Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD13-02311
StatusFinaled
Name VERTICAL CORP
Site Address 800 W MAIN ST Unit: 230
Project Name8TH & MAIN STE 230
Customer Number 
ePlanReviewNo
Description
(FLATBREAD NEAPOLITAN PIZZERIA - SUITE 230 - 2ND FLOOR) The fire sprinkler system is used for high-rise. To create a 3,557 square foot restaurant tenant space on the 2nd story of a new high-rise building. Work is to include interior nonbearing walls, a grease hood and duct system (Type I) with an exhaust air scrubber, a solid-fuel-fired pizza oven and chimney with an exhaust air scrubber, a dishwasher hood and duct system (Type II), bar counters, tables, chairs, booths, firewood storage racks, wood paneling, wood flooring, tile flooring, a walk-in cooler, kitchen equipment, suspended acoustical ceilings, gypsum board soffits, suspended wood slats at the ceiling level, and interior finishes. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  5/15/2014 DONE
DetailsBarbara Stitt
First Notice 3/13/20145/5/2014 DONE
Permanent Occupancy  3/3/2014 DONE
DetailsChristina Prado
BLD-Final2/18/20142/18/20142/18/2014PPASS
DetailsDave Hannah
Aaron Baker Phone #: ###-####
BLD-Final2/12/20142/12/20142/12/2014PPEND
DetailsDave Hannah
Aaron Phone #: ###-#### ok for temp occ ok for perm after plumbing gos perm occ
Temporary Occupancy2/12/20145/13/20142/12/2014 DONE
DetailsChristina Prado
FIRE-Final Inspection2/11/20142/11/20142/11/2014PPASS
DetailsForrest France
C/N items verified for completion. Fire life safety finaled.
FIRE-Final Inspection2/10/20142/10/20142/10/2014PNR
DetailsForrest France
Items noted include; suite address, post max occupant load sign, post signage at the second exit passageway per review note #3, project related fire sprinkler permit needs finaled.
BLD-Ceiling Grid Inspection2/7/20142/10/20142/10/2014APASS
DetailsDave Hannah
Request first inspection of day - aaron Phone #: ###-####
BLD-Framing/Rough-in1/31/20141/31/20142/3/2014PPART
DetailsDave Hannah
Ceiling grid inspection please-Aaron Phone #: ###-#### needs th finish installing lights
BLD-Energy code compliance1/9/20141/9/20141/10/2014PPASS
DetailsDave Hannah
ROGER Phone #: ###-####
BLD-Framing/Rough-in1/3/20141/3/20141/6/2014PPART
DetailsDave Hannah
aaron Phone #: ###-#### ok to cover walls
BLD-Conference12/12/201312/16/201312/17/2013ADONE
DetailsDave Hannah
AARON Phone #: ###-####
BLD-Conference12/12/201312/13/201312/12/2013ACANC
DetailsDave Hannah
AARON Phone #: ###-####
Issue PAID IN FULL permit  11/14/2013 DONE
DetailsBarbara Stitt
Routing - PLAN CHECK10/25/2013 10/28/2013 PASS
DetailsCarl Westfall
Drawings approved with "red lines".
PLANS/APPL TAKEN TO FRONT DESK  10/28/2013  
Print Occupancy Form  10/28/2013 DONE
Permit Ready to Issue  10/28/2013 DONE
DetailsChristina Prado
Telephone call  10/28/2013 DONE
DetailsChristina Prado
Called Richard to advise permit is ready and gave fees due
Plan assigned to (CJW)8/23/2013 10/28/2013 PASS
DetailsCarl Westfall
FLATBREAD NEAPOLITAN PIZZERIA
Routing - PLUMBING10/24/2013 10/25/2013 PASS
DetailsDaryl Spivey

May require additional backflow protection
Per plan and ISPC.
Plan resubmittals received  10/25/2013  
10-25-13 received 1 transmittal , 1 copy of sheets A100, A511 sent to Carl W.
Plan resubmittals received  10/24/2013 DONE
DetailsChristina Prado
Received two sets of revised plan sheets marked e3.2 & e4.2 as well as 1 revised set of structural calcs;Taken to Carl Westfall for further review
Routing - MECHANICAL  10/24/2013 PASS
Routing - FIRE10/22/2013 10/23/2013 PASS
DetailsCraig D. Hanson
Plan resubmittals received  10/22/2013 DONE
DetailsChristina Prado
received two sets of revised structural calcs; Taken to Carl Westfall for further review
Routing - PLAN CHECK10/18/2013 10/22/2013 FAIL
DetailsCarl Westfall
Need more information
Plan resubmittals received  10/18/2013 DONE
Rec'd response letter, specs and sheets a0.01; a0.10; A100; A151; A314; A315; A511; M0.1; M0.2; M2.2; M6.1; M6.2; P2.2a; UP2.2; e2.2; e3.2; e4.1; e4.2 - taken to carl w
Meeting  9/25/2013 DONE
Met with the Architect, Mech Engineer, and the Owner to discuss the grease duct shaft concerns.
Route to Impact Fee Review9/17/20139/20/20139/19/2013 PASS
DetailsCindy M. Gould
Tenant improvement
Routing - FIRE9/17/20139/17/20139/19/2013 FAIL
DetailsCraig D. Hanson
Oven clarification and back egress hall redesign.
1st review completed  9/19/2013 FAIL
Failed Mech, Plans, Fire
Routing - PLAN CHECK9/13/2013 9/17/2013 FAIL
DetailsCarl Westfall
The IBC plan review was started on Sept 14 and was finished on Sept 17. Revised drawings were required. See the plan review report.
Routing - Design Review9/13/2013 9/13/2013 PASS
DetailsSarah Schafer
The grille to be installed on the Main Street elevation was shown on the Shell and Core permit. In speaking with Richard Honsinger from Erstad Architects they are still working on the scrubbers to be installed in the vents to make sure there is no soot on the building from the wood burning oven to be installed. The soot would be my main concern with the location of the vent.
Routing - PLAN CHECK9/3/2013 9/12/2013 PEND
DetailsCarl Westfall
Took site copy to Fire to see if they could get started on it.
Routing - MECHANICAL8/27/2013 9/3/2013 FAIL
DetailsTroy James
emailed corrections to architect
Routing - PLUMBING8/26/2013 8/27/2013 PASS
DetailsBill VanDegrift
May require additional backflow protection on equipment.
Per plan and ISPC.
Routing - PUBLIC WORKS8/23/2013 8/26/2013 PASS
DetailsConnie Baumgartner
Routing PW Environmental8/26/2013 8/26/2013 PASS
DetailsWalt Baumgartner
Plans indicated kitchen drains to common shell & core grease line.
Routing PW Sewer Rating8/26/2013 8/26/2013 PASS
DetailsConnie Baumgartner
Routing - Addressing8/23/2013 8/23/2013 PASS
DetailsJason C. Taylor
Pending Assignment by JCB8/22/2013 8/23/2013 DONE
DetailsJason Blais
Application received 8/22/20138/22/2013 DONE
DetailsBarbara Stitt
Plans ACCEPTED BY PLAN TECH  8/22/2013 DONE
Intake Approval  8/22/2013 PASS
DetailsTim L. Woodard