Permit Information
Permit NumberBLD13-02437
StatusFinaled
Name BOISE CITY PUBLIC WORKS
Site Address 150 N CAPITOL BLVD
Project NameCity Hall Bldg # 1
Customer Number 
ePlanReviewYes
Description
(CITY OF BOISE – 2nd & 4th Floor Lobby Soffit Remodel) Permit is to remodel City Hall Building #1 by adding new soffits to the second and fourth floors. Approval per approved plans on file. Work to include: installation of suspended gypsum soffit adjacent to the elevators on the floors mentioned, replace less than 50% of lobby lighting with new greater efficiency fixtures, and interior finishes in compliance with chapter 8 of the 2009 IBC. This building is fully fire sprinklered any alterations or modifications to the sprinkler system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA #13 as regulated by the fire department. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 9/7/201410/6/2014 DONE
interoffice mail to Scott Canning
First Notice7/14/20147/14/20148/28/2014 DONE
DetailsDave Hannah
interoffice mail to Scott Canning
BLD-Final7/14/20147/14/20147/14/2014PPASS
DetailsDave Hannah
Keith-Please call prior to inspection Phone #: ###-####
DOC - Permit Finaled7/14/20147/14/20147/14/2014PPASS
DetailsDave Hannah
BLD-Final7/11/20147/11/20147/14/2014PPART
DetailsDave Hannah
FIRE-Final Inspection7/11/20147/11/20147/11/2014PPASS
DetailsTroy Cobbley
life safety passed
BLD-Final7/10/20147/11/20147/11/2014ANR
DetailsDave Hannah
Kieth-call to meet Phone #: ###-####
FIRE-Final Inspection7/10/20147/11/20147/11/2014APASS
DetailsTroy Cobbley
Provide city approved plans and small documents.
BLD-Final10/25/201310/25/201310/28/2013PNR
DetailsDave Hannah
Phone #: ###-#### >> Inspection requested via web by Scott Canning needs a fire final first
BLD-Framing/Rough-in9/25/20139/25/20139/25/2013PPART
DetailsBob Archibald
Request framing inspection for soffit at 2nd floor elevators, bldg 1. Phone #: ###-#### >> Inspection requested via web by Scott Canning. 2nd floor ok for cover upon approval of electrical.
BLD-Framing/Rough-in9/19/20139/20/20139/20/2013APART
DetailsDave Hannah
scott Phone #: ###-#### 4th floor ok to cover
Fees Due Hold9/17/2013 9/18/2013 DONE
DetailsRita DeYoung
Plan assigned to (TLW)9/6/2013 9/16/2013 PASS
DetailsTim L. Woodard
Routing - PLAN CHECK9/6/2013 9/16/2013 PASS
DetailsTim L. Woodard
1st review completed  9/16/2013 DONE
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  9/16/2013 DONE
DetailsTim L. Woodard
Permit Ready to Issue  9/16/2013 DONE
Issue PAID IN FULL permit  9/16/2013 DONE
Inspection Record Card- Bld  9/16/2013 DONE
Intake Approval  9/6/2013 PASS
DetailsAdele J Schaffeld-Griffin
Application received  9/4/2013 DONE
Application submitted via PDS Online on Sep 4 2013 11:52AM