BLD-Final | 1/23/2014 | 1/23/2014 | 1/23/2014 | P | PASS |
Jim Storey
|
|
|
BRETT Phone #: ###-####
|
DOC - Permit Finaled | 1/23/2014 | 1/23/2014 | 1/23/2014 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 1/21/2014 | 1/23/2014 | 1/23/2014 | A | NR |
Jim Storey
|
|
|
bret Phone #: ###-#### 1000 apointment handrail/saftey glass
|
BLD-Final | 1/21/2014 | 1/21/2014 | 1/21/2014 | P | PART |
Jim Storey
|
|
|
bret Phone #: ###-#### pending hvac and back deck.
|
BLD-Framing/Rough-in | 12/10/2013 | 12/11/2013 | 12/11/2013 | A | PASS |
Jim Storey
|
|
|
BRETT Phone #: ###-####
|
BLD-Energy code compliance | 12/10/2013 | 12/11/2013 | 12/11/2013 | A | PASS |
Jim Storey
|
|
|
BRETT Phone #: ###-####
|
BLD-Framing/Rough-in | 12/6/2013 | 12/9/2013 | 12/9/2013 | P | PASS |
Jim Storey
|
|
|
Brett Phone #: ###-#### ok pending hvac for insulation.
|
BLD-Wall Bracing | 11/19/2013 | 11/20/2013 | 11/20/2013 | P | PASS |
Jim Storey
|
|
|
Brett Phone #: ###-####
|
BLD-Foundation | 10/4/2013 | 10/7/2013 | 10/7/2013 | A | PASS |
Jim Storey
|
|
|
dane Phone #: ###-####
|
BLD-Footing | 9/30/2013 | 9/30/2013 | 9/30/2013 | P | PASS |
Jim Storey
|
|
|
Dane Phone #: ###-####
|
PubWorks Subgrade Approval | 9/30/2013 | 9/30/2013 | 9/30/2013 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
OVERRIDE | | | 9/25/2013 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 9/25/2013 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 9/25/2013 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Bld | | | 9/20/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (JG) | 9/10/2013 | 9/10/2013 | 9/19/2013 | | PASS |
Javier Guzman
|
|
|
Due 9/20
|
1st review completed | | | 9/19/2013 | | FAIL |
Javier Guzman
|
|
|
Public Works not signed off
|
Routing - PLAN CHECK | 9/19/2013 | | 9/19/2013 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 9/19/2013 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/19/2013 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/13/2013 | | 9/19/2013 | | PASS |
Javier Guzman
|
|
|
|
Routing - PUBLIC WORKS | | | 9/19/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - MECHANICAL | 9/10/2013 | | 9/13/2013 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 9/9/2013 | 9/12/2013 | 9/10/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Route to Impact Fee Review | 9/9/2013 | 9/12/2013 | 9/10/2013 | | PASS |
Cindy M. Gould
|
|
|
|
Plan assigned to (AJS) | 9/9/2013 | 9/9/2013 | 9/10/2013 | | DEFR |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLANNING | | | 9/10/2013 | | PASS |
|
|
|
|
Routing - Addressing | 9/9/2013 | | 9/9/2013 | | PASS |
Jason C. Taylor
|
|
|
|
Intake Approval | | | 9/9/2013 | | PASS |
|
|
|
|
Routing PW Grading-Hillside | 9/9/2013 | | 9/9/2013 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
Application received | | 9/9/2013 | | | |
|
|
|
|