Second Notice | | 12/20/2015 | 1/4/2016 | | DONE |
|
|
|
This permit finaled on the web by Kirk Ledbetter
|
First Notice | | 11/14/2015 | 12/10/2015 | | DONE |
|
|
|
mailed 12-11-15
|
Permanent Occupancy | | | 11/4/2015 | | DONE |
|
|
|
|
BLD-Final | 1/29/2014 | 1/29/2014 | 1/30/2014 | P | PASS |
Dave Hannah
|
|
|
john Phone #: ###-####
|
FIRE-Final Inspection | 1/28/2014 | 1/29/2014 | 1/29/2014 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Framing/Rough-in | 10/1/2013 | 10/2/2013 | 10/2/2013 | A | PART |
Dave Hannah
|
|
|
John Phone #: ###-#### walls ok to cover restrooms will be started at a later date
|
OVERRIDE | | | 10/1/2013 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 10/1/2013 | | DONE |
|
|
|
|
Telephone call | | | 10/1/2013 | | DONE |
Christina Prado
|
|
|
Called to advise Cornel permit is ready pending GC & RP and gave fees due
|
Permit Ready to Issue | | | 10/1/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (CJW) | 9/3/2013 | 9/3/2013 | 9/27/2013 | | PASS |
Carl Westfall
|
|
|
WASHINGTON FEDERAL (20 days - Sept 26)
|
Routing - PLAN CHECK | 9/23/2013 | | 9/27/2013 | | PASS |
Carl Westfall
|
|
|
Drawings approved after the resubmittal review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/27/2013 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/27/2013 | | DONE |
|
|
|
|
Route to Impact Fee Review | 9/20/2013 | 9/25/2013 | 9/24/2013 | | PASS |
Cindy M. Gould
|
|
|
Tenent improvement no impact fees
|
Plan resubmittals received | | | 9/24/2013 | | DONE |
Tisha Gallop
|
|
|
received response and two copies of plan sheets G1.0, G2.0, A-2.0, A-3.0, A-4.0; taken to Carl Westfall.
|
Routing - FIRE | 9/20/2013 | 9/20/2013 | 9/23/2013 | | PASS |
Craig D. Hanson
|
|
|
|
1st review completed | | | 9/23/2013 | | FAIL |
|
|
|
Failed Plan Check
|
Routing - PLAN CHECK | 9/5/2013 | | 9/20/2013 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on Sept 17 and was finished on Sept 20. Revised drawings were requried. See the plan review report.
|
Routing - PUBLIC WORKS | 9/4/2013 | | 9/5/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 9/5/2013 | | 9/5/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | | | 9/4/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - Addressing | 9/3/2013 | | 9/4/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Pending Assignment by JCB | 8/30/2013 | | 9/3/2013 | | DONE |
Jason Blais
|
|
|
|
Application received | | 8/30/2013 | 8/30/2013 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/30/2013 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/30/2013 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 8/30/2013 | | PASS |
Carl D Madsen
|
|
|
|