BLD-Final | 4/2/2014 | 4/3/2014 | 4/3/2014 | P | PASS |
Jim Storey
|
|
|
The garage access code is either 9834 or 0713. Please give me a call if you have any questions. Thanks Kim Phone #: ###-#### >> Inspection requested via web by Kim Winkle
|
DOC - Permit Finaled | 4/3/2014 | 4/3/2014 | 4/3/2014 | P | PASS |
Jim Storey
|
|
|
|
BLD-Blower Door Test Results | 4/3/2014 | 4/3/2014 | 4/3/2014 | P | CANC |
Jim Storey
|
|
|
32
|
BLD-Conference | 3/21/2014 | 3/21/2014 | 3/21/2014 | P | FAIL |
Jim Storey
|
|
|
due to complaint please verify side setbacks, especially the front east corner. also complaint about gutter positioning toward neighboring property to the east. c/n posted left message to call for insp.
|
BLD-Framing/Rough-in | 1/9/2014 | 1/9/2014 | 1/9/2014 | P | PART |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Lucas Christian interior ok back deck pending engineering/ not per plan
|
BLD-Energy code compliance | 1/9/2014 | 1/9/2014 | 1/9/2014 | P | PASS |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Lucas Christian
|
BLD-Framing/Rough-in | 1/7/2014 | 1/7/2014 | 1/7/2014 | P | FAIL |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Lucas Christian back roof/deck not per plan/ front cantalever need engineering short nailling ?
|
BLD-Footing | 10/17/2013 | 10/18/2013 | 10/18/2013 | P | PASS |
Jim Storey
|
|
|
Heron Phone #: ###-####
|
PubWorks Subgrade Approval | 10/18/2013 | 10/18/2013 | 10/18/2013 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####
|
Issue PAID IN FULL permit | | | 10/4/2013 | | DONE |
|
|
|
|
OVERRIDE | | | 9/11/2013 | | |
|
|
|
|
Plan assigned to (JG) | 9/4/2013 | 9/4/2013 | 9/11/2013 | | PASS |
Javier Guzman
|
|
|
1st review complete failed ESC, Due 9/16/13
|
Routing - Erosion and Sediment | 9/11/2013 | | 9/11/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Case Summary (BLD) | | | 9/11/2013 | | |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/11/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/11/2013 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 9/11/2013 | | DONE |
Christina Prado
|
|
|
called Steve to advise permit is ready and gave fees due
|
Permit Ready to Issue | | | 9/11/2013 | | DONE |
Christina Prado
|
|
|
|
Routing - PLAN CHECK | 9/4/2013 | | 9/6/2013 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 9/6/2013 | | FAIL |
Javier Guzman
|
|
|
Failed ESC, 9/6
|
Plan assigned to (AJS) | | 8/28/2013 | 9/4/2013 | | DEFR |
Adele J Schaffeld-Griffin
|
|
|
Due 9/16/13 Hillside
|
Routing - FIRE | 9/3/2013 | | 9/4/2013 | | PASS |
Scott Arellano
|
|
|
No comments.
|
Routing - MECHANICAL | | | 9/3/2013 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 8/27/2013 | 8/30/2013 | 8/29/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Route to Impact Fee Review | 8/27/2013 | 8/30/2013 | 8/29/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 8/29/2013 | | 8/29/2013 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 8/28/2013 | | 8/29/2013 | | PASS |
Jason C. Taylor
|
|
|
Use corect address of 2552 E. Boise Ave., Unit B is not acceptable as an address identifier. JCT
|
Routing - PUBLIC WORKS | 8/29/2013 | | 8/29/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | | | 8/29/2013 | | FAIL |
Jason C. Taylor
|
|
|
Narritive needs revised. Sequence of events is missing. Jason Taylor ###-####.
|
Routing PW Grading-Hillside | | | 8/29/2013 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
Intake Approval | | | 8/28/2013 | | PASS |
Christina Prado
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/28/2013 | | DONE |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/28/2013 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 8/26/2013 | | FAIL |
Christina Prado
|
|
|
needs stair section and second SWPPP copy. Hillside Grading requirements NA per Jason(grading plans, CFH & Soils & Geotech)
|
Application received | | 8/26/2013 | | | |
|
|
|
|