Second Notice | | 4/11/2014 | 4/4/2014 | | DONE |
|
|
|
This permit finaled on the web by Justin Parrish
|
First Notice | 3/3/2014 | 3/3/2014 | 4/1/2014 | | DONE |
Mike Jordan
|
|
|
mailed 4-2-14
|
BLD-Final | 2/28/2014 | 3/3/2014 | 3/3/2014 | A | PASS |
Mike Jordan
|
|
|
Bob Phone #: ###-####
|
DOC - Permit Finaled | 3/3/2014 | 3/3/2014 | 3/3/2014 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 2/26/2014 | 2/28/2014 | 2/28/2014 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
Permit Ready to Issue | | | 2/26/2014 | | DONE |
Christina Prado
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/26/2014 | | DONE |
Christina Prado
|
|
|
|
(F) Reprint permit | | | 2/26/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (AJS) | | 2/18/2014 | 2/25/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
2/19/14 no plans submitted /ePlan review plan modification
|
Routing - PLAN CHECK | 2/21/2014 | | 2/25/2014 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
need informaiton on what plan mod is for.email sent
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/25/2014 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 2/21/2014 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
sent email to Joe 2/21/14
Joe, there were some plan sheets uploaded for a plan modification for the WINCO Foods DR TI. There was not a plan modification application uploaded in the documents. Could you please complete that and send it back?
Thank you
Adele Schaffeld-Griffin
Plans Examiner II
City of Boise PDS
###-####
|
BLD-Framing/Rough-in | 2/18/2014 | 2/18/2014 | 2/18/2014 | P | PART |
Mike Jordan
|
|
|
Bob Phone #: ###-####. Interior steel stud partial height walls for office cubicles (2) This is the additional work that needs to be submitted to plan review for approval.
|
Plan Modification Accepted | | | 2/18/2014 | | DONE |
Christina Prado
|
|
|
Chad called in to request plan mod to reflect changes in floor plan, specifically the amount of cubicles shown
|
BLD-Final | 1/27/2014 | 1/28/2014 | 1/28/2014 | P | NR |
Mike Jordan
|
|
|
bob Phone #: ###-####. Still needs mech. final. All life sfaety ok, final ok. Contracted noted added electrical work not yet completed. Will call back for final when done.
|
FIRE-Final Inspection | 1/27/2014 | 1/28/2014 | 1/28/2014 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Framing/Rough-in | 1/13/2014 | 1/14/2014 | 1/14/2014 | A | PASS |
Mike Jordan
|
|
|
Bob Phone #: ###-####. Interior steel studs for partial and full height walls ok.
|
FIRE-Conference | 1/10/2014 | 1/13/2014 | 1/13/2014 | A | DONE |
Troy Cobbley
|
|
|
Bob and I discussed the new office partitions obstruction of the ceiling mounted audio/visual devices.
|
Inspection Record Card- Bld | | | 1/8/2014 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 11/22/2013 | | DONE |
Darla L Downs
|
|
|
|
Inspection Record Card- Bld | | | 11/22/2013 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/22/2013 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 9/18/2013 | 9/18/2013 | 10/2/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed due 10/1 level 2 e plan
|
Routing - PLAN CHECK | 10/2/2013 | | 10/2/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/2/2013 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/2/2013 | | DONE |
Darla L Downs
|
|
|
|
Routing - PLAN CHECK | 9/18/2013 | | 9/30/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
see change marks in e plan
|
1st review completed | | | 9/30/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Payment Received | | | 9/18/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Intake Approval | | | 9/18/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Intake Approval | | | 9/12/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please re upload the specification book as one document. Sorry for the confusion. Documents are uploaded differently then drawings. Drawings are uploaded per sheet and documents are uploaded per document.
Please complete and upload the 518 checklist.
Please upload the 304 Design Professional of Record form.
|
Application received | | | 9/11/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 11 2013 3:46PM
|