Permanent Occupancy | | | 11/27/2013 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 11/25/2013 | 11/26/2013 | 11/26/2013 | P | PASS |
Mike Jordan
|
|
|
Kevin Phone #: ###-####. ok for perm occ.
|
FIRE-Final Inspection | 11/25/2013 | 11/25/2013 | 11/25/2013 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. Building inspector please verify that the additional exit/emergency light is installed in the corridor that runs east/west.
|
BLD-Conference | 9/6/2013 | 9/9/2013 | 9/9/2013 | A | DONE |
Mike Jordan
|
|
|
call before to meet// Kevin ###-####. Walk through inspection. Provide all missing items on approved plans
|
BLD-Final | 9/4/2013 | 9/5/2013 | 9/5/2013 | A | NR |
Mike Jordan
|
|
|
Kevin Phone #: ###-####. Life/safety inspection has failed.
|
FIRE-Final Inspection | 9/4/2013 | 9/4/2013 | 9/4/2013 | P | FAIL |
Troy Cobbley
|
|
|
Remove thumb turn locks from all marked required exits, provide sticker at the main exit, resubmitt plans showing the preferred exiting, provide exit signs and emergency lights as discussed or per the resubmittted plans, provide fire extinguishers as discussed, provide single action hardware on exterior doors eccept for the main exit.
|
Issue PAID IN FULL permit | | | 9/4/2013 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 8/26/2013 | 8/26/2013 | 8/30/2013 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 8/26/2013 | | 8/30/2013 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 8/30/2013 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 8/30/2013 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/30/2013 | | DONE |
|
|
|
|
Telephone call | | | 8/30/2013 | | DONE |
Christina Prado
|
|
|
Called Cliff to advise permit is ready for pick up
|
Permit Ready to Issue | | | 8/30/2013 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 8/30/2013 | | DONE |
Christina Prado
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/26/2013 | | DONE |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/26/2013 | | DONE |
Christina Prado
|
|
|
|
First Notice | | 12/7/2013 | | | |
|
|
|
|
Application received | | 8/26/2013 | | | |
|
|
|
|