Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD13-02515
StatusFinaled
Name ESI
Site Address 650 N ARMSTRONG PL
Project NameWinCo Foods H.R. Tenant Improv
Customer Number 
ePlanReviewYes
Description
(WINCO FOODS HR TI) 2-25-14 plan modification to include 2 additional work spaces inside an existing open office as per approved plans. Permit to reconfigure existing cubicle layout into new layout for added workstations/offices. Remodel of 4,244 sq ft in an existing 73,030 square foot office building. Approval contingent upon adhering to the approved plans on file. Minor demolition per approved plans. Scope of work to include interior nonbearing noncombustible full height and partial height walls. New mechanical and electrical per approved plans. Interior finish shall be per Chapter 8 IBC. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **AJS***
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 4/11/20144/4/2014 DONE
This permit finaled on the web by Justin Parrish
First Notice3/3/20143/3/20144/1/2014 DONE
DetailsMike Jordan
mailed 4-2-14
BLD-Final2/28/20143/3/20143/3/2014APASS
DetailsMike Jordan
Bob Phone #: ###-####
DOC - Permit Finaled3/3/20143/3/20143/3/2014PPASS
DetailsMike Jordan
FIRE-Final Inspection2/26/20142/28/20142/28/2014APASS
DetailsTroy Cobbley
Life safety passed.
Permit Ready to Issue  2/26/2014 DONE
DetailsChristina Prado
CHANGE STATUS TO (ISS)  2/26/2014 DONE
DetailsChristina Prado
(F) Reprint permit  2/26/2014 DONE
DetailsChristina Prado
Plan assigned to (AJS) 2/18/20142/25/2014 PASS
DetailsAdele J Schaffeld-Griffin
2/19/14 no plans submitted /ePlan review plan modification
Routing - PLAN CHECK2/21/2014 2/25/2014 PASS
DetailsAdele J Schaffeld-Griffin
need informaiton on what plan mod is for.email sent
PLANS/APPL TAKEN TO FRONT DESK  2/25/2014 DONE
Plan Reviewer's activity  2/21/2014 DONE
DetailsAdele J Schaffeld-Griffin
sent email to Joe 2/21/14

Joe, there were some plan sheets uploaded for a plan modification for the WINCO Foods DR TI. There was not a plan modification application uploaded in the documents. Could you please complete that and send it back?

Thank you

Adele Schaffeld-Griffin
Plans Examiner II
City of Boise PDS
###-####

BLD-Framing/Rough-in2/18/20142/18/20142/18/2014PPART
DetailsMike Jordan
Bob Phone #: ###-####. Interior steel stud partial height walls for office cubicles (2) This is the additional work that needs to be submitted to plan review for approval.
Plan Modification Accepted  2/18/2014 DONE
DetailsChristina Prado
Chad called in to request plan mod to reflect changes in floor plan, specifically the amount of cubicles shown
BLD-Final1/27/20141/28/20141/28/2014PNR
DetailsMike Jordan
bob Phone #: ###-####. Still needs mech. final. All life sfaety ok, final ok. Contracted noted added electrical work not yet completed. Will call back for final when done.
FIRE-Final Inspection1/27/20141/28/20141/28/2014APASS
DetailsTroy Cobbley
life safety passed
BLD-Framing/Rough-in1/13/20141/14/20141/14/2014APASS
DetailsMike Jordan
Bob Phone #: ###-####. Interior steel studs for partial and full height walls ok.
FIRE-Conference1/10/20141/13/20141/13/2014ADONE
DetailsTroy Cobbley
Bob and I discussed the new office partitions obstruction of the ceiling mounted audio/visual devices.
Inspection Record Card- Bld  1/8/2014 DONE
CHANGE STATUS TO (ISS)  11/22/2013 DONE
DetailsDarla L Downs
Inspection Record Card- Bld  11/22/2013 DONE
Issue PAID IN FULL permit  11/22/2013 DONE
Plan assigned to (AJS)9/18/20139/18/201310/2/2013 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed due 10/1 level 2 e plan
Routing - PLAN CHECK10/2/2013 10/2/2013 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  10/2/2013 DONE
Permit Ready to Issue  10/2/2013 DONE
DetailsDarla L Downs
Routing - PLAN CHECK9/18/2013 9/30/2013 FAIL
DetailsAdele J Schaffeld-Griffin
see change marks in e plan
1st review completed  9/30/2013 FAIL
DetailsAdele J Schaffeld-Griffin
Payment Received  9/18/2013 DONE
Payment received via Govolutions
Intake Approval  9/18/2013 PASS
DetailsAdele J Schaffeld-Griffin
Intake Approval  9/12/2013 FAIL
DetailsAdele J Schaffeld-Griffin
Please re upload the specification book as one document. Sorry for the confusion. Documents are uploaded differently then drawings. Drawings are uploaded per sheet and documents are uploaded per document.

Please complete and upload the 518 checklist.

Please upload the 304 Design Professional of Record form.
Application received  9/11/2013 DONE
Application submitted via PDS Online on Sep 11 2013 3:46PM