Third Notice | | 5/10/2014 | 5/20/2014 | | DONE |
|
|
|
|
Second Notice | | 4/11/2014 | 5/5/2014 | | DONE |
|
|
|
|
First Notice | | 3/15/2014 | 4/1/2014 | | DONE |
Barbara Stitt
|
|
|
Faxed 4-1-14
|
Permanent Occupancy | | | 3/5/2014 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 2/25/2014 | 2/26/2014 | 2/26/2014 | P | PASS |
Dave Hannah
|
|
|
perry Phone #: ###-####
|
FIRE-Final Inspection | 2/21/2014 | 2/24/2014 | 2/24/2014 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory.
|
BLD-Other | 2/6/2014 | 2/7/2014 | 2/7/2014 | A | PASS |
Tony Young
|
|
|
acoustical ceiling // Perry Phone #: ###-####
|
BLD-Framing/Rough-in | 1/17/2014 | 1/17/2014 | 1/23/2014 | P | PASS |
Dave Hannah
|
|
|
perry late as possible PLEASE Phone #: ###-####
|
BLD-Footing | 1/2/2014 | 1/2/2014 | 1/3/2014 | P | PASS |
Dave Hannah
|
|
|
Rebar inspection please-Perry Phone #: ###-####
|
BLD-Concrete | 12/31/2013 | 12/31/2013 | 12/31/2013 | P | CANC |
Jim Sly
|
|
|
Rebar - Perry Phone #: ###-####
|
Permit Ready to Issue | | | 12/9/2013 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 12/9/2013 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/9/2013 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 9/26/2013 | 9/26/2013 | 11/1/2013 | | PASS |
Carl Westfall
|
|
|
CHIPOTLE - ePlanReview - Level 3 TI - (20 days - Oct 22)
|
Routing Off Site - C.D.H | 10/31/2013 | | 11/1/2013 | | PASS |
Byron Grover
|
|
|
|
Routing - Design Review | 10/31/2013 | | 11/1/2013 | | PASS |
Cody Riddle
|
|
|
Rails added to short exterior walls.
Approved. The rails are consistent with DR approval, and required for the patio by City Clerk and other agencies.
The awning over the public right-of-way is allowed through the master agreement with the Ada County Highway Distrct. CER
|
Routing - PLAN CHECK | 11/1/2013 | | 11/1/2013 | | PASS |
Carl Westfall
|
|
|
Drawings approved after issues were resolved.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/1/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/29/2013 | | 10/31/2013 | | FAIL |
Carl Westfall
|
|
|
Item 35 that applies to the occupancy of the public way was not resolved.
|
Plan resubmittals received | | | 10/29/2013 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 10/11/2013 | | DONE |
|
|
|
|
1st review completed | | | 10/11/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/26/2013 | | 10/11/2013 | | FAIL |
Carl Westfall
|
|
|
A few items need to be resolved.
|
Routing Off Site - C.D.H | 9/26/2013 | | 10/8/2013 | | FAIL |
Byron Grover
|
|
|
Review not completed. Fee and more information required.
|
Routing - FIRE | 9/26/2013 | 9/26/2013 | 10/1/2013 | | PASS |
Craig D. Hanson
|
|
|
|
Routing - Design Review | 9/26/2013 | | 9/27/2013 | | PASS |
Sarah Schafer
|
|
|
Sarah Schafer Approved per DRH12-00319.
|
Plan Reviewer's activity | | | 9/26/2013 | | DONE |
Jason Blais
|
|
|
Emailed contact to have him contact ACHD for evaluation of any additional impact fees are due. Written verification from ACHD needs to be provided to our Permit Counter prior to the building permit being issued.
|
Routing PW Sewer Rating | 9/26/2013 | | 9/26/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Solid Waste | 9/26/2013 | | 9/26/2013 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Environmental | 9/26/2013 | | 9/26/2013 | | PASS |
Walt Baumgartner
|
|
|
GI installed w/ Shell & core. Kitchen plans show all necessary drainage route to GI, OK
|
Pending Assignment by JCB | 9/26/2013 | | 9/26/2013 | | DONE |
Jason Blais
|
|
|
|
Routing - Erosion and Sediment | 9/26/2013 | | 9/26/2013 | | PASS |
Evan Jenkins
|
|
|
|
Routing - PLUMBING | 9/26/2013 | | 9/26/2013 | | PASS |
Bill VanDegrift
|
|
|
1. Provide RPBP on filtered water.
2. Provide a RPBP on carbonater for soda.
3. May require an RPBP on rethermalizer equipment.
4. May requir additional backflow protection on equipment.
5. Provide tempered water to public lavs and hand wash sinks.
|
Routing - Addressing | 9/26/2013 | | 9/26/2013 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 9/26/2013 | | 9/26/2013 | | PASS |
Beverly Mountain
|
|
|
|
Payment Received | | | 9/25/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Intake Approval | | | 9/25/2013 | | PASS |
Jason Blais
|
|
|
Prescreen passed on 9/23/13. Plan Review Fees paid on 9/25/13.
|
Intake Approval | | | 9/19/2013 | | FAIL |
Tim L. Woodard
|
|
|
Please provide an ESC Waiver, ESC Application, and an exterior lighting compliance. Also please reupload sheet HD2 in the horizontal position.
Please email me with any questions,
twoodard@cityofboise.org
|
Application received | | | 9/6/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 6 2013 4:34PM
|