Second Notice | | 2/7/2014 | 2/10/2014 | | DONE |
|
|
|
This permit finaled on the web by Tony O'Neil
|
First Notice | 12/31/2013 | 12/31/2013 | 1/28/2014 | | DONE |
Dave Hannah
|
|
|
|
BLD-Final | 12/30/2013 | 12/30/2013 | 12/31/2013 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Scott Stimpson
|
DOC - Permit Finaled | 12/31/2013 | 12/31/2013 | 12/31/2013 | A | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 11/26/2013 | 11/26/2013 | 11/26/2013 | A | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
FIRE-Final Inspection | 11/21/2013 | 11/21/2013 | 11/21/2013 | P | PASS |
Forrest France
|
|
|
Scope of work passed fire life safety.
|
BLD-Final | 11/17/2013 | 11/18/2013 | 11/19/2013 | A | NR |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Scott Stimpson needs other trades to final first
|
FIRE-Final Inspection | 11/17/2013 | 11/18/2013 | 11/18/2013 | A | PART |
Forrest France
|
|
|
Fire life safety final pending project related hood suppression work.
|
Issue PAID IN FULL permit | | | 10/15/2013 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 10/15/2013 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (CDM) | 10/7/2013 | 10/7/2013 | 10/14/2013 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 10/7/2013 | | 10/14/2013 | | PASS |
Carl D Madsen
|
|
|
|
Routing Off Site - C.D.H | 10/7/2013 | | 10/14/2013 | | PASS |
Carl D Madsen
|
|
|
|
Routing PW Environmental | 10/9/2013 | | 10/14/2013 | | PASS |
Walt Baumgartner
|
|
|
Existing grease interceptor on site, ok
|
1st review completed | | | 10/14/2013 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/14/2013 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/14/2013 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 10/14/2013 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 10/14/2013 | | DONE |
Barbara Stitt
|
|
|
Emailed Tony Oneil that permit is ready & fees due on 10-14-13 @ 4:50pm///BAS
|
Routing - MECHANICAL | 10/10/2013 | | 10/10/2013 | | PASS |
Troy James
|
|
|
Approval pending make-up air design does not create a discomfort to the employee. See letter from mechanical engineer.
|
Routing - PUBLIC WORKS | 10/9/2013 | | 10/9/2013 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Sewer Rating | 10/9/2013 | | 10/9/2013 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - MECHANICAL | 10/7/2013 | | 10/8/2013 | | FAIL |
Troy James
|
|
|
eplan, make up air design and need roof plan
|
Payment Received | | | 10/7/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
Intake Approval | | | 10/7/2013 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Intake Approval | | | 9/16/2013 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
1 The design professional that signed the 304 for needs to stamp and sign the plans.
2 Please have the mechanical plans stamped by a mechanical engineer. Please include the make up air calculations and how the make up air will be addressed.
|
Application received | | | 9/13/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 13 2013 2:35PM
|