Third Notice | | 11/8/2014 | 11/20/2014 | | DONE |
|
|
|
This permit finaled on the web by Maureen Yogerst
|
Second Notice | | 10/16/2014 | 11/3/2014 | | DONE |
|
|
|
|
First Notice | 9/30/2014 | 9/30/2014 | 10/6/2014 | | DONE |
Phil Shearer
|
|
|
|
BLD-Final | 9/29/2014 | 9/30/2014 | 9/30/2014 | A | PASS |
Phil Shearer
|
|
|
Nick Phone #: ###-####
|
DOC - Permit Finaled | 9/30/2014 | 9/30/2014 | 9/30/2014 | P | PASS |
Phil Shearer
|
|
|
|
FIRE-Final Inspection | 9/26/2014 | 9/26/2014 | 9/26/2014 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 9/23/2014 | 9/23/2014 | 9/23/2014 | P | FAIL |
Troy Cobbley
|
|
|
Waiting of signage or curb painting(fire dept access) before a final sign off.
|
BLD-Other | 9/23/2014 | 9/23/2014 | 9/23/2014 | A | DONE |
Lori Flook
|
|
|
Brian Murphy signed occupany card.
|
FIRE-Final Inspection | 9/19/2014 | 9/19/2014 | 9/19/2014 | P | FAIL |
Troy Cobbley
|
|
|
There were no city approved plans or fire review documents for the inspection so I spoke to Nick about a possible requirement for fire dept access signage. No actual inspection was performed.
|
PubWorks Occupancy Approval | 9/25/2014 | 9/25/2014 | 9/19/2014 | | DONE |
Lori Flook
|
|
|
Brian Murphy inspected
|
BLD-Other | 8/5/2014 | 8/6/2014 | 8/6/2014 | A | CANC |
Phil Shearer
|
|
|
George-seepage bed Phone #: ###-####
public owrks need to do the inspection
|
OVERRIDE | | | 7/8/2014 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 7/8/2014 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 7/8/2014 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 7/8/2014 | | DONE |
Christina Prado
|
|
|
|
Extend Review Timeline | | | 3/27/2014 | | DONE |
Christina Prado
|
|
|
180 day extension granted from 3/8/14
|
Plan assigned to (LEG) Tisha | 2/27/2014 | | 3/18/2014 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 3/17/2014 | | 3/18/2014 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/18/2014 | | DONE |
Tisha Gallop
|
|
|
|
Routing - Design Review | 3/17/2014 | | 3/17/2014 | | PASS |
Andrea Tuning
|
|
|
|
Plan resubmittals received | | | 3/17/2014 | | |
|
|
|
resub received
|
Routing - PLAN CHECK | 2/27/2014 | | 3/17/2014 | | PASS |
Tisha Gallop
|
|
|
Tisha
|
Routing - Erosion and Sediment | 2/27/2014 | | 3/12/2014 | | PASS |
Evan Jenkins
|
|
|
Recieved this plan on 3-11-14 and approved
|
Routing PW Drainage | 2/27/2014 | | 3/7/2014 | | PASS |
Brian Murphy
|
|
|
|
Routing - FIRE | 2/27/2014 | 2/27/2014 | 3/5/2014 | | PASS |
Craig D. Hanson
|
|
|
See Fire Plan Review 03-05-14
|
Routing - PLANNING Land Div | 2/27/2014 | | 2/28/2014 | | PASS |
Todd Tucker
|
|
|
|
Routing - Addressing | 2/27/2014 | | 2/27/2014 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 2/27/2014 | | 2/27/2014 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Design Review | 2/27/2014 | | 2/27/2014 | | FAIL |
Andrea Tuning
|
|
|
DRH13-00293 // All pole lighting is requried to be located outside of the required planters. Sheet E.01 should be modified to located the pole lighting outside of the interior planter island to comoply wtih the Design Review approval (DRH13-00293).
|
Routing PW Street Lights | 2/27/2014 | | 2/27/2014 | | PASS |
Mike D Hedge
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/27/2014 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 2/27/2014 | | PASS |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/27/2014 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | | 9/9/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 9 2013 4:48PM
|