | | 4/3/2014 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/3/2014 | | DONE |
John Menard
|
|
|
|
CHANGE STATUS TO (ISS) | | | 4/3/2014 | | DONE |
Tisha Gallop
|
|
|
plan mod approved and paid
|
Routing - FIRE | 3/28/2014 | | 4/1/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Report MOD 04-01-14
|
BLD-Footing | 3/28/2014 | 3/31/2014 | 3/31/2014 | A | PASS |
Tom Arcoraci
|
|
|
ron Phone #: ###-####
|
BLD-Foundation | 3/27/2014 | 3/28/2014 | 3/28/2014 | A | PASS |
Tom Arcoraci
|
|
|
Ron - Late AM Please Phone #: ###-####
|
BLD-Energy code compliance | 3/26/2014 | 3/27/2014 | 3/27/2014 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 3/25/2014 | 3/26/2014 | 3/26/2014 | A | PASS |
Tom Arcoraci
|
|
|
Ron Phone #: ###-####
|
BLD-Footing | 3/25/2014 | 3/25/2014 | 3/25/2014 | P | PASS |
Tom Arcoraci
|
|
|
ron Phone #: ###-####
|
BLD-Foundation | 2/13/2014 | 2/14/2014 | 2/14/2014 | A | PEND |
Tony Young
|
|
|
ron Phone #: ###-####,, dock area,, west side,, pending special inspection report
|
BLD-Foundation | 2/4/2014 | 2/5/2014 | 2/5/2014 | A | PASS |
Tom Arcoraci
|
|
|
request first thing in AM .. Ron Phone #: ###-####
|
BLD-Footing | 1/23/2014 | 1/23/2014 | 1/23/2014 | P | PASS |
Tom Arcoraci
|
|
|
ron Phone #: ###-#### spec insp
|
BLD-Foundation | 1/21/2014 | 1/21/2014 | 1/21/2014 | P | PART |
Jim Sly
|
|
|
Ron-Please call at least 30 mins prior to inspection Phone #: ###-#### 80% of North wall...... Covered.......supplimental heat.
|
BLD-Foundation | 1/16/2014 | 1/16/2014 | 1/16/2014 | P | PART |
Mike Jordan
|
|
|
ron Phone #: ###-####. pEnding special inspection.
|
BLD-Foundation | 1/13/2014 | 1/15/2014 | 1/15/2014 | A | PART |
Mike Jordan
|
|
|
Ron Phone #: ###-####
|
BLD-Footing | 1/13/2014 | 1/15/2014 | 1/15/2014 | A | PASS |
Mike Jordan
|
|
|
Ron Phone #: ###-####
|
BLD-Footing | 12/31/2013 | 1/2/2014 | 1/2/2014 | A | PASS |
Jim Storey
|
|
|
Ron Phone #: ###-####
|
BLD-Conference | 12/23/2013 | 12/24/2013 | 12/24/2013 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Footing | 12/20/2013 | 12/23/2013 | 12/23/2013 | A | PASS |
Tom Arcoraci
|
|
|
ron Phone #: ###-####
|
BLD-Foundation | 12/18/2013 | 12/19/2013 | 12/19/2013 | A | PASS |
Tom Arcoraci
|
|
|
ron Phone #: ###-####
|
BLD-Concrete | 12/12/2013 | 12/12/2013 | 12/12/2013 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Footing | 12/11/2013 | 12/12/2013 | 12/12/2013 | A | PART |
Tom Arcoraci
|
|
|
ron Phone #: ###-####
|
BLD-Footing | 12/3/2013 | 12/5/2013 | 12/5/2013 | A | PART |
Tom Arcoraci
|
|
|
Ron Phone #: ###-#### spec inspector on site cold weather protection appears in place
|
OVERRIDE | | | 11/26/2013 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/26/2013 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 11/26/2013 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 11/26/2013 | | DONE |
Christina Prado
|
|
|
Spoke to Mike over phone - Mike provided revised values early October, emailed fee calc and advised proper forms will need to be filled out at time of permit issuance. Also advised ACHD is req'd
|
Permit Ready to Issue | | | 11/26/2013 | | DONE |
Christina Prado
|
|
|
|
Routing - Erosion and Sediment | 11/22/2013 | | 11/25/2013 | | PASS |
Jason C. Taylor
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/25/2013 | | DONE |
John Menard
|
|
|
|
Plan assigned to (JCM) | 9/6/2013 | | 11/25/2013 | | PASS |
John Menard
|
|
|
1st Review Complete 10/22
|
Routing Off Site - STRUCTURAL | 11/13/2013 | | 11/21/2013 | | PASS |
John Menard
|
|
|
|
Plan Reviewer's activity | | | 11/19/2013 | | PASS |
John Menard
|
|
|
Reviewed and approved plan resubmittals. JCM
|
Routing - PLAN CHECK | 11/13/2013 | | 11/19/2013 | | PASS |
John Menard
|
|
|
|
Routing - FIRE | 11/13/2013 | | 11/19/2013 | | PASS |
Scott Arellano
|
|
|
See Fire Report Rev 1
|
Routing - Erosion and Sediment | 11/13/2013 | | 11/15/2013 | | FAIL |
Jason C. Taylor
|
|
|
|
1st review completed | | | 10/23/2013 | | DONE |
John Menard
|
|
|
|
Routing - PLAN CHECK | 9/6/2013 | | 10/22/2013 | | FAIL |
John Menard
|
|
|
|
Routing - PUBLIC WORKS | 9/6/2013 | | 10/21/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 9/6/2013 | | 10/21/2013 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLANNING | 10/1/2013 | | 10/1/2013 | | PASS |
David Moser
|
|
|
|
Routing - PLANNING Land Div | 10/1/2013 | | 10/1/2013 | | PASS |
Dave Abo
|
|
|
ROS13-00059 completed.
|
Routing - FIRE | 9/6/2013 | 9/6/2013 | 9/30/2013 | | FAIL |
Craig D. Hanson
|
|
|
|
Routing - PLANNING | 9/6/2013 | | 9/25/2013 | | FAIL |
David Moser
|
|
|
Need to complete the ROS and need approval letter from Airport for Wildlife Plan
|
Routing Off Site - STRUCTURAL | 9/6/2013 | | 9/19/2013 | | FAIL |
John Menard
|
|
|
|
Routing - Design Review | 9/6/2013 | | 9/11/2013 | | PASS |
Josh Wilson
|
|
|
|
Routing - PLUMBING | 9/6/2013 | | 9/10/2013 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Route to Impact Fee Review | 9/6/2013 | | 9/10/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing PW Sewer Rating | 9/6/2013 | | 9/10/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | 9/6/2013 | | 9/10/2013 | | FAIL |
Jason C. Taylor
|
|
|
Needs SWPPP Plan submitted for review. Jason Taylor ###-####
|
Routing PW Street Lights | 9/6/2013 | | 9/9/2013 | | PASS |
Mike D Hedge
|
|
|
|
Routing PW Solid Waste | 9/6/2013 | | 9/9/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING Land Div | 9/6/2013 | | 9/9/2013 | | FAIL |
Dave Abo
|
|
|
Must complete Record of Survey for Parcel Consolidation.
ROS13-00059
|
Routing PW Sewer Design | 9/6/2013 | | 9/9/2013 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Payment Received | | | 9/6/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Pending Assignment by JCM | 9/6/2013 | | 9/6/2013 | | DONE |
John Menard
|
|
|
|
Routing - Addressing | 9/6/2013 | | 9/6/2013 | | PASS |
Emily Dixon
|
|
|
|
Application received | | | 8/20/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 20 2013 9:38AM
|