PubWorks Occupancy Approval | 6/27/2014 | 6/27/2014 | 6/27/2014 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Final | 4/29/2014 | 4/29/2014 | 4/29/2014 | P | PASS |
Tony Young
|
|
|
John-the later the better please Phone #: ###-####
|
DOC - Permit Finaled | 4/29/2014 | 4/29/2014 | 4/29/2014 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 4/28/2014 | 4/29/2014 | 4/29/2014 | A | NR |
Tom Arcoraci
|
|
|
John Phone #: ###-#### no fire final called no answer
|
BLD-Energy code compliance | 1/17/2014 | 1/21/2014 | 1/21/2014 | P | PASS |
Tom Arcoraci
|
|
|
JOHN Phone #: ###-####
|
BLD-Framing/Rough-in | 1/16/2014 | 1/17/2014 | 1/17/2014 | A | PASS |
Jim Sly
|
|
|
John Phone #: ###-####
|
BLD-Wall Bracing | 12/11/2013 | 12/11/2013 | 12/11/2013 | P | PASS |
Tony Young
|
|
|
john Phone #: ###-####
|
BLD-Wall Bracing | 12/10/2013 | 12/11/2013 | 12/11/2013 | A | NR |
Tony Young
|
|
|
john Phone #: ###-####
|
BLD-Wall Bracing | 12/10/2013 | 12/10/2013 | 12/10/2013 | P | FAIL |
Tony Young
|
|
|
john Phone #: ###-####,, not per plan
|
BLD-Foundation | 10/3/2013 | 10/4/2013 | 10/4/2013 | A | PASS |
Tom Arcoraci
|
|
|
adam Phone #: ###-####
|
BLD-Footing | 10/3/2013 | 10/3/2013 | 10/3/2013 | P | PASS |
Tony Young
|
|
|
adam Phone #: ###-####
|
PubWorks Subgrade Approval | 10/2/2013 | 10/2/2013 | 10/2/2013 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 9/26/2013 | | DONE |
|
|
|
|
OVERRIDE | | | 9/25/2013 | | |
|
|
|
|
Plan assigned to (JG) | 9/3/2013 | 9/3/2013 | 9/25/2013 | | PASS |
Javier Guzman
|
|
|
1st review completed, Due 9/20
|
Routing - PLAN CHECK | 9/20/2013 | | 9/25/2013 | | PASS |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 9/25/2013 | | 9/25/2013 | | PASS |
Troy James
|
|
|
|
Case Summary (BLD) | | | 9/25/2013 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/25/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/25/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/25/2013 | | DONE |
|
|
|
|
Telephone call | | | 9/25/2013 | | DONE |
Tisha Gallop
|
|
|
spoke to John in office, told him fees due.
|
Permit Ready to Issue | | | 9/25/2013 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 9/23/2013 | | DONE |
Christina Prado
|
|
|
Received one 11X17 truss layout, one copy of plan review report and two sets of 8 1/2 X 11 truss calcs;routed to Javier for review
|
Routing - PLAN CHECK | 9/17/2013 | | 9/20/2013 | | FAIL |
Javier Guzman
|
|
|
emailed applicant report
|
1st review completed | | | 9/20/2013 | | FAIL |
Javier Guzman
|
|
|
|
Routing - FIRE | 9/17/2013 | 9/17/2013 | 9/17/2013 | | PASS |
Scott Arellano
|
|
|
No comments attached to plans. Separate fire sprinkler permit will be required.
|
Routing PW Grading-Hillside | 9/16/2013 | | 9/16/2013 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Routing - FIRE | 9/11/2013 | | 9/11/2013 | | FAIL |
Scott Arellano
|
|
|
Emailed Fire comments to applicant.
|
Routing - MECHANICAL | 9/9/2013 | | 9/10/2013 | | FAIL |
Troy James
|
|
|
emailed corrections to Idaho Hvac
|
Routing - PLANNING | 9/6/2013 | | 9/9/2013 | | PASS |
Colleen T Carroll
|
|
|
CFH13-12 David Moser
Shower/tub not allowed in Studio
|
Routing - PUBLIC WORKS | 9/5/2013 | | 9/6/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Route to Impact Fee Review | 9/3/2013 | 9/6/2013 | 9/5/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Route to Impact Fee Review | 8/30/2013 | 9/5/2013 | 9/5/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Addressing | 9/3/2013 | | 9/5/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - Erosion and Sediment | 9/3/2013 | | 9/5/2013 | | PASS |
Jason C. Taylor
|
|
|
See ESC Permit For Details.
|
Routing PW Grading-Hillside | 9/3/2013 | | 9/5/2013 | | FAIL |
Jason C. Taylor
|
|
|
Geotechnical report needs revised to address building setback from top of slope. Additional full size grading plan needs to be submitted for approval. Jason Taylor ###-####.
|
Plan assigned to (AJS) | 9/3/2013 | 9/3/2013 | 9/3/2013 | | DEFR |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | 8/30/2013 | 9/3/2013 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/3/2013 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/3/2013 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 9/3/2013 | | PASS |
Tisha Gallop
|
|
|
|
Intake Approval | | | 8/30/2013 | | FAIL |
|
|
|
8-30-13 Need : Structural calcs,Building Envelope Energy Compliance, Erosion and Sediment Control Narrative,Soils and Geotechnical report, Erosion and Sediment Control Plans, Site Grading and Drainage Plans . Will also need to insert foundation plan into sets of plans.
|