Information based on query as of Thursday, July 4, 2024.
Permit Information
Permit NumberBLD13-02548
StatusFinaled
Name FALASH & ROSS CONSTRUCTION
Site Address 250 E PARKCENTER BLVD
Project NameALBERTSON GEN OFFICE-EXERCISE
Customer Number 
ePlanReviewNo
Description
ALBERTSON GEN OFFICE-EXERCISE-FPP Demo office area to create exercise space.New office furniture lay on the 1st floor. New lights and gridlay out. Fire spk. and alrm permits required thru fire planreview to meet NFPA. Plan Modifction aproved to remove selected interior partition walls,doors and replace with new walls and doors as well as system furniture. fire spk relocate will require permit and review. ele lighting with engery code per plan.
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 5/5/20145/8/2014 DONE
DetailsChristina Prado
completed 5-8-14
Print Statement  5/8/2014 DONE
DetailsChristina Prado
First Notice4/10/20144/10/20144/25/2014 DONE
DetailsTom Arcoraci
Letter of compliance/Occupancy  4/14/2014 DONE
DetailsChristina Prado
FIRE-Final Inspection4/9/20144/10/20144/10/2014APART
DetailsForrest France
Fire life safety final pending project related fire alarm permit work. Also noted one exit sign to be repaired and one missing escutcheon at the new exercise room.
BLD-Final4/9/20144/10/20144/10/2014APASS
DetailsTom Arcoraci
Greg Phone #: ###-####
DOC - Permit Finaled4/10/20144/10/20144/10/2014PPASS
DetailsTom Arcoraci
BLD-Ceiling Grid Inspection4/7/20144/8/20144/8/2014APASS
DetailsDave Hannah
Greg Phone #: ###-#### ok to cover ceiling in gym area
BLD-Final3/17/20143/18/20143/18/2014ACANC
DetailsJim Storey
kim Phone #: ###-#### need hvac insp.
CHANGE STATUS TO (ISS)  2/3/2014 DONE
(F) Reprint permit  2/3/2014 DONE
Plan assigned to (301)1/8/20141/8/20141/9/2014 PASS
DetailsJim Storey
Plans ACCEPTED BY PLAN CHECK  1/9/2014 DONE
1st review completed  1/9/2014 DONE
PLANS/APPL TAKEN TO FRONT DESK  1/9/2014 DONE
Inspection Record Card- Bld  1/9/2014 DONE
Permit Ready to Issue  1/9/2014 DONE
DetailsTisha Gallop
Telephone call  1/9/2014 DONE
DetailsTisha Gallop
called Chris Anderson and told him plan mod is ready, fee due.
Plan Modification Accepted  1/8/2014 DONE
DetailsBarbara Stitt
Plan modification accepted to remove selected interior partion walls, doors and systems furniture to be replaced with new partion walls, doors and systems furniture on the 1st floor. No additional value.
FIRE-Conference1/6/20141/6/20141/6/2014PDONE
DetailsForrest France
Regarding related FIR trade work
BLD-Ceiling Grid Inspection11/19/201311/20/201311/20/2013APASS
DetailsJim Storey
Greg Phone #: ###-####
Plan assigned to (301)9/16/20139/16/201310/11/2013 PASS
DetailsJim Storey
Routing - PLAN CHECK9/16/2013 10/11/2013 PASS
DetailsJim Storey
Jim Storey
PLANS/APPL TAKEN TO FRONT DESK  10/11/2013 DONE
Inspection Record Card- Bld  10/11/2013 DONE
DetailsBarbara Stitt
Inspection Record Card- Bld  10/11/2013 DONE
DetailsBarbara Stitt
Telephone call  10/11/2013 DONE
DetailsChristina Prado
called Chris to advise permit is ready for pick up pending GC form and gave fees due
Permit Ready to Issue  10/11/2013 DONE
DetailsChristina Prado
Issue PAID IN FULL permit  10/11/2013 DONE
Routing - MECHANICAL9/20/2013 9/20/2013 PASS
DetailsTroy James
Plan Reviewer's activity  9/19/2013 DONE
1st review completed  9/19/2013 DONE
Print permit w/o conditions  9/19/2013 DONE
Application received 9/16/20139/16/2013 DONE
DetailsBarbara Stitt
Plans ACCEPTED BY PLAN TECH  9/16/2013 DONE
DetailsBarbara Stitt
Routing - PLAN CHECK1/8/2014    
DetailsJim Storey