Permit Information
Permit NumberBLD13-02364
StatusIssued
Name TBL CONSTRUCTION
Site Address 1319 N 8TH ST
Project NameHOLLYWOOD MARKET YOGA
Customer Number 
ePlanReviewNo
Description
(HOLLYWOOD MARKET YOGA) Permit for the construction of a 787 sq. ft. two story addition to an existing 1,742 sq. ft. building. The first story is 500 sq. ft. and consists of a yoga exercise area with the second being 287 sq. ft. with two treatment areas. The new construction will be type VB construction nonsprinklered. All finishes to comply with chapter 8 of the IBC. All work per the approved plans, attached engineering and any notations. CDM
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Conference2/24/20183/8/20183/8/2018ACANC
DetailsTony Young
status review to close out permit Inspection cancelled from web by: Timothy Beaudoin
BLD-Final2/15/20182/21/20182/24/2018APEND
DetailsTony Young
status review to close out permit
BLD-Final2/13/20182/15/20182/15/2018APEND
DetailsTony Young
status review to close out permit
BLD-Conference2/8/20182/13/20182/13/2018ANH
DetailsTony Young
status review to close out permit
BLD-Conference2/7/20182/8/20182/8/2018PPEND
DetailsTony Young
status review to close out permit
BLD-Conference2/7/20182/7/20182/7/2018PNH
DetailsTony Young
Zoning Approval2/7/20182/7/20182/7/2018 DONE
DetailsTed Vanegas
BLD-Energy code compliance1/23/20141/23/20141/23/2014PPASS
DetailsTony Young
Insulators will be there in the AM and should be finished prior to 12pm. Call Tim if there are any problems. Thank you. Phone #: ###-#### >> Inspection requested via web by Timothy Beaudoin
BLD-Framing/Rough-in1/21/20141/22/20141/22/2014APASS
DetailsTony Young
Phone #: ###-####0
BLD-Foundation11/14/201311/14/201311/14/2013PPART
DetailsTony Young
adam Phone #: ###-####
BLD-Footing11/8/201311/8/201311/10/2013PPART
DetailsTony Young
adam Phone #: ###-####,, work in progress,, ok to pour when ready
Print Occupancy Form  10/23/2013 DONE
Issue PAID IN FULL permit  10/23/2013 DONE
OVERRIDE  10/16/2013  
Print Occupancy Form  10/16/2013 DONE
DetailsTisha Gallop
Telephone call  10/16/2013 DONE
DetailsChristina Prado
called Cathy to advise permit is ready pending GC, ACHD & RP info and gave fees due
Permit Ready to Issue  10/16/2013 DONE
DetailsChristina Prado
Plan assigned to (CDM)8/27/20138/27/201310/15/2013 PASS
DetailsCarl D Madsen
First review completed
Case Summary (BLD)  10/15/2013 DONE
PLANS/APPL TAKEN TO FRONT DESK  10/15/2013 DONE
Routing - PLAN CHECK10/9/2013 10/15/2013 PASS
DetailsCarl D Madsen
Routing - Erosion and Sediment10/10/2013 10/14/2013 PASS
DetailsJason C. Taylor
Plan resubmittals received  10/14/2013  
10-14-13 received 1 correction, and 2 copies of sheets A2.01,A3.01,A6.01 inserted by Catherine Sewell and taken back to Carl M
Plan resubmittals received  10/11/2013 DONE
DetailsTisha Gallop
received two copies of ESC narrative and plans; taken to Carl Madsen.
Routing - PUBLIC WORKS10/9/2013 10/10/2013 PASS
DetailsBeverly Mountain
Routing PW Drainage10/9/2013 10/10/2013 PASS
DetailsBrian Murphy
LESS THAN 1000 SQUARE FREE
Routing - PLAN CHECK9/20/2013 10/9/2013 FAIL
DetailsCarl D Madsen
East wall is required to be one hour construction and need a continuity detail for wall at the stair section. CDM
Routing - Design Review10/9/2013 10/9/2013 PASS
DetailsMatthew A Halitsky
Plan resubmittals received  10/1/2013  
10-1-13 received 1 transmittal,1 comment,1 response,1 evaluation report, 3 structural calcs , 5 copies of sheets S1.01 & S2.01 , and 4 copies of sheets G1.00,A1.01,A2.01,A2.02,A4.01,A4.02,A6.01, and 5 copies of sheets A3.01 inserted by Catherine Sewell and taken back to Carl M.
1st review completed  9/20/2013 FAIL
Failed PW, Plan check,Errosion,
Route to Impact Fee Review8/27/20138/30/20139/19/2013 PASS
DetailsCindy M. Gould
Routing - FIRE9/18/20138/27/20139/19/2013 PASS
DetailsCraig D. Hanson
See attached letter for field verification
Routing - PLAN CHECK9/17/2013 9/18/2013 FAIL
DetailsCarl D Madsen
Routing - Design Review9/6/2013 9/17/2013 PASS
DetailsMatthew A Halitsky
Routing Off Site - STRUCTURAL8/27/2013 9/9/2013 PASS
DetailsCarl D Madsen
Receive first review comments E-Mailed to Cathy Sewell 9-9-13 CDM All review comments were adressed with no reason to route back to the structural outsouce engineer. CDM 10-15-13
Routing - PLUMBING9/3/2013 9/6/2013 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing PW Drainage8/29/2013 8/30/2013 FAIL
DetailsBrian Murphy
DOWNSPOUT LOCATION
Routing PW Sewer Rating8/29/2013 8/29/2013 PASS
DetailsConnie Baumgartner
Routing - Erosion and Sediment  8/29/2013 FAIL
DetailsJason C. Taylor
ESC plan required, waiver denied. Please submit plans for review. Jason Taylor ###-####.
Routing - Addressing8/28/2013 8/29/2013 PASS
DetailsJason C. Taylor
Routing - PLANNING Land Div8/27/2013 8/28/2013 PASS
DetailsDave Abo
Existing structure built in 1927 on parcel. Parcel created prior to October 30, 1965.
Plans ACCEPTED BY PLAN TECH  8/27/2013 DONE
DetailsChristina Prado
Intake Approval  8/27/2013 PASS
DetailsAdele J Schaffeld-Griffin
Recd Pcfee & Taken To Pln CK  8/27/2013 DONE
DetailsChristina Prado
Telephone call  8/27/2013 DONE
DetailsChristina Prado
called Action Couriers for pick up
Application received 8/27/2013   
Routing - PUBLIC WORKS8/30/2013   FAIL
DetailsBeverly Mountain
Failed by Drainage - Brian Murphy