Permit Information
Permit NumberBLD13-02561
StatusFinaled
Name SEAN CAFFERTY ENTERPRISES
Site Address 2305 W BOISE AVE
Project Name 
Customer Number 
ePlanReviewNo
Description
4/24/15 plan modification for fire access **ajs**Permit for the construction of a new 6825 sq. ft., three story (below grade 1700 sq. ft., main level 3180 sq. ft., upper level 1945 sq. ft.) single family dwelling with 5 bedrooms, 5.5 bathrooms, 780 sq ft patior and balcony, 160 sq foot trellis for outdoor kitchen, and a 1834 sq. ft. attached garage per the approved plans, plan review report, statement of special inspection, engineering, ESE on spray insulation, perscriptive energy, and any notations. R-1C zoning and setbacks per planning. AJS A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/4/20155/5/20155/5/2015APASS
DetailsJim Storey
Sean Phone #: ###-####
DOC - Permit Finaled5/5/20155/5/20155/5/2015PPASS
DetailsJim Storey
CHANGE STATUS TO (ISS)  5/4/2015 DONE
OVERRIDE  4/24/2015  
Routing - FIRE4/21/20154/21/20154/24/2015 PASS
DetailsScott Arellano
Attached revised comments to case.
Plan assigned to (AJS)4/21/20154/21/20154/24/2015 PASS
DetailsAdele J Schaffeld-Griffin
Site plan Plan Modification
Routing - PLAN CHECK4/21/2015 4/24/2015 PASS
DetailsAdele J Schaffeld-Griffin
updated site plan approved by fire for secondary access, not change to building review
Routing - PLAN CHECK4/24/2015 4/24/2015 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  4/24/2015 DONE
Permit Ready to Issue  4/24/2015 DONE
DO NOT REISSUE-PLAN MOD
Telephone call  4/24/2015 DONE
called Sean- left message plans are ready for pick up
Routing - PLANNING4/21/2015 4/22/2015 PASS
DetailsLeon Letson
revised site plan approved
Plan Modification Accepted  4/21/2015 DONE
received two copies of sheet S1.1 and packet of property information- got original plans out of file cabinet in Public Records- put on Adele's desk
Telephone call  4/17/2015 DONE
DetailsScott Arellano
Mr. Bauer,

we can support the proposed revised fire department vehicle access design. However, the building department must have the architectural site plan modified to reflect the new a fire department vehicle access under BLD13-02561. Additionally, because this secondary access requires the use of the adjacent property, a lot consolidation will be required; or a recorded cross access agreement signed by both property owners stipulating that this fire department vehicle access must be maintained as a condition of the approval of BLD13-02561. The application for the lot consolidation can be obtained from Planning and Development Services; contact the permit technicians at ###-#### for more information.
BLD-Framing/Rough-in11/13/201411/13/201411/13/2014PPASS
DetailsJim Sly
Shawn Phone #: ###-####
BLD-Energy code compliance11/13/201411/13/201411/13/2014PPASS
DetailsJim Sly
Shawn Phone #: ###-####
BLD-Framing/Rough-in10/30/201410/31/201410/31/2014APASS
DetailsJim Storey
Sean Phone #: ###-####
BLD-Framing/Rough-in10/29/201410/30/201410/30/2014ADEFR
DetailsJim Storey
Sean Phone #: ###-#### out of time
Plan Modification Accepted  9/3/2014 DONE
new manual j
Routing - MECHANICAL9/3/2014 9/3/2014 PASS
DetailsTroy James
resubmitted manual j
BLD-Wall Bracing7/23/20147/24/20147/24/2014APASS
DetailsJim Storey
Sean Phone #: ###-####
BLD-Foundation10/29/201310/30/201310/30/2013APASS
DetailsJim Storey
Sean-Late morning please Phone #: ###-####
BLD-Foundation10/23/201310/23/201310/23/2013PPASS
DetailsJim Storey
Sean Phone #: ###-####
BLD-Footing10/17/201310/18/201310/18/2013APASS
DetailsJim Storey
sean Phone #: ###-####
PubWorks Subgrade Approval10/17/201310/17/201310/17/2013 DONE
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
Plan assigned to (AJS) 9/18/201310/17/2013 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed Due 10/4 Hillside
Routing - PLAN CHECK10/17/2013 10/17/2013 PASS
DetailsAdele J Schaffeld-Griffin
Case Summary (BLD)  10/17/2013 DONE
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  10/17/2013 DONE
Inspection Record Card- Bld  10/17/2013 DONE
DetailsChristina Prado
Permit Ready to Issue  10/17/2013  
Telephone call  10/17/2013  
10-17-13 called Sean permit ready and fee given ///dld
Issue PAID IN FULL permit  10/17/2013 DONE
DetailsBarbara Stitt
Plan resubmittals received  10/16/2013 DONE
received two copies of plan sheets sh1.1, sh1.2, sh1.3, a1.1, a1.3, a1.4, a5.1, a5.2; taken to Adele
Routing - PLAN CHECK10/15/2013 10/15/2013 FAIL
DetailsAdele J Schaffeld-Griffin
plans reviewed/ okay but need revised structural sheets as there appears to be a formatting issue with the plans. architect will submitt new plans with engineers stamp.
Plan resubmittals received  10/10/2013  
10-10-13 received 2 statement of special inspections,2main level floor framing,2 icc-es evaluation report,2 evaluation report,2 transmittals & 3 copies of A1.1,A1.3,- 2 copies of sheets A2.1,A5.1,A1.4 & A5.2 & 6 copies of A2.2,A2.3,A4.4 SH1.1,SH1.2,SH1.3 sent to Adele
Routing - PLAN CHECK10/8/2013 10/9/2013 FAIL
DetailsAdele J Schaffeld-Griffin
emailed plan review comments 10/9/13 see letter in documents
1st review completed  10/9/2013 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - FIRE10/8/201310/8/201310/8/2013 PASS
DetailsScott Arellano
Attached comments to case.
Plan resubmittals received  10/4/2013 DONE
DetailsChristina Prado
received two sets of revised plan sheets marked SP; Plans taken to Adele for further review
Routing - MECHANICAL10/2/2013 10/2/2013 PASS
DetailsTroy James
Routing - FIRE9/25/20139/18/20139/27/2013 FAIL
DetailsScott Arellano
Emailed and faxed plan review report with correction items to applicant.
Routing - MECHANICAL  9/25/2013 FAIL
DetailsTroy James
emailed corrections to don heating supply
Routing - PLANNING9/20/2013 9/23/2013 PASS
DetailsLeon Letson
Routing - PUBLIC WORKS  9/20/2013 PASS
Routing - Erosion and Sediment  9/20/2013 PASS
See Redlines on plans and narrative. Applicant must schedule and PASS a ESC site Prep inspection PRIOR to any clearing or grubbing. Jason Taylor ###-####
Routing PW Grading-Hillside  9/19/2013 PASS
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Routing - Addressing9/18/2013 9/19/2013 PASS
DetailsJason C. Taylor
Route to Impact Fee Review9/18/20139/21/20139/18/2013 PASS
DetailsCindy M. Gould
Route to Impact Fee Review9/17/20139/20/20139/18/2013 PASS
Details
Plans ACCEPTED BY PLAN TECH  9/17/2013 DONE
DetailsChristina Prado
Intake Approval  9/17/2013 PASS
DetailsBarbara Stitt
Recd Pcfee & Taken To Pln CK  9/17/2013 DONE
DetailsChristina Prado
Application received 9/17/2013